FM 2259_SH 7 TO 2.55 MI S. OF SH 7
2116-01-024 · let May 6, 2026 · Nacogdoches, Lufkin · Safety Improvement Projects
$5,074,604Low bid: DREWERY CONSTRUCTION COMPANY, INCORPORATED-8.9% vs estimate $5,568,463
$258,467Left on the table5.1% gap to the second bid
9BiddersSpread 34% low to high
74Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | DREWERY CONSTRUCTION COMPANY, INCORPORATED | $5,074,604 | -8.9% | $258,467 | 1+$27,724 | 4-$940,030 | |
| 2 | PINTO CONSTRUCTION CO., INC. | $5,333,070 | +5.1% | -4.2% | $209,859 | 1+$90,888 | 3-$623,628 |
| 3 | A. L. HELMCAMP, INC. | $5,542,929 | +9.2% | -0.5% | $119,835 | 0 | 3-$542,111 |
| 4 | THK CONSTRUCTION LLC | $5,662,764 | +11.6% | 1.7% | $235,395 | 4+$186,081 | 2-$818,816 |
| 5 | EAST TEXAS BRIDGE, INC. | $5,898,159 | +16.2% | 5.9% | $2,217 | 2+$511,449 | 2-$512,344 |
| 6 | LONGVIEW BRIDGE AND ROAD, LTD. | $5,900,377 | +16.3% | 6.0% | $265,628 | ||
| 7 | L. S. EQUIPMENT CO., INC. | $6,166,004 | +21.5% | 10.7% | $388,349 | ||
| 8 | FOUTSCO PAVING COMPANY, LLC | $6,554,353 | +29.2% | 17.7% | $266,308 | ||
| 9 | DRAKE COMPANIES LLC | $6,820,662 | +34.4% | 22.5% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
DREWERY CONSTRUCTION COMPANY, INCORPORATED vs PINTO CONSTRUCTION CO., INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 247-7210 FL BS (RDWY DEL) (TY D GR 3) | 14,168 TON | $54.00 | $63.00 | $42.12 | $127,512 |
| 344-7019 SP MIXES SP-C PG70-22 | 4,660 TON | $153.75 | $169.96 | $142.22 | $75,539 |
| 344-7020 SP MIXES SP-C SAC-A PG70-22 | 4,660 TON | $153.75 | $169.96 | $137.95 | $75,539 |
| 530-7010 DRIVEWAYS (ACP) | 10,145 SY | $53.00 | $47.24 | $54.96 | -$58,435 |
| 500-7001 MOBILIZATION | 1 LS | $250,000.00 | $300,000.00 | $523,850.32 | $50,000 |
| 275-7009 CEMENT TRT (EXIST MATL & NEW BASE)(12") | 42,362 SY | $3.75 | $4.64 | $2.49 | $37,702 |
| 530-7018 TURNOUTS (ACP) | 1,232 SY | $90.00 | $62.36 | $82.59 | -$34,052 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $2,400.00 | $5,000.00 | $11,585.04 | $33,800 |
| 112-7001 SUBGR WIDEN (OC) | 134.64 STA | $250.00 | $500.00 | $458.34 | $33,660 |
| 530-7006 DRIVEWAYS (CONC) | 832 SY | $170.00 | $140.00 | $109.20 | -$24,960 |
| 275-7001 CEMENT | 763 TON | $220.00 | $192.02 | $224.93 | -$21,349 |
| 134-7002 BACKFILL (TY B) | 134.64 STA | $165.00 | $300.00 | $206.94 | $18,176 |
| 316-7032 ASPH (RC-250) | 46 TON | $1,000.00 | $1,382.51 | $1,089.28 | $17,595 |
| 341-7064 D-GR HMA TY-D PG 64-22 (EXEMPT) | 121 TON | $382.00 | $239.17 | $152.88 | -$17,282 |
| 505-7001 TMA (STATIONARY) | 140 DAY | $110.00 | $225.00 | $217.57 | $16,100 |
| 506-7002 ROCK FILTER DAMS (INSTALL) (TY 2) | 2,740 LF | $33.00 | $29.00 | $44.91 | -$10,960 |
| 150-7001 BLADING | 134.64 STA | $225.00 | $300.00 | $152.64 | $10,098 |
| 316-7088 ASPH (AC-15P OR CRS-2P) | 76 TON | $1,150.00 | $1,026.80 | $1,008.86 | -$9,363 |
| 316-7268 AGGR (TY E OR L, PE OR PL GR 4) | 315 CY | $180.00 | $209.66 | $172.39 | $9,343 |
| 662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) | 26,928 LF | $0.5500 | $0.2100 | $0.2770 | -$9,156 |
Positive: the low bidder was cheaper on that item. These 20 items account for $319,507 of the $258,467 gap.
DREWERY CONSTRUCTION COMPANY, INCORPORATED: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 341-7064 D-GR HMA TY-D PG 64-22 (EXEMPT) | 121 TON | $382.00 | $152.88 | 2.50x | $27,724 |
| 100-7002 PREPARING ROW | 134.64 STA | $2,250.00 | $6,072.92 | 0.37x | -$514,718 |
| 500-7001 MOBILIZATION | 1 LS | $250,000.00 | $523,850.32 | 0.48x | -$273,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $2,400.00 | $11,585.04 | 0.21x | -$119,406 |
| 168-7001 VEGETATIVE WATERING | 3,805.5 TGL | $0.0100 | $8.43 | 0.00x | -$32,056 |
PINTO CONSTRUCTION CO., INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 275-7009 CEMENT TRT (EXIST MATL & NEW BASE)(12") | 42,362 SY | $4.64 | $2.49 | 1.86x | $90,888 |
| 100-7002 PREPARING ROW | 134.64 STA | $2,315.00 | $6,072.92 | 0.38x | -$505,967 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $5,000.00 | $11,585.04 | 0.43x | -$85,606 |
| 168-7001 VEGETATIVE WATERING | 3,805.5 TGL | $0.0100 | $8.43 | 0.00x | -$32,056 |
A. L. HELMCAMP, INC.: unbalanced items
Placed 3THK CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7088 ASPH (AC-15P OR CRS-2P) | 76 TON | $1,765.50 | $1,008.86 | 1.75x | $57,505 |
| 316-7268 AGGR (TY E OR L, PE OR PL GR 4) | 315 CY | $337.05 | $172.39 | 1.96x | $51,868 |
| 316-7032 ASPH (RC-250) | 46 TON | $1,926.00 | $1,089.28 | 1.77x | $38,489 |
| 150-7001 BLADING | 134.64 STA | $436.50 | $152.64 | 2.86x | $38,219 |
| 100-7002 PREPARING ROW | 134.64 STA | $1,000.00 | $6,072.92 | 0.16x | -$683,018 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $1,139.07 | $11,585.04 | 0.10x | -$135,798 |
EAST TEXAS BRIDGE, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7210 FL BS (RDWY DEL) (TY D GR 3) | 14,168 TON | $76.00 | $42.12 | 1.80x | $479,957 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $25,000.00 | $9,253.78 | 2.70x | $31,492 |
| 100-7002 PREPARING ROW | 134.64 STA | $3,000.00 | $6,072.92 | 0.49x | -$413,738 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $4,000.00 | $11,585.04 | 0.35x | -$98,606 |