Culvert Replacement 07 06.26
6497-79-001 · let Jun 10, 2026 · Collin, Dallas · Routine Maintenance Project - Sealed
$109,861Low bid: SHALOM SERVICES CORPORATION-9.7% vs estimate $121,696
$4,303Left on the table3.9% gap to the second bid
5BiddersSpread 135% low to high
14Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SHALOM SERVICES CORPORATION | $109,861 | -9.7% | $4,303 | 1+$4,208 | 3-$540,584 | |
| 2 | GHB EQUIPMENT COMPANY, L.L.C. | $114,164 | +3.9% | -6.2% | $16,930 | 1+$4,208 | 3-$531,712 |
| 3 | ICOS MANAGEMENT, LLC | $131,095 | +19.3% | 7.7% | $70,350 | 2+$7,265 | 2-$526,018 |
| 4 | JAGOE-PUBLIC COMPANY | $201,444 | +83.4% | 65.5% | $56,539 | 4+$39,852 | 2-$506,542 |
| 5 | QUALITY EXCAVATION, LLC | $257,983 | +134.8% | 112.0% | 4+$63,483 | 1-$498,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
SHALOM SERVICES CORPORATION vs GHB EQUIPMENT COMPANY, L.L.C., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 400-7006 CUT & RESTORING PAV | 43 SY | $250.00 | $94.00 | $171.81 | -$6,708 |
| 462-7004 CONC BOX CULV (4 FT X 3 FT) | 55 LF | $400.00 | $500.00 | $404.43 | $5,500 |
| 466-7175 WINGWALL (PW - 1) (HW=5 FT) | 2 EA | $18,500.00 | $16,000.00 | $23,385.57 | -$5,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $2,500.00 | $5,000.00 | $11,585.04 | $5,000 |
| 500-7001 MOBILIZATION | 1 LS | $7,500.00 | $10,000.00 | $523,850.32 | $2,500 |
| 505-7001 TMA (STATIONARY) | 28 DAY | $1.00 | $50.00 | $217.57 | $1,372 |
| 402-7001 TRENCH EXCAVATION PROTECTION | 53 LF | $1.00 | $25.00 | $5.96 | $1,272 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 14 CY | $25.00 | $100.00 | $13.19 | $1,050 |
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN) | 64 CY | $195.00 | $180.00 | $179.97 | -$960 |
| 496-7007 REMOV STR (PIPE) | 112 LF | $25.00 | $19.04 | $23.96 | -$668 |
| 496-7006 REMOV STR (HEADWALL) | 2 EA | $1,000.00 | $1,331.38 | $1,533.90 | $663 |
| 496-7002 REMOV STR (INLET) | 2 EA | $1,000.00 | $1,100.67 | $1,291.45 | $201 |
| 658-7248 INSTL OM ASSM (OM-2Z)(WFLX)GNDLL | 2 EA | $50.00 | $90.28 | $69.01 | $81 |
| 400-7010 CEM STABIL BKFL | 26 CY | $300.00 | $300.00 | $138.14 | $0 |
Positive: the low bidder was cheaper on that item. These 14 items account for $4,303 of the $4,303 gap.
SHALOM SERVICES CORPORATION: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 400-7010 CEM STABIL BKFL | 26 CY | $300.00 | $138.14 | 2.17x | $4,208 |
| 500-7001 MOBILIZATION | 1 LS | $7,500.00 | $523,850.32 | 0.01x | -$516,350 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $2,500.00 | $11,585.04 | 0.22x | -$18,170 |
| 505-7001 TMA (STATIONARY) | 28 DAY | $1.00 | $217.57 | 0.00x | -$6,064 |
GHB EQUIPMENT COMPANY, L.L.C.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 400-7010 CEM STABIL BKFL | 26 CY | $300.00 | $138.14 | 2.17x | $4,208 |
| 500-7001 MOBILIZATION | 1 LS | $10,000.00 | $523,850.32 | 0.02x | -$513,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $5,000.00 | $11,585.04 | 0.43x | -$13,170 |
| 505-7001 TMA (STATIONARY) | 28 DAY | $50.00 | $217.57 | 0.23x | -$4,692 |
ICOS MANAGEMENT, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 400-7010 CEM STABIL BKFL | 26 CY | $315.00 | $138.14 | 2.28x | $4,598 |
| 496-7002 REMOV STR (INLET) | 2 EA | $2,625.00 | $1,291.45 | 2.03x | $2,667 |
| 500-7001 MOBILIZATION | 1 LS | $21,000.00 | $523,850.32 | 0.04x | -$502,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $1.00 | $11,585.04 | 0.00x | -$23,168 |
JAGOE-PUBLIC COMPANY: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $25,000.00 | $11,585.04 | 2.16x | $26,830 |
| 400-7010 CEM STABIL BKFL | 26 CY | $380.00 | $138.14 | 2.75x | $6,288 |
| 402-7001 TRENCH EXCAVATION PROTECTION | 53 LF | $78.00 | $5.96 | 13.09x | $3,818 |
| 496-7007 REMOV STR (PIPE) | 112 LF | $50.00 | $23.96 | 2.09x | $2,916 |
| 500-7001 MOBILIZATION | 1 LS | $22,000.00 | $523,850.32 | 0.04x | -$501,850 |
| 505-7001 TMA (STATIONARY) | 28 DAY | $50.00 | $217.57 | 0.23x | -$4,692 |
QUALITY EXCAVATION, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $26,000.00 | $11,585.04 | 2.24x | $28,830 |
| 400-7006 CUT & RESTORING PAV | 43 SY | $830.00 | $171.81 | 4.83x | $28,302 |
| 402-7001 TRENCH EXCAVATION PROTECTION | 53 LF | $75.00 | $5.96 | 12.59x | $3,659 |
| 496-7007 REMOV STR (PIPE) | 112 LF | $48.00 | $23.96 | 2.00x | $2,692 |
| 500-7001 MOBILIZATION | 1 LS | $25,000.00 | $523,850.32 | 0.05x | -$498,850 |