SH 242; East of IH 45
3538-01-061 · let May 7, 2026 · Montgomery, Houston · Landscape & Scenic Enhancement
$1,579,083Low bid: CENTRAL NORTH CONSTRUCTION, LLC-28.8% vs estimate $2,218,949
$105,069Left on the table6.7% gap to the second bid
7BiddersSpread 30% low to high
38Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | CENTRAL NORTH CONSTRUCTION, LLC | $1,579,083 | -28.8% | $105,069 | 1+$340,423 | 7-$659,144 | |
| 2 | APEX LANDSCAPE & IRRIGATION, LLC | $1,684,152 | +6.7% | -24.1% | $1,539 | 5+$271,826 | 11-$698,863 |
| 3 | TIGHT LINE CONSTRUCTION, LLC | $1,685,692 | +6.8% | -24.0% | $68,234 | 1+$62,634 | 4-$570,339 |
| 4 | YELLOWSTONE LANDSCAPE - CENTRAL, INC. | $1,753,926 | +11.1% | -21.0% | $8,634 | 6+$288,870 | 6-$662,168 |
| 5 | GREEN SAGE SERVICES LLC | $1,762,560 | +11.6% | -20.6% | $286,858 | 5+$230,982 | 3-$499,445 |
| 6 | ABESCAPE LANDSCAPING, LLC | $2,049,418 | +29.8% | -7.6% | $3,199 | ||
| 7 | TEXAS WALL & LANDSCAPE | $2,052,617 | +30.0% | -7.5% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
CENTRAL NORTH CONSTRUCTION, LLC vs APEX LANDSCAPE & IRRIGATION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 170-7002 IRRIGATION SYSTEM (TY I) | 1 EA | $491,326.50 | $310,000.00 | $150,903.93 | -$181,327 |
| 500-7001 MOBILIZATION | 1 LS | $75,000.00 | $165,000.00 | $523,850.32 | $90,000 |
| 193-7033 LANDSCAPE TREAT (TY VIII) | 1,131 EA | $29.00 | $85.00 | $22.32 | $63,336 |
| 192-7032 PLANT MATERIAL (45 GAL) | 283 EA | $320.00 | $540.00 | $337.34 | $62,260 |
| 192-7040 PLANT MATERIAL (45 GAL) (TREE) | 189 EA | $320.00 | $540.00 | $474.97 | $41,580 |
| 193-7002 LANDSCAPE ESTABLISH | 2 CYC | $25,000.00 | $10,000.00 | $21,267.99 | -$30,000 |
| 162-7002 BLOCK SODDING | 18,682 SY | $2.75 | $1.25 | $4.39 | -$28,023 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $4,500.00 | $9,000.00 | $11,585.04 | $27,000 |
| 192-7012 PLANT BED PREP (TY III) | 46,722 SY | $1.00 | $0.5000 | $1.98 | -$23,361 |
| 193-7040 LANDSCAPE TREAT (TY VII) | 148 CYC | $300.00 | $450.00 | $1,029.18 | $22,200 |
| 192-7021 LANDSCAPE EDGE (CONC) | 1,294 LF | $42.00 | $26.00 | $28.30 | -$20,704 |
| 192-7031 PLANT MATERIAL (30 GAL) | 226 EA | $200.00 | $290.00 | $347.98 | $20,340 |
| 192-7039 PLANT MATERIAL (30 GAL) (TREE) | 253 EA | $200.00 | $280.00 | $323.72 | $20,240 |
| 193-7032 LANDSCAPE TREAT (TY VII) | 283 EA | $35.00 | $105.00 | $30.98 | $19,810 |
| 192-7030 PLANT MATERIAL (15 GAL) | 905 EA | $110.00 | $130.00 | $166.41 | $18,100 |
| 192-7008 SOIL AMEND (TY I) | 46,772 SY | $0.7500 | $0.4000 | $0.8084 | -$16,370 |
| 192-7026 PLANT MATERIAL (1 GAL) | 4,133 EA | $5.00 | $8.00 | $6.82 | $12,399 |
| 193-7035 LANDSCAPE TREAT (TY X) | 1,414 EA | $2.00 | $10.00 | $1.92 | $11,312 |
| 193-7036 LANDSCAPE TREAT (TY III) | 2 CYC | $4,500.00 | $10,000.00 | $8,682.96 | $11,000 |
| 192-7084 SOIL AMEND (TY II) | 46,772 SY | $0.5000 | $0.3000 | $0.8229 | -$9,354 |
Positive: the low bidder was cheaper on that item. These 20 items account for $110,438 of the $105,069 gap.
CENTRAL NORTH CONSTRUCTION, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 170-7002 IRRIGATION SYSTEM (TY I) | 1 EA | $491,326.50 | $150,903.93 | 3.26x | $340,423 |
| 500-7001 MOBILIZATION | 1 LS | $75,000.00 | $523,850.32 | 0.14x | -$448,850 |
| 193-7040 LANDSCAPE TREAT (TY VII) | 148 CYC | $300.00 | $1,029.18 | 0.29x | -$107,919 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $4,500.00 | $11,585.04 | 0.39x | -$42,510 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $5.00 | $217.57 | 0.02x | -$21,257 |
| 193-7028 LANDSCAPE TREAT (TY III) | 6,175 EA | $0.9500 | $3.50 | 0.27x | -$15,775 |
| 505-7003 TMA (MOBILE OPERATION) | 65 DAY | $15.00 | $229.60 | 0.07x | -$13,949 |
| 193-7023 LANDSCAPE TREAT (TY I) | 2,042 EA | $0.9500 | $5.30 | 0.18x | -$8,883 |
APEX LANDSCAPE & IRRIGATION, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 170-7002 IRRIGATION SYSTEM (TY I) | 1 EA | $310,000.00 | $150,903.93 | 2.05x | $159,096 |
| 193-7033 LANDSCAPE TREAT (TY VIII) | 1,131 EA | $85.00 | $22.32 | 3.81x | $70,887 |
| 193-7032 LANDSCAPE TREAT (TY VII) | 283 EA | $105.00 | $30.98 | 3.39x | $20,948 |
| 193-7035 LANDSCAPE TREAT (TY X) | 1,414 EA | $10.00 | $1.92 | 5.20x | $11,420 |
| 193-7031 LANDSCAPE TREAT (TY VI) | 136 EA | $90.00 | $20.34 | 4.43x | $9,474 |
| 500-7001 MOBILIZATION | 1 LS | $165,000.00 | $523,850.32 | 0.31x | -$358,850 |
| 193-7040 LANDSCAPE TREAT (TY VII) | 148 CYC | $450.00 | $1,029.18 | 0.44x | -$85,719 |
| 192-7012 PLANT BED PREP (TY III) | 46,722 SY | $0.5000 | $1.98 | 0.25x | -$68,966 |
| 162-7002 BLOCK SODDING | 18,682 SY | $1.25 | $4.39 | 0.28x | -$58,619 |
| 192-7084 SOIL AMEND (TY II) | 46,772 SY | $0.3000 | $0.8229 | 0.36x | -$24,457 |
| 193-7002 LANDSCAPE ESTABLISH | 2 CYC | $10,000.00 | $21,267.99 | 0.47x | -$22,536 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $5.00 | $217.57 | 0.02x | -$21,257 |
| 192-7008 SOIL AMEND (TY I) | 46,772 SY | $0.4000 | $0.8084 | 0.49x | -$19,102 |
| 193-7028 LANDSCAPE TREAT (TY III) | 6,175 EA | $1.00 | $3.50 | 0.29x | -$15,467 |
| 505-7003 TMA (MOBILE OPERATION) | 65 DAY | $5.00 | $229.60 | 0.02x | -$14,599 |
TIGHT LINE CONSTRUCTION, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 193-7036 LANDSCAPE TREAT (TY III) | 2 CYC | $40,000.00 | $8,682.96 | 4.61x | $62,634 |
| 500-7001 MOBILIZATION | 1 LS | $150,000.00 | $523,850.32 | 0.29x | -$373,850 |
| 193-7040 LANDSCAPE TREAT (TY VII) | 148 CYC | $150.00 | $1,029.18 | 0.15x | -$130,119 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $3,000.00 | $11,585.04 | 0.26x | -$51,510 |
| 505-7003 TMA (MOBILE OPERATION) | 65 DAY | $1.00 | $229.60 | 0.00x | -$14,859 |
YELLOWSTONE LANDSCAPE - CENTRAL, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 100 DAY | $1,196.95 | $217.57 | 5.50x | $97,938 |
| 505-7003 TMA (MOBILE OPERATION) | 65 DAY | $1,193.06 | $229.60 | 5.20x | $62,625 |
| 193-7036 LANDSCAPE TREAT (TY III) | 2 CYC | $36,245.63 | $8,682.96 | 4.17x | $55,125 |
| 193-7002 LANDSCAPE ESTABLISH | 2 CYC | $42,146.08 | $21,267.99 | 1.98x | $41,756 |
| 193-7031 LANDSCAPE TREAT (TY VI) | 136 EA | $156.19 | $20.34 | 7.68x | $18,476 |
| 168-7001 VEGETATIVE WATERING | 463.4 TGL | $36.38 | $8.43 | 4.31x | $12,950 |
| 500-7001 MOBILIZATION | 1 LS | $158,841.88 | $523,850.32 | 0.30x | -$365,008 |
| 193-7040 LANDSCAPE TREAT (TY VII) | 148 CYC | $136.69 | $1,029.18 | 0.13x | -$132,089 |
| 192-7012 PLANT BED PREP (TY III) | 46,722 SY | $0.4510 | $1.98 | 0.23x | -$71,256 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $4,456.25 | $11,585.04 | 0.38x | -$42,773 |
| 192-7084 SOIL AMEND (TY II) | 46,772 SY | $0.1440 | $0.8229 | 0.17x | -$31,754 |
| 192-7008 SOIL AMEND (TY I) | 46,772 SY | $0.3960 | $0.8084 | 0.49x | -$19,289 |
GREEN SAGE SERVICES LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 192-7001 MULCH | 3,895 CY | $56.00 | $26.88 | 2.08x | $113,434 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $680.00 | $217.57 | 3.13x | $46,243 |
| 505-7003 TMA (MOBILE OPERATION) | 65 DAY | $690.00 | $229.60 | 3.01x | $29,926 |
| 193-7031 LANDSCAPE TREAT (TY VI) | 136 EA | $200.00 | $20.34 | 9.83x | $24,434 |
| 168-7001 VEGETATIVE WATERING | 463.4 TGL | $45.00 | $8.43 | 5.34x | $16,945 |
| 500-7001 MOBILIZATION | 1 LS | $80,000.00 | $523,850.32 | 0.15x | -$443,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $5,000.00 | $11,585.04 | 0.43x | -$39,510 |
| 193-7028 LANDSCAPE TREAT (TY III) | 6,175 EA | $0.9000 | $3.50 | 0.26x | -$16,084 |