01 Cable Barrier Repair 0526
6497-28-001 · let May 13, 2026 · Navarro, Dallas · Routine Maintenance Project - Sealed
$70,945Low bid: FIREMAN EXCAVATING, INC.-9.6% vs estimate $78,500
$4,835Left on the table6.8% gap to the second bid
3BiddersSpread 52% low to high
7Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | FIREMAN EXCAVATING, INC. | $70,945 | -9.6% | $4,835 | 0 | 3-$29,665 | |
| 2 | BK FIELD OPERATIONS LLC | $75,780 | +6.8% | -3.5% | $31,930 | 0 | 2-$26,658 |
| 3 | MARCOM'S MOWING SERVICE, LLC | $107,710 | +51.8% | 37.2% | 1+$7,262 | 2-$26,658 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
FIREMAN EXCAVATING, INC. vs BK FIELD OPERATIONS LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 771-7030 CHECK AND RE-TENSION CABLE SYSTEM | 10 EA | $50.00 | $500.00 | $350.67 | $4,500 |
| 771-7026 REPLACE LINE OR TERMINAL POST (GIBRAL) | 305 EA | $225.00 | $230.00 | $176.83 | $1,525 |
| 771-7029 REPLACE CABLE RELEASE POST | 10 EA | $100.00 | $1.00 | $148.81 | -$990 |
| 771-7031 REPLACE CABLE | 500 LF | $0.5000 | $0.1000 | $3.23 | -$200 |
| 500-7002 MOBILIZATION (CALLOUT) | 30 EA | $1.00 | $1.00 | $600.85 | $0 |
| 505-7001 TMA (STATIONARY) | 40 DAY | $1.00 | $1.00 | $217.57 | $0 |
| 771-7033 SPLICE CABLE | 5 EA | $100.00 | $100.00 | $342.77 | $0 |
Positive: the low bidder was cheaper on that item. These 7 items account for $4,835 of the $4,835 gap.