Rigid Pavement Repair EAO
6498-81-001 · let May 5, 2026 · El Paso, El Paso · Routine Maintenance Project
$1,650,378Low bid: SYNERGY PROJECT CONTRACTORS, INC.+65.2% vs estimate $998,900
$347,697Left on the table21.1% gap to the second bid
3BiddersSpread 40% low to high
7Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SYNERGY PROJECT CONTRACTORS, INC. | $1,650,378 | 65.2% | $347,697 | 1+$1,021,831 | 1-$518,150 | |
| 2 | O. TREVINO CONSTRUCTION, LLC | $1,998,075 | +21.1% | 100.0% | $317,875 | 3+$1,178,907 | 1-$325,850 |
| 3 | HAWK CONSTRUCTION | $2,315,950 | +40.3% | 131.9% | 3+$1,663,013 | 1-$503,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
SYNERGY PROJECT CONTRACTORS, INC. vs O. TREVINO CONSTRUCTION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $5,700.00 | $198,000.00 | $523,850.32 | $192,300 |
| 361-7044 FULL-DEPTH REPAIR CRCP (VAR DEPTH) | 475 CY | $3,363.00 | $3,635.00 | $1,211.78 | $129,200 |
| 720-7001 SPALLING REPAIR (HYDRAULIC CEMENT) | 40 CF | $273.60 | $600.00 | $206.00 | $13,056 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 60 SF | $153.90 | $355.00 | $153.06 | $12,066 |
| 505-7001 TMA (STATIONARY) | 50 DAY | $267.90 | $280.00 | $217.57 | $605 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 50 SF | $205.20 | $215.00 | $85.28 | $490 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 20 DAY | $171.00 | $170.00 | $87.82 | -$20 |
Positive: the low bidder was cheaper on that item. These 7 items account for $347,697 of the $347,697 gap.
SYNERGY PROJECT CONTRACTORS, INC.: unbalanced items
Placed 1O. TREVINO CONSTRUCTION, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 361-7044 FULL-DEPTH REPAIR CRCP (VAR DEPTH) | 475 CY | $3,635.00 | $1,211.78 | 3.00x | $1,151,031 |
| 720-7001 SPALLING REPAIR (HYDRAULIC CEMENT) | 40 CF | $600.00 | $206.00 | 2.91x | $15,760 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 60 SF | $355.00 | $153.06 | 2.32x | $12,116 |
| 500-7001 MOBILIZATION | 1 LS | $198,000.00 | $523,850.32 | 0.38x | -$325,850 |
HAWK CONSTRUCTION: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 361-7044 FULL-DEPTH REPAIR CRCP (VAR DEPTH) | 475 CY | $4,500.00 | $1,211.78 | 3.71x | $1,561,906 |
| 505-7001 TMA (STATIONARY) | 50 DAY | $1,950.00 | $217.57 | 8.96x | $86,621 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 50 SF | $375.00 | $85.28 | 4.40x | $14,486 |
| 500-7001 MOBILIZATION | 1 LS | $20,000.00 | $523,850.32 | 0.04x | -$503,850 |