BPM FY2027 Atlanta District
6499-57-001 · let Jun 3, 2026 · Bowie, Atlanta · Bridge Preventative Maintenance - Sealed
$904,025Low bid: THK CONSTRUCTION LLC-54.7% vs estimate $1,994,770
$97,795Left on the table10.8% gap to the second bid
11BiddersSpread 203% low to high
17Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | THK CONSTRUCTION LLC | $904,025 | -54.7% | $97,795 | 2+$53,056 | 3-$521,504 | |
| 2 | JACKSON EXCAVATION, LLC | $1,001,820 | +10.8% | -49.8% | $247,078 | 5+$231,304 | 3-$551,582 |
| 3 | SHALOM SERVICES CORPORATION | $1,248,898 | +38.1% | -37.4% | $138,657 | 7+$226,782 | 4-$600,268 |
| 4 | PATHFIELD INVESTMENTS LLC | $1,387,555 | +53.5% | -30.4% | $152,405 | 6+$382,917 | 4-$594,739 |
| 5 | GARRET SHIELDS INFRASTRUCTURE | $1,539,960 | +70.3% | -22.8% | $65,781 | 5+$328,159 | 1-$343,850 |
| 6 | MACIAS SPECIALTY CONTRACTING LLC | $1,605,741 | +77.6% | -19.5% | $84,454 | ||
| 7 | ICOS MANAGEMENT, LLC | $1,690,195 | +87.0% | -15.3% | $23,787 | ||
| 8 | REAR CONTRACTORS LLC | $1,713,981 | +89.6% | -14.1% | $485,579 | ||
| 9 | CROSS PLUS CONSTRUCTION, LLC | $2,199,560 | +143.3% | 10.3% | $184,320 | ||
| 10 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | $2,383,880 | +163.7% | 19.5% | $353,250 | ||
| 11 | EAST TEXAS BRIDGE, INC. | $2,737,130 | +202.8% | 37.2% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
THK CONSTRUCTION LLC vs JACKSON EXCAVATION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 502-7004 BARRICADES, SIGNS AND TRAFFIC HANDLING | 29 EA | $615.52 | $5,000.00 | $3,068.24 | $127,150 |
| 132-7001 EMBANK (FNL)(OC)(TY A) | 3,004 CY | $20.00 | $50.00 | $22.62 | $90,120 |
| 505-7001 TMA (STATIONARY) | 336 DAY | $250.00 | $500.00 | $217.57 | $84,000 |
| 500-7001 MOBILIZATION | 1 LS | $82,000.00 | $10,000.00 | $523,850.32 | -$72,000 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 760 SF | $150.00 | $80.00 | $150.68 | -$53,200 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 336 DAY | $100.00 | $10.00 | $87.82 | -$30,240 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 1,228 LF | $50.00 | $30.00 | $15.92 | -$24,560 |
| 432-7050 BEDDING MATERIAL (6 IN) | 331 CY | $170.00 | $100.00 | $190.99 | -$23,170 |
| 788-7004 CONCRETE BEAM REP (STRAND SPLICE) | 2 EA | $10,000.00 | $100.00 | $5,892.50 | -$19,800 |
| 110-7002 EXCAV (CHANNEL) | 942 CY | $20.00 | $40.00 | $16.69 | $18,840 |
| 780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT) | 150 LF | $20.00 | $100.00 | $76.83 | $12,000 |
| 480-7002 CLEAN EXIST CULVERTS | 2,354 CY | $30.00 | $25.00 | $42.86 | -$11,770 |
| 7020-7003 GEN DEBRIS REMOVE FROM UNDER BRIDGES | 370 CY | $60.00 | $70.00 | $29.72 | $3,700 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 35 SF | $180.00 | $100.00 | $95.74 | -$2,800 |
| 104-7006 REMOV CONC (RIPRAP) | 95 SY | $25.00 | $20.00 | $14.32 | -$475 |
| 401-7001 FLOWABLE BACKFILL | 69 CY | $400.00 | $400.00 | $298.77 | $0 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 1,317 CY | $170.00 | $170.00 | $184.74 | $0 |
Positive: the low bidder was cheaper on that item. These 17 items account for $97,795 of the $97,795 gap.
THK CONSTRUCTION LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 1,228 LF | $50.00 | $15.92 | 3.14x | $41,854 |
| 7020-7003 GEN DEBRIS REMOVE FROM UNDER BRIDGES | 370 CY | $60.00 | $29.72 | 2.02x | $11,202 |
| 500-7001 MOBILIZATION | 1 LS | $82,000.00 | $523,850.32 | 0.16x | -$441,850 |
| 502-7004 BARRICADES, SIGNS AND TRAFFIC HANDLING | 29 EA | $615.52 | $3,068.24 | 0.20x | -$71,129 |
| 780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT) | 150 LF | $20.00 | $76.83 | 0.26x | -$8,524 |
JACKSON EXCAVATION, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 336 DAY | $500.00 | $217.57 | 2.30x | $94,896 |
| 132-7001 EMBANK (FNL)(OC)(TY A) | 3,004 CY | $50.00 | $22.62 | 2.21x | $82,258 |
| 110-7002 EXCAV (CHANNEL) | 942 CY | $40.00 | $16.69 | 2.40x | $21,954 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 1,228 LF | $30.00 | $15.92 | 1.88x | $17,294 |
| 7020-7003 GEN DEBRIS REMOVE FROM UNDER BRIDGES | 370 CY | $70.00 | $29.72 | 2.35x | $14,902 |
| 500-7001 MOBILIZATION | 1 LS | $10,000.00 | $523,850.32 | 0.02x | -$513,850 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 336 DAY | $10.00 | $87.82 | 0.11x | -$26,147 |
| 788-7004 CONCRETE BEAM REP (STRAND SPLICE) | 2 EA | $100.00 | $5,892.50 | 0.02x | -$11,585 |
SHALOM SERVICES CORPORATION: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7001 EMBANK (FNL)(OC)(TY A) | 3,004 CY | $40.00 | $22.62 | 1.77x | $52,218 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 35 SF | $1,500.00 | $95.74 | 15.67x | $49,149 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 1,228 LF | $50.00 | $15.92 | 3.14x | $41,854 |
| 7020-7003 GEN DEBRIS REMOVE FROM UNDER BRIDGES | 370 CY | $125.00 | $29.72 | 4.21x | $35,252 |
| 110-7002 EXCAV (CHANNEL) | 942 CY | $40.00 | $16.69 | 2.40x | $21,954 |
| 788-7004 CONCRETE BEAM REP (STRAND SPLICE) | 2 EA | $15,000.00 | $5,892.50 | 2.55x | $18,215 |
| 104-7006 REMOV CONC (RIPRAP) | 95 SY | $100.00 | $14.32 | 6.98x | $8,140 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 502-7004 BARRICADES, SIGNS AND TRAFFIC HANDLING | 29 EA | $500.00 | $3,068.24 | 0.16x | -$74,479 |
| 505-7001 TMA (STATIONARY) | 336 DAY | $1.00 | $217.57 | 0.00x | -$72,768 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 336 DAY | $1.00 | $87.82 | 0.01x | -$29,171 |
PATHFIELD INVESTMENTS LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7001 EMBANK (FNL)(OC)(TY A) | 3,004 CY | $95.00 | $22.62 | 4.20x | $217,438 |
| 110-7002 EXCAV (CHANNEL) | 942 CY | $80.00 | $16.69 | 4.79x | $59,634 |
| 7020-7003 GEN DEBRIS REMOVE FROM UNDER BRIDGES | 370 CY | $120.00 | $29.72 | 4.04x | $33,402 |
| 401-7001 FLOWABLE BACKFILL | 69 CY | $700.00 | $298.77 | 2.34x | $27,685 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 1,228 LF | $38.00 | $15.92 | 2.39x | $27,118 |
| 104-7006 REMOV CONC (RIPRAP) | 95 SY | $200.00 | $14.32 | 13.97x | $17,640 |
| 500-7001 MOBILIZATION | 1 LS | $120,000.00 | $523,850.32 | 0.23x | -$403,850 |
| 502-7004 BARRICADES, SIGNS AND TRAFFIC HANDLING | 29 EA | $1.00 | $3,068.24 | 0.00x | -$88,950 |
| 505-7001 TMA (STATIONARY) | 336 DAY | $1.00 | $217.57 | 0.00x | -$72,768 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 336 DAY | $1.00 | $87.82 | 0.01x | -$29,171 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 480-7002 CLEAN EXIST CULVERTS | 2,354 CY | $120.00 | $42.86 | 2.80x | $181,592 |
| 132-7001 EMBANK (FNL)(OC)(TY A) | 3,004 CY | $40.00 | $22.62 | 1.77x | $52,218 |
| 7020-7003 GEN DEBRIS REMOVE FROM UNDER BRIDGES | 370 CY | $120.00 | $29.72 | 4.04x | $33,402 |
| 110-7002 EXCAV (CHANNEL) | 942 CY | $50.00 | $16.69 | 3.00x | $31,374 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 1,228 LF | $40.00 | $15.92 | 2.51x | $29,574 |
| 500-7001 MOBILIZATION | 1 LS | $180,000.00 | $523,850.32 | 0.34x | -$343,850 |