Reflectorized Pvmt. Markings 09 0226
6489-32-001 · let Jun 10, 2026 · Ellis, Dallas · Routine Maintenance Project - Sealed
$159,616Low bid: TRP INFRASTRUCTURE SERVICES, LLC-46.9% vs estimate $300,758
$5,520Left on the table3.5% gap to the second bid
4BiddersSpread 132% low to high
25Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TRP INFRASTRUCTURE SERVICES, LLC | $159,616 | -46.9% | $5,520 | 0 | 4-$584,052 | |
| 2 | STRIPE-A-ZONE, LLC | $165,136 | +3.5% | -45.1% | $75,084 | 1+$3,147 | 5-$590,526 |
| 3 | D. I. J. CONSTRUCTION, INC. | $240,220 | +50.5% | -20.1% | $129,922 | 2+$9,558 | 4-$561,553 |
| 4 | STRIPE LINES, INC. | $370,143 | +131.9% | 23.1% | 5+$51,025 | 2-$529,020 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
TRP INFRASTRUCTURE SERVICES, LLC vs STRIPE-A-ZONE, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $6,500.00 | $15,000.00 | $523,850.32 | $8,500 |
| 666-7213 RE PM TY II (Y) 6" (SLD) | 59,664 LF | $0.1700 | $0.0400 | $0.1749 | -$7,756 |
| 677-7008 ELIM EXT PM & MRKS (24") | 10,726 LF | $0.5000 | $0.0100 | $2.87 | -$5,256 |
| 666-7410 REFL PAV MRK TY I (W)6"(SLD)(090MIL) | 86,578 LF | $0.4500 | $0.5000 | $0.4886 | $4,329 |
| 677-7001 ELIM EXT PM & MRKS (4") | 9,375 LF | $0.2000 | $0.6000 | $0.2643 | $3,750 |
| 666-7035 REFL PAV MRK TY I (W)24"(SLD)(090MIL) | 816 LF | $6.40 | $10.50 | $7.10 | $3,346 |
| 666-7422 REFL PAV MRK TY I (Y)6"(SLD)(090MIL) | 145,304 LF | $0.4500 | $0.4400 | $0.5014 | -$1,453 |
| 666-7211 RE PM TY II (Y) 6" (BRK) | 10,726 LF | $0.1700 | $0.0400 | $0.1759 | -$1,394 |
| 666-7044 REFL PAV MRK TY I(W)(DBL ARROW)(090MIL) | 5 EA | $175.00 | $400.00 | $210.27 | $1,125 |
| 666-7407 REFL PAV MRK TY I (W)6"(BRK)(090MIL) | 21,460 LF | $0.4500 | $0.5000 | $0.5397 | $1,073 |
| 505-7003 TMA (MOBILE OPERATION) | 87 DAY | $10.00 | $0.0100 | $229.60 | -$869 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $500.00 | $100.00 | $11,585.04 | -$800 |
| 666-7041 REFL PAV MRK TY I (W)(ARROW)(090MIL) | 4 EA | $125.00 | $300.00 | $164.35 | $700 |
| 666-7023 REFL PAV MRK TY I (W)8"(SLD)(090MIL) | 4,500 LF | $0.8000 | $0.9500 | $0.9036 | $675 |
| 666-7184 RE PM TY II (W) 24" (SLD) | 296 LF | $1.70 | $0.5000 | $3.83 | -$355 |
| 666-7347 PAVEMENT SLER 6" | 9,300 LF | $0.1300 | $0.1000 | $0.1841 | -$279 |
| 677-7004 ELIM EXT PM & MRKS (8") | 450 LF | $0.5000 | $1.00 | $0.6468 | $225 |
| 677-7009 ELIM EXT PM & MRKS (ARROW) | 4 EA | $40.00 | $80.00 | $50.50 | $160 |
| 677-7010 ELIM EXT PM & MRKS (DBL ARROW) | 5 EA | $50.00 | $80.00 | $65.64 | $150 |
| 666-7419 REFL PAV MRK TY I (Y)6"(BRK)(090MIL) | 10,726 LF | $0.4500 | $0.4400 | $0.5412 | -$107 |
Positive: the low bidder was cheaper on that item. These 20 items account for $5,762 of the $5,520 gap.
TRP INFRASTRUCTURE SERVICES, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $6,500.00 | $523,850.32 | 0.01x | -$517,350 |
| 677-7008 ELIM EXT PM & MRKS (24") | 10,726 LF | $0.5000 | $2.87 | 0.17x | -$25,427 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $500.00 | $11,585.04 | 0.04x | -$22,170 |
| 505-7003 TMA (MOBILE OPERATION) | 87 DAY | $10.00 | $229.60 | 0.04x | -$19,105 |
STRIPE-A-ZONE, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 677-7001 ELIM EXT PM & MRKS (4") | 9,375 LF | $0.6000 | $0.2643 | 2.27x | $3,147 |
| 500-7001 MOBILIZATION | 1 LS | $15,000.00 | $523,850.32 | 0.03x | -$508,850 |
| 677-7008 ELIM EXT PM & MRKS (24") | 10,726 LF | $0.0100 | $2.87 | 0.00x | -$30,683 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $100.00 | $11,585.04 | 0.01x | -$22,970 |
| 505-7003 TMA (MOBILE OPERATION) | 87 DAY | $0.0100 | $229.60 | 0.00x | -$19,974 |
| 666-7213 RE PM TY II (Y) 6" (SLD) | 59,664 LF | $0.0400 | $0.1749 | 0.23x | -$8,049 |
D. I. J. CONSTRUCTION, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 677-7001 ELIM EXT PM & MRKS (4") | 9,375 LF | $0.8500 | $0.2643 | 3.22x | $5,491 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 9,375 LF | $0.5000 | $0.0662 | 7.55x | $4,067 |
| 500-7001 MOBILIZATION | 1 LS | $24,000.00 | $523,850.32 | 0.05x | -$499,850 |
| 677-7008 ELIM EXT PM & MRKS (24") | 10,726 LF | $0.2000 | $2.87 | 0.07x | -$28,645 |
| 505-7003 TMA (MOBILE OPERATION) | 87 DAY | $1.00 | $229.60 | 0.00x | -$19,888 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $5,000.00 | $11,585.04 | 0.43x | -$13,170 |
STRIPE LINES, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 666-7213 RE PM TY II (Y) 6" (SLD) | 59,664 LF | $0.5500 | $0.1749 | 3.14x | $22,380 |
| 505-7001 TMA (STATIONARY) | 10 DAY | $1,350.00 | $217.57 | 6.20x | $11,324 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 9,375 LF | $1.00 | $0.0662 | 15.11x | $8,754 |
| 677-7001 ELIM EXT PM & MRKS (4") | 9,375 LF | $0.7500 | $0.2643 | 2.84x | $4,553 |
| 666-7211 RE PM TY II (Y) 6" (BRK) | 10,726 LF | $0.5500 | $0.1759 | 3.13x | $4,013 |
| 500-7001 MOBILIZATION | 1 LS | $15,000.00 | $523,850.32 | 0.03x | -$508,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $1,500.00 | $11,585.04 | 0.13x | -$20,170 |