FM2320 Drainage Improvement
6481-94-001 · let May 13, 2026 · Kent, Abilene · Routine Maintenance Project - Sealed
$572,628Low bid: ICOS MANAGEMENT, LLC-34.0% vs estimate $867,769
$39,223Left on the table6.8% gap to the second bid
7BiddersSpread 90% low to high
24Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ICOS MANAGEMENT, LLC | $572,628 | -34.0% | $39,223 | 8+$75,788 | 3-$488,333 | |
| 2 | SHALOM SERVICES CORPORATION | $611,851 | +6.8% | -29.5% | $78,983 | 5+$41,154 | 3-$500,883 |
| 3 | BLACKSMITH VENTURES LLC | $690,834 | +20.6% | -20.4% | $21,891 | 4+$22,388 | 4-$495,513 |
| 4 | BK FIELD OPERATIONS LLC | $712,725 | +24.5% | -17.9% | $244,687 | 3+$84,366 | 4-$535,978 |
| 5 | EARTH BUILDERS, L.P. | $957,412 | +67.2% | 10.3% | $36,104 | 2+$290,344 | 2-$446,605 |
| 6 | DIGG COMMERCIAL, LLC | $993,516 | +73.5% | 14.5% | $92,007 | ||
| 7 | GILVIN-TERRILL, LTD. | $1,085,523 | +89.6% | 25.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
ICOS MANAGEMENT, LLC vs SHALOM SERVICES CORPORATION, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 110-7002 EXCAV (CHANNEL) | 2,651 CY | $32.00 | $10.00 | $16.69 | -$58,322 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 1,016 CY | $150.00 | $195.00 | $184.74 | $45,720 |
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN) | 732 CY | $150.00 | $205.00 | $179.97 | $40,260 |
| 104-7046 REMOV CONC (MISC) | 1,506 SY | $22.00 | $35.00 | $23.49 | $19,578 |
| 164-7049 HYDRO MULCH SEED (PERM_RURAL_SAND) | 1.9 AC | $2,140.00 | $8,000.00 | $2,140.00 | $11,134 |
| 432-7002 RIPRAP (CONC)(5 IN) | 10 CY | $1,070.00 | $2,000.00 | $585.15 | $9,300 |
| 552-7011 WIRE FENCE (REMOVE) | 1,009 LF | $11.00 | $3.00 | $2.42 | -$8,072 |
| 500-7001 MOBILIZATION | 1 LS | $67,000.00 | $60,000.00 | $523,850.32 | -$7,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $5,350.00 | $3,500.00 | $11,585.04 | -$5,550 |
| 467-7327 SET (TY II) (24 IN) (RCP) (6: 1) (C) | 1 EA | $5,350.00 | $3,000.00 | $2,267.09 | -$2,350 |
| 552-7001 WIRE FENCE (TY A) | 1,121 LF | $22.00 | $20.00 | $22.53 | -$2,242 |
| 467-7326 SET (TY II) (24 IN) (RCP) (4: 1) (C) | 1 EA | $4,280.00 | $2,500.00 | $2,065.28 | -$1,780 |
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 50 EA | $107.00 | $75.00 | $60.77 | -$1,600 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 480 LF | $2.00 | $5.00 | $3.92 | $1,440 |
| 506-7046 BIODEG EROSN CONT LOGS (REMOVE) | 280 LF | $5.00 | $1.00 | $1.29 | -$1,120 |
| 506-7044 BIODEG EROSN CONT LOGS (INSTL) (12") | 280 LF | $10.00 | $7.00 | $5.23 | -$840 |
| 168-7001 VEGETATIVE WATERING | 145 TGL | $10.00 | $15.00 | $8.43 | $725 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 288 CY | $43.00 | $45.00 | $16.96 | $576 |
| 150-7002 BLADING | 10 HR | $535.00 | $500.00 | $171.50 | -$350 |
| 166-7001 FERTILIZER | 2.1 AC | $2,140.00 | $2,000.00 | $717.14 | -$294 |
Positive: the low bidder was cheaper on that item. These 20 items account for $39,213 of the $39,223 gap.
ICOS MANAGEMENT, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7002 EXCAV (CHANNEL) | 2,651 CY | $32.00 | $16.69 | 1.92x | $40,576 |
| 552-7011 WIRE FENCE (REMOVE) | 1,009 LF | $11.00 | $2.42 | 4.54x | $8,657 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 288 CY | $43.00 | $16.96 | 2.53x | $7,499 |
| 432-7002 RIPRAP (CONC)(5 IN) | 10 CY | $1,070.00 | $585.15 | 1.83x | $4,849 |
| 401-7001 FLOWABLE BACKFILL | 10 CY | $749.00 | $298.77 | 2.51x | $4,502 |
| 150-7002 BLADING | 10 HR | $535.00 | $171.50 | 3.12x | $3,635 |
| 467-7327 SET (TY II) (24 IN) (RCP) (6: 1) (C) | 1 EA | $5,350.00 | $2,267.09 | 2.36x | $3,083 |
| 166-7001 FERTILIZER | 2.1 AC | $2,140.00 | $717.14 | 2.98x | $2,988 |
| 500-7001 MOBILIZATION | 1 LS | $67,000.00 | $523,850.32 | 0.13x | -$456,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $5,350.00 | $11,585.04 | 0.46x | -$18,705 |
| 505-7001 TMA (STATIONARY) | 59 DAY | $1.00 | $217.57 | 0.00x | -$12,778 |
SHALOM SERVICES CORPORATION: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 432-7002 RIPRAP (CONC)(5 IN) | 10 CY | $2,000.00 | $585.15 | 3.42x | $14,149 |
| 164-7049 HYDRO MULCH SEED (PERM_RURAL_SAND) | 1.9 AC | $8,000.00 | $2,140.00 | 3.74x | $11,134 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 288 CY | $45.00 | $16.96 | 2.65x | $8,075 |
| 401-7001 FLOWABLE BACKFILL | 10 CY | $750.00 | $298.77 | 2.51x | $4,512 |
| 150-7002 BLADING | 10 HR | $500.00 | $171.50 | 2.92x | $3,285 |
| 500-7001 MOBILIZATION | 1 LS | $60,000.00 | $523,850.32 | 0.11x | -$463,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $3,500.00 | $11,585.04 | 0.30x | -$24,255 |
| 505-7001 TMA (STATIONARY) | 59 DAY | $1.00 | $217.57 | 0.00x | -$12,778 |
BLACKSMITH VENTURES LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 401-7001 FLOWABLE BACKFILL | 10 CY | $1,000.00 | $298.77 | 3.35x | $7,012 |
| 506-7044 BIODEG EROSN CONT LOGS (INSTL) (12") | 280 LF | $25.00 | $5.23 | 4.78x | $5,537 |
| 164-7049 HYDRO MULCH SEED (PERM_RURAL_SAND) | 1.9 AC | $5,000.00 | $2,140.00 | 2.34x | $5,434 |
| 162-7008 ROLL SODDING | 880 SY | $10.00 | $4.99 | 2.00x | $4,405 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $1.00 | $11,585.04 | 0.00x | -$34,752 |
| 552-7001 WIRE FENCE (TY A) | 1,121 LF | $1.00 | $22.53 | 0.04x | -$24,133 |
| 505-7001 TMA (STATIONARY) | 59 DAY | $1.00 | $217.57 | 0.00x | -$12,778 |
BK FIELD OPERATIONS LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7002 EXCAV (CHANNEL) | 2,651 CY | $40.00 | $16.69 | 2.40x | $61,784 |
| 164-7049 HYDRO MULCH SEED (PERM_RURAL_SAND) | 1.9 AC | $10,000.00 | $2,140.00 | 4.67x | $14,934 |
| 552-7011 WIRE FENCE (REMOVE) | 1,009 LF | $10.00 | $2.42 | 4.13x | $7,648 |
| 500-7001 MOBILIZATION | 1 LS | $40,000.00 | $523,850.32 | 0.08x | -$483,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $1.00 | $11,585.04 | 0.00x | -$34,752 |
| 505-7001 TMA (STATIONARY) | 59 DAY | $1.00 | $217.57 | 0.00x | -$12,778 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 288 CY | $1.00 | $16.96 | 0.06x | -$4,597 |
EARTH BUILDERS, L.P.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 104-7046 REMOV CONC (MISC) | 1,506 SY | $210.00 | $23.49 | 8.94x | $280,883 |
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 50 EA | $250.00 | $60.77 | 4.11x | $9,461 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $4,000.00 | $11,585.04 | 0.35x | -$22,755 |