FY26 Brazoria Flexpave/Asphalt Repair
6498-37-001 · let Jun 2, 2026 · Brazoria, Houston · Routine Maintenance Project - Sealed
$1,369,590Low bid: CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.+7.3% vs estimate $1,276,674
$187,522Left on the table13.7% gap to the second bid
4BiddersSpread 37% low to high
11Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | $1,369,590 | 7.3% | $187,522 | 1+$8,625 | 0 | |
| 2 | HAYDEN PAVING, INC. | $1,557,112 | +13.7% | 22.0% | $129,928 | 0 | 0 |
| 3 | MC2 CIVIL, LLC | $1,687,040 | +23.2% | 32.1% | $183,632 | 1+$14,121 | 0 |
| 4 | FORDE CONSTRUCTION COMPANY, INC. | $1,870,672 | +36.6% | 46.5% | 3+$242,156 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. vs HAYDEN PAVING, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 351-7001 FLEXIBLE PAVEMENT STRUCTURE REPAIR(2") | 20,000 SY | $26.65 | $37.00 | $30.34 | $207,000 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 6,000 SY | $84.00 | $82.00 | $60.19 | -$12,000 |
| 662-7008 WK ZN PAV MRK NON-REMOV (W)6"(SLD) | 5,000 LF | $2.00 | $0.7000 | $0.2750 | -$6,500 |
| 505-7001 TMA (STATIONARY) | 50 DAY | $125.00 | $250.00 | $217.57 | $6,250 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 6,000 SY | $48.30 | $49.00 | $35.01 | $4,200 |
| 500-7033 MOBILIZATION (EMERGENCY) | 4 EA | $2,000.00 | $1,000.00 | $844.81 | -$4,000 |
| 662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) | 3,000 LF | $2.00 | $0.7000 | $0.2770 | -$3,900 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 14 DAY | $250.00 | $150.00 | $87.82 | -$1,400 |
| 662-7036 WK ZN PAV MRK NON-REMOV (Y)6"(BRK) | 760 LF | $2.00 | $0.5000 | $0.2544 | -$1,140 |
| 662-7005 WK ZN PAV MRK NON-REMOV (W)6"(BRK) | 760 LF | $2.00 | $0.7000 | $0.3316 | -$988 |
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $500.00 | $500.00 | $600.85 | $0 |
Positive: the low bidder was cheaper on that item. These 11 items account for $187,522 of the $187,522 gap.
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 662-7008 WK ZN PAV MRK NON-REMOV (W)6"(SLD) | 5,000 LF | $2.00 | $0.2750 | 7.27x | $8,625 |
MC2 CIVIL, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 50 DAY | $500.00 | $217.57 | 2.30x | $14,121 |