Mowing Highway Right of Way - AAO
6495-56-001 · let May 5, 2026 · Brewster, El Paso · Routine Maintenance Project
$678,600Low bid: LUKEDA SANDBLASTING & SERVICES LLC-21.6% vs estimate $866,000
$143,600Left on the table21.2% gap to the second bid
3BiddersSpread 23% low to high
2Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | LUKEDA SANDBLASTING & SERVICES LLC | $678,600 | -21.6% | $143,600 | 0 | 1-$75,595 | |
| 2 | LIGHT & FOLIAGE SUPPLY, LLC | $822,200 | +21.2% | -5.1% | $13,800 | 0 | 1-$75,595 |
| 3 | DOUBLE A CONTRACTING, L.P. | $836,000 | +23.2% | -3.5% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
LUKEDA SANDBLASTING & SERVICES LLC vs LIGHT & FOLIAGE SUPPLY, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 730-7022 FULL - WIDTH MOWING | 20,000 AC | $33.87 | $41.05 | $38.53 | $143,600 |
| 505-7002 TMA (MOBILE OPERATION) | 1,200 HR | $1.00 | $1.00 | $64.00 | $0 |
Positive: the low bidder was cheaper on that item. These 2 items account for $143,600 of the $143,600 gap.
LUKEDA SANDBLASTING & SERVICES LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7002 TMA (MOBILE OPERATION) | 1,200 HR | $1.00 | $64.00 | 0.02x | -$75,595 |
LIGHT & FOLIAGE SUPPLY, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7002 TMA (MOBILE OPERATION) | 1,200 HR | $1.00 | $64.00 | 0.02x | -$75,595 |