RMC 6495-60-001
6495-60-001 · let Jun 9, 2026 · Waller, Houston · Routine Maintenance Project - Sealed
$284,602Low bid: WAYNE YANCEY, INC.-7.1% vs estimate $306,206
$115,166Left on the table40.5% gap to the second bid
3BiddersSpread 53% low to high
3Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | WAYNE YANCEY, INC. | $284,602 | -7.1% | $115,166 | 0 | 2-$10,125 | |
| 2 | BOEN LANDSCAPING & IRRIGATION, LLC | $399,768 | +40.5% | 30.6% | $36,219 | 0 | 0 |
| 3 | YELLOWSTONE LANDSCAPE - CENTRAL, INC. | $435,987 | +53.2% | 42.4% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
WAYNE YANCEY, INC. vs BOEN LANDSCAPING & IRRIGATION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 730-7022 FULL - WIDTH MOWING | 9,048.66 AC | $31.44 | $42.50 | $38.53 | $100,078 |
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $1.00 | $1,000.00 | $600.85 | $11,988 |
| 730-7021 SPOT MOWING | 100 AC | $1.00 | $32.00 | $30.27 | $3,100 |
Positive: the low bidder was cheaper on that item. These 3 items account for $115,166 of the $115,166 gap.