KingsvilleInterschool&Resd.Multi.Connect
0916-02-025 · let May 7, 2026 · Kleberg, Corpus Christi · Bicycle Infrastructure Improvements
$1,171,489Low bid: 3LW CIVIL LLC-17.9% vs estimate $1,426,805
$13,831Left on the table1.2% gap to the second bid
8BiddersSpread 91% low to high
39Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | 3LW CIVIL LLC | $1,171,489 | -17.9% | $13,831 | 2+$16,018 | 3-$456,868 | |
| 2 | GARRET SHIELDS INFRASTRUCTURE | $1,185,319 | +1.2% | -16.9% | $86,110 | 2+$12,399 | 3-$482,744 |
| 3 | LUCANIA CONTRACTORS LLC | $1,271,429 | +8.5% | -10.9% | $29,923 | 4+$46,778 | 3-$519,992 |
| 4 | TI-ZACK CONCRETE, LLC | $1,301,352 | +11.1% | -8.8% | $90,987 | 2+$25,088 | 4-$519,799 |
| 5 | ICOS MANAGEMENT, LLC | $1,392,339 | +18.9% | -2.4% | $40,766 | 5+$96,048 | 2-$546,773 |
| 6 | STX CIVIL | $1,433,105 | +22.3% | 0.4% | $407,746 | ||
| 7 | ARTILLERY L.L.C. | $1,840,850 | +57.1% | 29.0% | $395,043 | ||
| 8 | O. TREVINO CONSTRUCTION, LLC | $2,235,893 | +90.9% | 56.7% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
3LW CIVIL LLC vs GARRET SHIELDS INFRASTRUCTURE, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 529-7009 CONC CURB & GUTTER (TY II) | 2,979 LF | $42.00 | $20.00 | $32.57 | -$65,538 |
| 505-7001 TMA (STATIONARY) | 180 DAY | $0.1000 | $300.00 | $217.57 | $53,982 |
| 531-7010 CURB RAMPS (TY 7) | 49 EA | $1,577.04 | $2,500.00 | $2,829.94 | $45,225 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $8,282.07 | $5,000.00 | $11,585.04 | -$26,257 |
| 531-7003 CONC SIDEWALKS (6") | 5,876 SY | $76.27 | $80.00 | $88.84 | $21,917 |
| 464-7005 RC PIPE (CL III)(24 IN) | 659 LF | $88.48 | $120.00 | $108.34 | $20,772 |
| 465-7016 INLET (COMPL)(PCO)(3FT)(BOTH) | 5 EA | $8,659.30 | $5,000.00 | $8,359.98 | -$18,297 |
| 500-7001 MOBILIZATION | 1 LS | $117,000.00 | $100,000.00 | $523,850.32 | -$17,000 |
| 402-7001 TRENCH EXCAVATION PROTECTION | 659 LF | $20.00 | $1.00 | $5.96 | -$12,521 |
| 644-7064 IN SM RD SN SUP&AM (INST SIGN ONLY) | 56 EA | $115.50 | $300.00 | $309.66 | $10,332 |
| 531-7007 CURB RAMPS (TY 3) | 11 EA | $1,720.31 | $2,500.00 | $3,389.47 | $8,577 |
| 644-7025 IN SM RD SN SUP&AM TYS80(1)SA(P) | 40 EA | $693.00 | $500.00 | $847.35 | -$7,720 |
| 644-7067 RELOCATE SM RD SN SUP&AM TY S80 | 16 EA | $693.00 | $300.00 | $688.32 | -$6,288 |
| 530-7006 DRIVEWAYS (CONC) | 514 SY | $110.34 | $100.00 | $109.20 | -$5,315 |
| 506-7042 BIODEG EROSN CONT LOGS (INSTL) (6") | 880 LF | $0.1000 | $5.00 | $3.11 | $4,312 |
| 666-7422 REFL PAV MRK TY I (Y)6"(SLD)(090MIL) | 12,695 LF | $0.2800 | $0.6000 | $0.5014 | $4,062 |
| 168-7001 VEGETATIVE WATERING | 27 TGL | $150.00 | $20.00 | $8.43 | -$3,510 |
| 666-7347 PAVEMENT SLER 6" | 20,439 LF | $0.3500 | $0.5000 | $0.1841 | $3,066 |
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 11 EA | $250.00 | $500.00 | $60.77 | $2,750 |
| 104-7011 REMOV CONC (DRIVEWAYS) | 264 SY | $30.00 | $20.00 | $19.70 | -$2,640 |
Positive: the low bidder was cheaper on that item. These 20 items account for $9,910 of the $13,831 gap.
3LW CIVIL LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 402-7001 TRENCH EXCAVATION PROTECTION | 659 LF | $20.00 | $5.96 | 3.36x | $9,253 |
| 162-7002 BLOCK SODDING | 1,645 SY | $8.50 | $4.39 | 1.94x | $6,765 |
| 500-7001 MOBILIZATION | 1 LS | $117,000.00 | $523,850.32 | 0.22x | -$406,850 |
| 505-7001 TMA (STATIONARY) | 180 DAY | $0.1000 | $217.57 | 0.00x | -$39,145 |
| 644-7064 IN SM RD SN SUP&AM (INST SIGN ONLY) | 56 EA | $115.50 | $309.66 | 0.37x | -$10,873 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 666-7347 PAVEMENT SLER 6" | 20,439 LF | $0.5000 | $0.1841 | 2.72x | $6,457 |
| 162-7002 BLOCK SODDING | 1,645 SY | $8.00 | $4.39 | 1.82x | $5,942 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $5,000.00 | $11,585.04 | 0.43x | -$52,680 |
| 644-7067 RELOCATE SM RD SN SUP&AM TY S80 | 16 EA | $300.00 | $688.32 | 0.44x | -$6,213 |
LUCANIA CONTRACTORS LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 162-7002 BLOCK SODDING | 1,645 SY | $13.75 | $4.39 | 3.13x | $15,401 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 56 DAY | $300.00 | $87.82 | 3.42x | $11,882 |
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 11 EA | $1,000.00 | $60.77 | 16.45x | $10,331 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 1,645 SY | $7.00 | $1.43 | 4.90x | $9,164 |
| 500-7001 MOBILIZATION | 1 LS | $93,000.00 | $523,850.32 | 0.18x | -$430,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $1,700.00 | $11,585.04 | 0.15x | -$79,080 |
| 644-7064 IN SM RD SN SUP&AM (INST SIGN ONLY) | 56 EA | $130.00 | $309.66 | 0.42x | -$10,061 |
TI-ZACK CONCRETE, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 160-7002 FURN & PLACE TOPSOIL (4") | 1,645 SY | $10.40 | $1.43 | 7.28x | $14,757 |
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 11 EA | $1,000.00 | $60.77 | 16.45x | $10,331 |
| 500-7001 MOBILIZATION | 1 LS | $122,976.00 | $523,850.32 | 0.23x | -$400,874 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $3,200.00 | $11,585.04 | 0.28x | -$67,080 |
| 505-7001 TMA (STATIONARY) | 180 DAY | $1.00 | $217.57 | 0.00x | -$38,983 |
| 644-7064 IN SM RD SN SUP&AM (INST SIGN ONLY) | 56 EA | $80.00 | $309.66 | 0.26x | -$12,861 |
ICOS MANAGEMENT, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 530-7006 DRIVEWAYS (CONC) | 514 SY | $210.00 | $109.20 | 1.92x | $51,812 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 1,645 SY | $12.60 | $1.43 | 8.82x | $18,376 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 56 DAY | $262.50 | $87.82 | 2.99x | $9,782 |
| 666-7347 PAVEMENT SLER 6" | 20,439 LF | $0.6300 | $0.1841 | 3.42x | $9,114 |
| 666-7422 REFL PAV MRK TY I (Y)6"(SLD)(090MIL) | 12,695 LF | $1.05 | $0.5014 | 2.09x | $6,964 |
| 500-7001 MOBILIZATION | 1 LS | $69,750.00 | $523,850.32 | 0.13x | -$454,100 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $1.00 | $11,585.04 | 0.00x | -$92,672 |