FY 2025 REFLECTIVE PAVEMENT MARKINGS

6484-78-001 · let May 12, 2026 · Galveston, Houston · Routine Maintenance Project - Sealed

$847,316Low bid: BATTERSON, LLP-14.2% vs estimate $987,638
$2,445Left on the table0.3% gap to the second bid
4BiddersSpread 11% low to high
16Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1BATTERSON, LLP $847,316-14.2% $2,445 1+$17,395 3-$77,886
2TRP INFRASTRUCTURE SERVICES, LLC $849,762+0.3%-14.0% $27,842 1+$17,395 3-$72,306
3STRIPE LINES, INC. $877,604+3.6%-11.1% $64,549 1+$11,395 2-$23,533
4INTERSTATE BARRICADES & MARKINGS, INC. $942,152+11.2%-4.6% 2+$68,772 1-$41,573

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.

Where the job was won

BATTERSON, LLP vs TRP INFRASTRUCTURE SERVICES, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
677-7002 ELIM EXT PM & MRKS (6")739,728 LF $0.2900$0.3600$0.2755 $51,781
672-7002 REFL PAV MRKR TY I-C20,000 EA $5.50$4.00$4.04 -$30,000
672-7004 REFL PAV MRKR TY II-A-A7,000 EA $5.50$4.00$3.97 -$10,500
666-7236 RE PM TY III (W)(6")(SLD)140,000 LF $0.6500$0.6000$0.6919 -$7,000
666-7248 RE PM TY III (Y)(6")(SLD)140,000 LF $0.6500$0.6000$0.7409 -$7,000
678-7033 PAV SURF PREP FOR MRK (RPM)27,000 EA $0.0100$0.2500$0.5416 $6,480
666-7262 RE PM TY III (BLK)(6")(SHADOW)9,728 LF $1.00$0.6900$0.7183 -$3,016
666-7420 REFL PAV MRK TY I (Y)6"(BRK)(100MIL)50,000 LF $0.5700$0.6300$0.4829 $3,000
666-7408 REFL PAV MRK TY I (W)6"(BRK)(100MIL)40,000 LF $0.5700$0.6300$0.5627 $2,400
666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL)140,000 LF $0.5700$0.5600$0.4757 -$1,400
666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL)140,000 LF $0.5700$0.5600$0.4986 -$1,400
505-7003 TMA (MOBILE OPERATION)100 DAY $10.00$1.00$229.60 -$900
500-7002 MOBILIZATION (CALLOUT)6 EA $3,500.00$3,500.00$600.85 $0
666-7237 RE PM TY III (W)(6")(BRK)40,000 LF $0.6500$0.6500$0.7099 $0
666-7249 RE PM TY III (Y)(6")(BRK)40,000 LF $0.6500$0.6500$0.9724 $0
678-7002 PAV SURF PREP FOR MRK (6")739,728 LF $0.0100$0.0100$0.0662 $0

Positive: the low bidder was cheaper on that item. These 16 items account for $2,445 of the $2,445 gap.

BATTERSON, LLP: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
500-7002 MOBILIZATION (CALLOUT)6 EA $3,500.00$600.855.83x$17,395
678-7002 PAV SURF PREP FOR MRK (6")739,728 LF $0.0100$0.06620.15x-$41,573
505-7003 TMA (MOBILE OPERATION)100 DAY $10.00$229.600.04x-$21,960
678-7033 PAV SURF PREP FOR MRK (RPM)27,000 EA $0.0100$0.54160.02x-$14,353

TRP INFRASTRUCTURE SERVICES, LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
500-7002 MOBILIZATION (CALLOUT)6 EA $3,500.00$600.855.83x$17,395
678-7002 PAV SURF PREP FOR MRK (6")739,728 LF $0.0100$0.06620.15x-$41,573
505-7003 TMA (MOBILE OPERATION)100 DAY $1.00$229.600.00x-$22,860
678-7033 PAV SURF PREP FOR MRK (RPM)27,000 EA $0.2500$0.54160.46x-$7,873

STRIPE LINES, INC.: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
500-7002 MOBILIZATION (CALLOUT)6 EA $2,500.00$600.854.16x$11,395
505-7003 TMA (MOBILE OPERATION)100 DAY $100.00$229.600.44x-$12,960
678-7033 PAV SURF PREP FOR MRK (RPM)27,000 EA $0.1500$0.54160.28x-$10,573

INTERSTATE BARRICADES & MARKINGS, INC.: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
500-7002 MOBILIZATION (CALLOUT)6 EA $10,000.00$600.8516.64x$56,395
678-7033 PAV SURF PREP FOR MRK (RPM)27,000 EA $1.00$0.54161.85x$12,377
678-7002 PAV SURF PREP FOR MRK (6")739,728 LF $0.0100$0.06620.15x-$41,573