FM 491 - Shoulders
0861-01-071 · let Jun 2, 2026 · Hidalgo, Pharr · Safety Improvement Projects
$7,675,891Low bid: FOREMOST PAVING, INC.-10.7% vs estimate $8,600,027
$486,948Left on the table6.3% gap to the second bid
7BiddersSpread 27% low to high
191Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | FOREMOST PAVING, INC. | $7,675,891 | -10.7% | $486,948 | 5+$336,130 | 7-$1,179,504 | |
| 2 | IOC COMPANY LLC | $8,162,840 | +6.3% | -5.1% | $295,164 | 3+$309,524 | 8-$1,054,225 |
| 3 | TEXAS CORDIA CONSTRUCTION, LLC | $8,458,004 | +10.2% | -1.7% | $177,758 | 5+$828,643 | 4-$973,285 |
| 4 | REIM CONSTRUCTION, INC. | $8,635,762 | +12.5% | 0.4% | $608,840 | 2+$511,185 | 3-$300,303 |
| 5 | CK NEWBERRY, LLC | $9,244,602 | +20.4% | 7.5% | $42,372 | 4+$687,558 | 4-$1,179,323 |
| 6 | EARTHWORKS ENTERPRISE | $9,286,974 | +21.0% | 8.0% | $456,852 | ||
| 7 | 3LW CIVIL LLC | $9,743,826 | +26.9% | 13.3% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
FOREMOST PAVING, INC. vs IOC COMPANY LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 132-7006 EMBANK (FNL)(DC)(TY C) | 30,703 CY | $18.20 | $1.00 | $13.19 | -$528,092 |
| 344-7064 SP MIXES SP-D SAC-A PG76-22 | 10,310 TON | $113.86 | $150.00 | $129.17 | $372,603 |
| 100-7002 PREPARING ROW | 160 STA | $2,000.00 | $4,000.00 | $6,072.92 | $320,000 |
| 500-7001 MOBILIZATION | 1 LS | $500,000.00 | $800,000.00 | $523,850.32 | $300,000 |
| 110-7001 EXCAV (ROADWAY) | 5,257 CY | $18.72 | $45.00 | $11.68 | $138,154 |
| 247-7277 FL BS (RDWY DEL)(TY E GR 4)(FNL POS) | 17,182 CY | $31.48 | $38.00 | $29.59 | $112,027 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $118,170.00 | $10,000.00 | $136,676.66 | -$108,170 |
| 105-7024 RMV (4") TRT/UNTRT BASE & ASPH PAV | 37,354 SY | $0.3200 | $3.00 | $3.38 | $100,109 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 17 MO | $7,300.00 | $2,500.00 | $11,585.04 | -$81,600 |
| 275-7012 CEMENT TRT (NEW BASE)(10") | 61,851 SY | $3.79 | $2.50 | $3.10 | -$79,788 |
| 416-7004 DRILL SHAFT (24 IN) | 1,360 LF | $404.00 | $360.00 | $234.98 | -$59,840 |
| 432-7001 RIPRAP (CONC)(4 IN) | 164 CY | $409.05 | $750.00 | $573.24 | $55,916 |
| 420-7038 CL C CONC (COLUMN) | 13.9 CY | $5,050.00 | $1,200.00 | $1,548.37 | -$53,515 |
| 260-7005 LIME (COM OR QK)(SLURRY) | 1,288 TON | $250.71 | $210.00 | $295.18 | -$52,434 |
| 260-7009 LIME TRT (EXIST MATL)(12") | 65,053 SY | $3.26 | $2.50 | $3.88 | -$49,440 |
| 425-7016 PRESTR CONC SLAB BEAM (4SB12) | 1,005 LF | $272.70 | $225.00 | $259.02 | -$47,939 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $8,145.87 | $20,000.00 | $9,253.78 | $47,417 |
| 5029-7001 BIRD EXCLUSION METHOD | 5,858 SF | $10.10 | $2.11 | $1.92 | -$46,805 |
| 407-7002 SHEET PILING (PZ - 27) | 6,556 SF | $52.00 | $58.00 | $62.41 | $39,336 |
| 168-7001 VEGETATIVE WATERING | 1,509 TGL | $59.59 | $35.00 | $8.43 | -$37,106 |
Positive: the low bidder was cheaper on that item. These 20 items account for $340,832 of the $486,948 gap.
FOREMOST PAVING, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 420-7022 CL C CONC (CAP) | 34.4 CY | $4,646.00 | $1,543.38 | 3.01x | $106,730 |
| 168-7001 VEGETATIVE WATERING | 1,509 TGL | $59.59 | $8.43 | 7.07x | $77,195 |
| 316-7266 ASPH (TIER II) | 17,595 GAL | $6.82 | $3.66 | 1.86x | $55,604 |
| 420-7038 CL C CONC (COLUMN) | 13.9 CY | $5,050.00 | $1,548.37 | 3.26x | $48,673 |
| 5029-7001 BIRD EXCLUSION METHOD | 5,858 SF | $10.10 | $1.92 | 5.27x | $47,928 |
| 100-7002 PREPARING ROW | 160 STA | $2,000.00 | $6,072.92 | 0.33x | -$651,667 |
| 434-7001 ELASTOMERIC BEARING (PLAIN) | 120 EA | $1.01 | $1,155.61 | 0.00x | -$138,552 |
| 105-7024 RMV (4") TRT/UNTRT BASE & ASPH PAV | 37,354 SY | $0.3200 | $3.38 | 0.09x | -$114,415 |
| 403-7001 TEMPORARY SPL SHORING | 3,750 SF | $0.0100 | $25.56 | 0.00x | -$95,815 |
| 305-7034 SALV,HAUL & STKPL RCL ASPH PV (1 TO 3") | 34,905 SY | $1.34 | $3.49 | 0.38x | -$75,004 |
| 505-7003 TMA (MOBILE OPERATION) | 253 DAY | $0.0100 | $229.60 | 0.00x | -$58,086 |
| 505-7001 TMA (STATIONARY) | 253 DAY | $35.89 | $217.57 | 0.16x | -$45,965 |
IOC COMPANY LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7001 EXCAV (ROADWAY) | 5,257 CY | $45.00 | $11.68 | 3.85x | $175,152 |
| 420-7022 CL C CONC (CAP) | 34.4 CY | $4,200.00 | $1,543.38 | 2.72x | $91,388 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $20,000.00 | $9,253.78 | 2.16x | $42,985 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 30,703 CY | $1.00 | $13.19 | 0.08x | -$374,328 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 17 MO | $2,500.00 | $11,585.04 | 0.22x | -$154,446 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $10,000.00 | $136,676.66 | 0.07x | -$126,677 |
| 434-7001 ELASTOMERIC BEARING (PLAIN) | 120 EA | $200.00 | $1,155.61 | 0.17x | -$114,673 |
| 305-7034 SALV,HAUL & STKPL RCL ASPH PV (1 TO 3") | 34,905 SY | $1.00 | $3.49 | 0.29x | -$86,872 |
| 403-7001 TEMPORARY SPL SHORING | 3,750 SF | $3.00 | $25.56 | 0.12x | -$84,602 |
| 505-7003 TMA (MOBILE OPERATION) | 253 DAY | $1.00 | $229.60 | 0.00x | -$57,835 |
| 505-7001 TMA (STATIONARY) | 253 DAY | $1.00 | $217.57 | 0.00x | -$54,793 |
TEXAS CORDIA CONSTRUCTION, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7277 FL BS (RDWY DEL)(TY E GR 4)(FNL POS) | 17,182 CY | $55.00 | $29.59 | 1.86x | $436,517 |
| 422-7007 REINF CONC SLAB (SLAB BEAM) | 5,851 SF | $50.00 | $23.90 | 2.09x | $152,689 |
| 450-7008 RAIL (TY T223) | 364 LF | $500.00 | $141.07 | 3.54x | $130,652 |
| 316-7266 ASPH (TIER II) | 17,595 GAL | $7.00 | $3.66 | 1.91x | $58,771 |
| 400-7010 CEM STABIL BKFL | 309 CY | $300.00 | $138.14 | 2.17x | $50,014 |
| 100-7002 PREPARING ROW | 160 STA | $2,000.00 | $6,072.92 | 0.33x | -$651,667 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 17 MO | $500.00 | $11,585.04 | 0.04x | -$188,446 |
| 434-7001 ELASTOMERIC BEARING (PLAIN) | 120 EA | $470.00 | $1,155.61 | 0.41x | -$82,273 |
| 110-7001 EXCAV (ROADWAY) | 5,257 CY | $2.00 | $11.68 | 0.17x | -$50,899 |
REIM CONSTRUCTION, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 416-7004 DRILL SHAFT (24 IN) | 1,360 LF | $493.00 | $234.98 | 2.10x | $350,912 |
| 403-7001 TEMPORARY SPL SHORING | 3,750 SF | $68.30 | $25.56 | 2.67x | $160,273 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 17 MO | $2,940.00 | $11,585.04 | 0.25x | -$146,966 |
| 434-7001 ELASTOMERIC BEARING (PLAIN) | 120 EA | $276.00 | $1,155.61 | 0.24x | -$105,553 |
| 505-7001 TMA (STATIONARY) | 253 DAY | $28.70 | $217.57 | 0.13x | -$47,785 |
CK NEWBERRY, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $925,000.00 | $523,850.32 | 1.77x | $401,150 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $325,000.00 | $136,676.66 | 2.38x | $188,323 |
| 420-7022 CL C CONC (CAP) | 34.4 CY | $3,000.00 | $1,543.38 | 1.94x | $50,108 |
| 420-7038 CL C CONC (COLUMN) | 13.9 CY | $5,000.00 | $1,548.37 | 3.23x | $47,978 |
| 100-7002 PREPARING ROW | 160 STA | $300.00 | $6,072.92 | 0.05x | -$923,667 |
| 434-7001 ELASTOMERIC BEARING (PLAIN) | 120 EA | $35.00 | $1,155.61 | 0.03x | -$134,473 |
| 305-7034 SALV,HAUL & STKPL RCL ASPH PV (1 TO 3") | 34,905 SY | $1.50 | $3.49 | 0.43x | -$69,419 |
| 505-7003 TMA (MOBILE OPERATION) | 253 DAY | $25.00 | $229.60 | 0.11x | -$51,763 |