FY 26, Guardrail Repair N. Harris
6498-52-001 · let Jun 9, 2026 · Harris, Houston · Routine Maintenance Project - Sealed
$599,300Low bid: ROY JORGENSEN ASSOCIATES, INC.-19.3% vs estimate $742,281
$32,382Left on the table5.4% gap to the second bid
3BiddersSpread 12% low to high
62Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ROY JORGENSEN ASSOCIATES, INC. | $599,300 | -19.3% | $32,382 | 6+$34,943 | 6-$117,840 | |
| 2 | RHINO EQUITY, LLC | $631,682 | +5.4% | -14.9% | $36,708 | 5+$49,500 | 12-$189,602 |
| 3 | AUSTIN BARRICADE COMPANY, L.L.C. | $668,390 | +11.5% | -10.0% | 7+$242,090 | 14-$258,378 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
ROY JORGENSEN ASSOCIATES, INC. vs RHINO EQUITY, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 770-7001 REPLACE RAIL ELEMENT (W-BEAM) | 4,000 LF | $20.00 | $35.00 | $22.03 | $60,000 |
| 770-7006 REPLACE TIMBER POST W/O CONC FND | 250 EA | $25.00 | $150.00 | $89.82 | $31,250 |
| 770-7015 REPL SINGLE GDRAIL TERM IMPACT HEAD | 45 EA | $700.00 | $1,200.00 | $975.38 | $22,500 |
| 771-7007 REPLACE POSTS (TL-4)(TRINITY) | 100 EA | $150.00 | $300.00 | $144.70 | $15,000 |
| 658-7012 INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB | 2,000 EA | $8.00 | $1.00 | $9.89 | -$14,000 |
| 778-7002 CONCRETE RAIL REPAIR (MISC) | 100 LF | $115.00 | $250.00 | $113.22 | $13,500 |
| 658-7031 INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB | 2,000 EA | $7.00 | $1.00 | $12.61 | -$12,000 |
| 770-7016 REPLACE SINGLE GDRAIL TERMINAL RAIL | 2,000 LF | $24.00 | $30.00 | $31.82 | $12,000 |
| 776-7003 REPAIR (STEEL PED. RAIL) | 100 LF | $170.00 | $50.00 | $148.66 | -$12,000 |
| 5010-7001 PEDESTRIAN BARRIER (FURN & INSTALL) | 1,000 LF | $40.00 | $30.00 | $38.33 | -$10,000 |
| 770-7017 REPLACE SINGLE GDRAIL TERMINAL POST | 80 EA | $225.00 | $100.00 | $67.59 | -$10,000 |
| 770-7003 REPL RAIL ELMNT(THRIE-BM TRANS TO W-BM) | 75 EA | $50.00 | $175.00 | $65.99 | $9,375 |
| 500-7033 MOBILIZATION (EMERGENCY) | 12 EA | $750.00 | $1,500.00 | $844.81 | $9,000 |
| 512-7108 PORT CTB (ALIGNING) | 8,000 LF | $2.00 | $1.00 | $9.07 | -$8,000 |
| 505-7001 TMA (STATIONARY) | 80 DAY | $100.00 | $1.00 | $217.57 | -$7,920 |
| 770-7008 REPLACE TIMBER POST W/ CONC FND | 125 EA | $90.00 | $150.00 | $94.21 | $7,500 |
| 770-7025 RAISE RAIL | 200 LF | $35.00 | $2.00 | $5.27 | -$6,600 |
| 770-7018 REPLACE BLOCKOUT | 200 EA | $40.00 | $70.00 | $44.95 | $6,000 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 10 CY | $750.00 | $200.00 | $616.83 | -$5,500 |
| 544-7003 GUARDRAIL END TREATMENT (REMOVE) | 2 EA | $3,000.00 | $500.00 | $284.94 | -$5,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for $95,105 of the $32,382 gap.
ROY JORGENSEN ASSOCIATES, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 770-7017 REPLACE SINGLE GDRAIL TERMINAL POST | 80 EA | $225.00 | $67.59 | 3.33x | $12,592 |
| 770-7025 RAISE RAIL | 200 LF | $35.00 | $5.27 | 6.64x | $5,945 |
| 544-7003 GUARDRAIL END TREATMENT (REMOVE) | 2 EA | $3,000.00 | $284.94 | 10.53x | $5,430 |
| 5010-7002 PEDESTRIAN BARRIER (REMOVE & REINSTALL) | 300 LF | $20.00 | $5.59 | 3.58x | $4,324 |
| 771-7018 CHECK / RE-TENSION CABLE (TL-4) | 5 EA | $750.00 | $67.25 | 11.15x | $3,414 |
| 104-7003 REMOV CONC (MOWSTRIP) | 25 SY | $150.00 | $20.48 | 7.33x | $3,238 |
| 512-7108 PORT CTB (ALIGNING) | 8,000 LF | $2.00 | $9.07 | 0.22x | -$56,556 |
| 770-7006 REPLACE TIMBER POST W/O CONC FND | 250 EA | $25.00 | $89.82 | 0.28x | -$16,205 |
| 500-7002 MOBILIZATION (CALLOUT) | 30 EA | $100.00 | $600.85 | 0.17x | -$15,025 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 5 EA | $1,000.00 | $3,190.07 | 0.31x | -$10,950 |
| 550-7001 CHAIN LINK FENCE (INSTALL) (6') | 300 LF | $10.00 | $42.32 | 0.24x | -$9,697 |
| 505-7001 TMA (STATIONARY) | 80 DAY | $100.00 | $217.57 | 0.46x | -$9,406 |
RHINO EQUITY, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7007 REPLACE POSTS (TL-4)(TRINITY) | 100 EA | $300.00 | $144.70 | 2.07x | $15,530 |
| 778-7002 CONCRETE RAIL REPAIR (MISC) | 100 LF | $250.00 | $113.22 | 2.21x | $13,678 |
| 770-7003 REPL RAIL ELMNT(THRIE-BM TRANS TO W-BM) | 75 EA | $175.00 | $65.99 | 2.65x | $8,176 |
| 500-7033 MOBILIZATION (EMERGENCY) | 12 EA | $1,500.00 | $844.81 | 1.78x | $7,862 |
| 770-7028 REALIGN EXISTING RAIL | 100 LF | $50.00 | $7.47 | 6.70x | $4,253 |
| 512-7108 PORT CTB (ALIGNING) | 8,000 LF | $1.00 | $9.07 | 0.11x | -$64,556 |
| 658-7031 INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB | 2,000 EA | $1.00 | $12.61 | 0.08x | -$23,227 |
| 500-7002 MOBILIZATION (CALLOUT) | 30 EA | $1.00 | $600.85 | 0.00x | -$17,995 |
| 658-7012 INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB | 2,000 EA | $1.00 | $9.89 | 0.10x | -$17,789 |
| 505-7001 TMA (STATIONARY) | 80 DAY | $1.00 | $217.57 | 0.00x | -$17,326 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 5 EA | $500.00 | $3,190.07 | 0.16x | -$13,450 |
| 776-7003 REPAIR (STEEL PED. RAIL) | 100 LF | $50.00 | $148.66 | 0.34x | -$9,866 |
| 550-7001 CHAIN LINK FENCE (INSTALL) (6') | 300 LF | $10.00 | $42.32 | 0.24x | -$9,697 |
| 740-7002 GRAFFITI REMOVAL (ABRASIVE CLEAN) | 3,000 SF | $1.00 | $2.63 | 0.38x | -$4,875 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 10 CY | $200.00 | $616.83 | 0.32x | -$4,168 |
AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 80 DAY | $2,000.00 | $217.57 | 9.19x | $142,594 |
| 770-7017 REPLACE SINGLE GDRAIL TERMINAL POST | 80 EA | $700.00 | $67.59 | 10.36x | $50,592 |
| 770-7006 REPLACE TIMBER POST W/O CONC FND | 250 EA | $198.00 | $89.82 | 2.20x | $27,045 |
| 740-7002 GRAFFITI REMOVAL (ABRASIVE CLEAN) | 3,000 SF | $5.00 | $2.63 | 1.90x | $7,125 |
| 770-7010 REALIGN POSTS | 100 EA | $90.00 | $24.32 | 3.70x | $6,568 |
| 740-7001 GRAFFITI REMOVAL (WATER BLAST CLEAN) | 500 SF | $10.00 | $0.4428 | 22.58x | $4,779 |
| 771-7020 REPLACE POST HARDWARE (TL-4) | 10 EA | $350.00 | $11.22 | 31.20x | $3,388 |
| 512-7108 PORT CTB (ALIGNING) | 8,000 LF | $1.00 | $9.07 | 0.11x | -$64,556 |
| 770-7016 REPLACE SINGLE GDRAIL TERMINAL RAIL | 2,000 LF | $1.00 | $31.82 | 0.03x | -$61,636 |
| 5010-7001 PEDESTRIAN BARRIER (FURN & INSTALL) | 1,000 LF | $10.00 | $38.33 | 0.26x | -$28,334 |
| 658-7031 INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB | 2,000 EA | $1.00 | $12.61 | 0.08x | -$23,227 |
| 500-7002 MOBILIZATION (CALLOUT) | 30 EA | $1.00 | $600.85 | 0.00x | -$17,995 |
| 658-7012 INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB | 2,000 EA | $1.00 | $9.89 | 0.10x | -$17,789 |
| 771-7007 REPLACE POSTS (TL-4)(TRINITY) | 100 EA | $50.00 | $144.70 | 0.35x | -$9,470 |
| 550-7001 CHAIN LINK FENCE (INSTALL) (6') | 300 LF | $18.00 | $42.32 | 0.43x | -$7,297 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 10 CY | $100.00 | $616.83 | 0.16x | -$5,168 |
| 770-7018 REPLACE BLOCKOUT | 200 EA | $20.00 | $44.95 | 0.44x | -$4,991 |