Van Horn- Rigid Pavement Repair
6497-76-001 · let May 5, 2026 · Culberson, El Paso · Routine Maintenance Project
$1,917,794Low bid: O. TREVINO CONSTRUCTION, LLC+92.8% vs estimate $994,580
$62,705Left on the table3.3% gap to the second bid
2BiddersSpread 3% low to high
7Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | O. TREVINO CONSTRUCTION, LLC | $1,917,794 | 92.8% | $62,705 | 4+$1,121,438 | 1-$334,850 | |
| 2 | SYNERGY PROJECT CONTRACTORS, INC. | $1,980,499 | +3.3% | 99.1% | 2+$1,332,099 | 1-$512,450 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
O. TREVINO CONSTRUCTION, LLC vs SYNERGY PROJECT CONTRACTORS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 361-7044 FULL-DEPTH REPAIR CRCP (VAR DEPTH) | 444 CY | $3,635.00 | $4,161.00 | $1,211.78 | $233,544 |
| 500-7001 MOBILIZATION | 1 LS | $189,000.00 | $11,400.00 | $523,850.32 | -$177,600 |
| 505-7001 TMA (STATIONARY) | 150 DAY | $165.00 | $324.90 | $217.57 | $23,985 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 124 SF | $315.00 | $153.90 | $153.06 | -$19,976 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 124 SF | $181.00 | $267.90 | $85.28 | $10,776 |
| 720-7001 SPALLING REPAIR (HYDRAULIC CEMENT) | 62 CF | $425.00 | $313.50 | $206.00 | -$6,913 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 10 DAY | $225.00 | $114.00 | $87.82 | -$1,110 |
Positive: the low bidder was cheaper on that item. These 7 items account for $62,705 of the $62,705 gap.
O. TREVINO CONSTRUCTION, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 361-7044 FULL-DEPTH REPAIR CRCP (VAR DEPTH) | 444 CY | $3,635.00 | $1,211.78 | 3.00x | $1,075,911 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 124 SF | $315.00 | $153.06 | 2.06x | $20,081 |
| 720-7001 SPALLING REPAIR (HYDRAULIC CEMENT) | 62 CF | $425.00 | $206.00 | 2.06x | $13,578 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 124 SF | $181.00 | $85.28 | 2.12x | $11,869 |
| 500-7001 MOBILIZATION | 1 LS | $189,000.00 | $523,850.32 | 0.36x | -$334,850 |