US 82, Kemp to US 287
0156-04-127 · let May 7, 2026 · Wichita, Wichita Falls · Rehabilitation of Existing Road
$3,670,513Low bid: O. TREVINO CONSTRUCTION, LLC-8.2% vs estimate $3,996,579
$264,435Left on the table7.2% gap to the second bid
5BiddersSpread 23% low to high
31Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | O. TREVINO CONSTRUCTION, LLC | $3,670,513 | -8.2% | $264,435 | 1+$24,142 | 1-$298,850 | |
| 2 | OVERLAND CORPORATION | $3,934,949 | +7.2% | -1.5% | $243,652 | 1+$94,800 | 1-$26,359 |
| 3 | AUSTIN BRIDGE & ROAD SERVICES, LP | $4,178,600 | +13.8% | 4.6% | $208,859 | 2+$123,494 | 1-$26,855 |
| 4 | JAGOE-PUBLIC COMPANY | $4,387,459 | +19.5% | 9.8% | $121,566 | 4+$326,157 | 0 |
| 5 | A. L. HELMCAMP, INC. | $4,509,025 | +22.8% | 12.8% | 0 | 1-$28,087 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
O. TREVINO CONSTRUCTION, LLC vs OVERLAND CORPORATION, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $225,000.00 | $400,155.00 | $523,850.32 | $175,155 |
| 341-7058 D-GR HMA TY-D SAC-B PG76-22 | 5,953 TON | $158.00 | $130.10 | $120.18 | -$166,089 |
| 361-7059 FULL-DEPTH REPAIR CPCD (8") | 7,300 SY | $123.50 | $143.00 | $164.78 | $142,350 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $6,550.00 | $30,545.00 | $11,585.04 | $119,975 |
| 347-7007 TOM-F PG76-22 SAC-B | 4,449 TON | $170.00 | $190.50 | $202.98 | $91,205 |
| 688-7005 VEH LP DETECT (SAWCUT)(14 AWG)(BLK) | 1,300 LF | $57.50 | $25.00 | $33.61 | -$42,250 |
| 361-7049 FULL - DEPTH REPAIR CRCP (8") | 1,400 SY | $143.00 | $163.00 | $189.93 | $28,000 |
| 354-7033 PLANE ASPH CONC PAV(0" TO 3") | 56,903 SY | $4.32 | $3.90 | $3.11 | -$23,899 |
| 505-7001 TMA (STATIONARY) | 124 DAY | $175.00 | $5.00 | $217.57 | -$21,080 |
| 531-7002 CONC SIDEWALKS (5") | 354 SY | $137.00 | $90.00 | $68.80 | -$16,638 |
| 3007-7001 BONDING COURSE | 9,965 GAL | $5.80 | $4.25 | $3.32 | -$15,446 |
| 505-7003 TMA (MOBILE OPERATION) | 8 DAY | $825.00 | $5.00 | $229.60 | -$6,560 |
| 529-7002 CONC CURB (TY II) | 306 LF | $29.00 | $50.00 | $26.45 | $6,426 |
| 479-7001 ADJUSTING MANHOLES | 7 EA | $1,075.00 | $1,750.00 | $1,510.21 | $4,725 |
| 432-7001 RIPRAP (CONC)(4 IN) | 29 CY | $870.00 | $750.00 | $573.24 | -$3,480 |
| 104-7017 REMOV CONC (CURB & GUTTER) | 97 LF | $33.00 | $7.00 | $8.04 | -$2,522 |
| 668-7089 PREFAB PM TY C (W)(24")(SLD) | 938 LF | $13.65 | $11.59 | $13.72 | -$1,932 |
| 104-7013 REMOV CONC (SIDEWALK, RAMP OR SUP) | 77 SY | $29.00 | $10.00 | $17.88 | -$1,463 |
| 752-7002 SPOT TREE TRIMMING / BRUSH REMOVAL | 1,450 LF | $11.50 | $11.00 | $1.20 | -$725 |
| 666-7030 REFL PAV MRK TY I (W)12"(SLD)(100MIL) | 2,738 LF | $3.15 | $2.90 | $2.94 | -$685 |
Positive: the low bidder was cheaper on that item. These 20 items account for $265,067 of the $264,435 gap.
O. TREVINO CONSTRUCTION, LLC: unbalanced items
Placed 1OVERLAND CORPORATION: unbalanced items
Placed 2AUSTIN BRIDGE & ROAD SERVICES, LP: unbalanced items
Placed 3JAGOE-PUBLIC COMPANY: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 354-7033 PLANE ASPH CONC PAV(0" TO 3") | 56,903 SY | $5.50 | $3.11 | 1.77x | $136,175 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $35,000.00 | $11,585.04 | 3.02x | $117,075 |
| 505-7001 TMA (STATIONARY) | 124 DAY | $550.00 | $217.57 | 2.53x | $41,221 |
| 529-7002 CONC CURB (TY II) | 306 LF | $130.00 | $26.45 | 4.91x | $31,686 |
A. L. HELMCAMP, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 688-7005 VEH LP DETECT (SAWCUT)(14 AWG)(BLK) | 1,300 LF | $12.00 | $33.61 | 0.36x | -$28,087 |