FY26, Flexible Pavement, Jack & Wise
6499-79-001 · let Jun 3, 2026 · Wise, Fort Worth · Routine Maintenance Project - Sealed
$5,864,828Low bid: NORTHEASTERN PAVERS, LLC-0.3% vs estimate $5,882,581
$374,750Left on the table6.4% gap to the second bid
6BiddersSpread 53% low to high
15Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | NORTHEASTERN PAVERS, LLC | $5,864,828 | -0.3% | $374,750 | 0 | 1-$37,900 | |
| 2 | FOUTSCO PAVING COMPANY, LLC | $6,239,578 | +6.4% | 6.1% | $803,416 | 1+$43,992 | 1-$37,900 |
| 3 | EUROVIA ATLANTIC COAST LLC | $7,042,993 | +20.1% | 19.7% | $302,624 | 1+$68,992 | 0 |
| 4 | JAGOE-PUBLIC COMPANY | $7,345,618 | +25.2% | 24.9% | $1,466,226 | 5+$414,655 | 0 |
| 5 | PEACHTREE CONSTRUCTION, LTD. | $8,811,843 | +50.2% | 49.8% | $169,628 | 3+$1,049,099 | 0 |
| 6 | OVERLAND CORPORATION | $8,981,471 | +53.1% | 52.7% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
NORTHEASTERN PAVERS, LLC vs FOUTSCO PAVING COMPANY, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 30,579 SY | $35.00 | $43.00 | $35.01 | $244,632 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 24,521.33 SY | $50.00 | $59.00 | $49.06 | $220,692 |
| 354-7033 PLANE ASPH CONC PAV(0" TO 3") | 32,074.89 SY | $5.00 | $2.10 | $3.11 | -$93,017 |
| 344-7024 SP MIXES SP-C SAC-A PG70-28 | 10,389.03 TON | $170.00 | $165.00 | $156.36 | -$51,945 |
| 500-7002 MOBILIZATION (CALLOUT) | 10 EA | $2,500.00 | $5,000.00 | $600.85 | $25,000 |
| 344-7077 TACK COAT | 3,200 GAL | $4.00 | $10.00 | $3.25 | $19,200 |
| 500-7033 MOBILIZATION (EMERGENCY) | 2 EA | $1,000.00 | $5,000.00 | $844.81 | $8,000 |
| 351-7011 FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") | 100 SY | $200.00 | $130.00 | $98.88 | -$7,000 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 1,000 SY | $70.00 | $75.00 | $60.19 | $5,000 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 672 EA | $1.00 | $5.00 | $1.03 | $2,688 |
| 351-7009 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") | 100 SY | $105.00 | $120.00 | $77.78 | $1,500 |
| 344-7025 SP MIXES SP-C SAC-B PG70-28 | 10,000 TON | $150.00 | $150.00 | $124.40 | $0 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 300 DAY | $1.00 | $1.00 | $87.82 | $0 |
| 505-7001 TMA (STATIONARY) | 175 DAY | $1.00 | $1.00 | $217.57 | $0 |
| 662-7113 WK ZN PAV MRK SHT TERM (TAB)TY Y | 540 EA | $1.00 | $1.00 | $1.11 | $0 |
Positive: the low bidder was cheaper on that item. These 15 items account for $374,750 of the $374,750 gap.
NORTHEASTERN PAVERS, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 175 DAY | $1.00 | $217.57 | 0.00x | -$37,900 |
FOUTSCO PAVING COMPANY, LLC: unbalanced items
Placed 2EUROVIA ATLANTIC COAST LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 10 EA | $7,500.00 | $600.85 | 12.48x | $68,992 |
JAGOE-PUBLIC COMPANY: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 354-7033 PLANE ASPH CONC PAV(0" TO 3") | 32,074.89 SY | $9.00 | $3.11 | 2.90x | $189,021 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 1,000 SY | $132.00 | $60.19 | 2.19x | $71,809 |
| 500-7002 MOBILIZATION (CALLOUT) | 10 EA | $6,500.00 | $600.85 | 10.82x | $58,992 |
| 351-7011 FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") | 100 SY | $600.00 | $98.88 | 6.07x | $50,112 |
| 351-7009 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") | 100 SY | $525.00 | $77.78 | 6.75x | $44,722 |