FY26 TYLER AO GUARDRAIL REPAIR
6500-52-001 · let May 12, 2026 · Smith, Tyler · Routine Maintenance Project - Sealed
$631,830Low bid: CATOCON, INC.+11.1% vs estimate $568,750
—Left on the tableOnly one bidder
1Bidders
39Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | CATOCON, INC. | $631,830 | 11.1% | 6+$37,817 | 2-$26,374 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 1 bidders.
CATOCON, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7014 REPR OR REPLC CABLE BARR TERM SEC(TL-4) | 6 EA | $3,000.00 | $1,019.22 | 2.94x | $11,885 |
| 770-7032 REPLACE HINGED TOP SGT POST (STEEL) | 5 EA | $2,000.00 | $167.32 | 11.95x | $9,163 |
| 770-7007 REPLACE STEEL POST W/O CONC FND | 100 EA | $100.00 | $46.70 | 2.14x | $5,330 |
| 770-7033 REALIGN HINGED TOP SGT POST ((STEEL) | 5 EA | $1,000.00 | $122.90 | 8.14x | $4,386 |
| 771-7010 CABLE SPLICE / TURNBUCKLE (TL-4) | 12 EA | $400.00 | $88.10 | 4.54x | $3,743 |
| 770-7017 REPLACE SINGLE GDRAIL TERMINAL POST | 25 EA | $200.00 | $67.59 | 2.96x | $3,310 |
| 500-7002 MOBILIZATION (CALLOUT) | 30 EA | $1.00 | $600.85 | 0.00x | -$17,995 |
| 505-7001 TMA (STATIONARY) | 50 DAY | $50.00 | $217.57 | 0.23x | -$8,379 |