US54(PAT FWY)Mainlane & Ramp Config
0167-01-122 · let Jun 3, 2026 · El Paso, El Paso · Widen Freeway
$69,133,971Low bid: JORDAN FOSTER CONSTRUCTION, LLC-19.3% vs estimate $85,671,123
$3,945,156Left on the table5.7% gap to the second bid
4BiddersSpread 25% low to high
360Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | JORDAN FOSTER CONSTRUCTION, LLC | $69,133,971 | -19.3% | $3,945,156 | 3+$6,834,201 | 1-$844,268 | |
| 2 | DAN WILLIAMS COMPANY | $73,079,126 | +5.7% | -14.7% | $3,476,825 | 3+$7,470,741 | 0 |
| 3 | INTERNATIONAL EAGLE ENTERPRISES, INC. | $76,555,951 | +10.7% | -10.6% | $10,117,686 | 2+$7,299,054 | 0 |
| 4 | SUNDT CONSTRUCTION, INC. | $86,673,637 | +25.4% | 1.2% | 6+$17,147,478 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
JORDAN FOSTER CONSTRUCTION, LLC vs DAN WILLIAMS COMPANY, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 132-7002 EMBANK (FNL)(DC)(TY A) | 434,660 CY | $14.00 | $18.00 | $15.82 | $1,738,640 |
| 100-7002 PREPARING ROW | 166 STA | $986.97 | $8,500.00 | $6,072.92 | $1,247,163 |
| 500-7001 MOBILIZATION | 1 LS | $6,150,215.00 | $6,900,000.00 | $523,850.32 | $749,785 |
| 104-7001 REMOV CONC (PAV) | 16,327 SY | $49.00 | $13.00 | $11.85 | -$587,772 |
| 400-7010 CEM STABIL BKFL | 11,110 CY | $167.00 | $200.00 | $138.14 | $366,630 |
| 192-7024 LOOSE AGGR GRND COVER (TY I) | 12,977 CY | $105.50 | $80.00 | $128.74 | -$330,914 |
| 422-7002 REINF CONC SLAB (HPC) | 69,908 SF | $26.00 | $30.00 | $26.91 | $279,632 |
| 360-7002 CONC PVMT (CRCP) (8") | 24,740 SY | $84.00 | $95.00 | $80.84 | $272,140 |
| 341-7015 D-GR HMA TY-C PG64-22 | 26,979 TON | $90.00 | $100.00 | $97.50 | $269,790 |
| 425-7003 PRESTR CONC GIRDER (TX40) | 8,248.87 LF | $285.00 | $260.00 | $213.86 | -$206,222 |
| 432-7001 RIPRAP (CONC)(4 IN) | 2,589.25 CY | $575.00 | $515.00 | $573.24 | -$155,355 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 36 MO | $15,900.00 | $20,000.00 | $11,585.04 | $147,600 |
| 422-7014 APPROACH SLAB (HPC) | 712.6 CY | $525.00 | $700.00 | $731.91 | $124,705 |
| 192-7004 PLANT SOIL MIX (PLANTING SOIL) | 2,909 CY | $116.00 | $74.00 | $96.67 | -$122,178 |
| 6101-7001 LED AESTHETIC LIGHT ASSEMBLY | 2 EA | $270,000.00 | $325,000.00 | $115,833.33 | $110,000 |
| 4075-7001 ORNAMENTAL STEEL STRUCTURE | 16,703 LF | $111.00 | $105.00 | $111.00 | -$100,218 |
| 420-7023 CL C CONC (CAP)(HPC) | 495.6 CY | $1,200.00 | $1,400.00 | $1,420.15 | $99,120 |
| 505-7003 TMA (MOBILE OPERATION) | 310 DAY | $315.00 | $1.00 | $229.60 | -$97,340 |
| 529-7006 CONC CURB (MONO) (TY I) | 20,772 LF | $14.50 | $10.00 | $13.85 | -$93,474 |
| 531-7001 CONC SIDEWALKS (4") | 15,501 SY | $49.00 | $55.00 | $70.57 | $93,006 |
Positive: the low bidder was cheaper on that item. These 20 items account for $3,804,739 of the $3,945,156 gap.
JORDAN FOSTER CONSTRUCTION, LLC: unbalanced items
Placed 1DAN WILLIAMS COMPANY: unbalanced items
Placed 2INTERNATIONAL EAGLE ENTERPRISES, INC.: unbalanced items
Placed 3SUNDT CONSTRUCTION, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $9,600,000.00 | $523,850.32 | 18.33x | $9,076,150 |
| 100-7002 PREPARING ROW | 166 STA | $32,800.00 | $6,072.92 | 5.40x | $4,436,695 |
| 400-7010 CEM STABIL BKFL | 11,110 CY | $300.00 | $138.14 | 2.17x | $1,798,223 |
| 104-7001 REMOV CONC (PAV) | 16,327 SY | $54.00 | $11.85 | 4.56x | $688,212 |
| 170-7001 IRRIGATION SYSTEM | 1 LS | $739,000.00 | $73,741.57 | 10.02x | $665,258 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 36 MO | $25,000.00 | $11,585.04 | 2.16x | $482,938 |