BMN | Bridge Joint Repair Districtwide
0909-00-108 · let Jun 3, 2026 · McLennan, Waco · Bridge Maintenance
$3,058,058Low bid: THE TRUESDELL CORPORATION-12.9% vs estimate $3,511,971
$294,635Left on the table9.6% gap to the second bid
9BiddersSpread 169% low to high
48Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | THE TRUESDELL CORPORATION | $3,058,058 | -12.9% | $294,635 | 5+$144,009 | 7-$411,032 | |
| 2 | ICOS MANAGEMENT, LLC | $3,352,693 | +9.6% | -4.5% | $314,743 | 9+$397,748 | 5-$930,899 |
| 3 | GARRET SHIELDS INFRASTRUCTURE | $3,667,437 | +19.9% | 4.4% | $151,972 | 1+$25,888 | 5-$690,299 |
| 4 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | $3,819,408 | +24.9% | 8.8% | $574,097 | 3+$174,411 | 4-$775,259 |
| 5 | STRUCTURAL INTEGRITY GROUP LLC | $4,393,505 | +43.7% | 25.1% | $325,602 | 8+$719,000 | 6-$438,257 |
| 6 | BLACKSMITH VENTURES LLC | $4,719,107 | +54.3% | 34.4% | $138,811 | ||
| 7 | SCR CIVIL CONSTRUCTION, LLC | $4,857,918 | +58.9% | 38.3% | $1,130,074 | ||
| 8 | RAGLE CONSTRUCTION, INC. | $5,987,991 | +95.8% | 70.5% | $2,236,626 | ||
| 9 | PREMIER CONTRACTORS LLC | $8,224,618 | +168.9% | 134.2% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
THE TRUESDELL CORPORATION vs ICOS MANAGEMENT, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 420-7060 CL C CONC (PILE ENCASEMENT) | 52.8 CY | $990.00 | $3,150.00 | $827.85 | $114,048 |
| 500-7001 MOBILIZATION | 1 LS | $261,938.00 | $150,135.00 | $523,850.32 | -$111,803 |
| 466-7183 WINGWALL (PW - 1) (HW=13 FT) | 2 EA | $77,000.00 | $26,250.00 | $70,348.54 | -$101,500 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $7,000.00 | $2.00 | $11,585.04 | -$90,974 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 8,805 SF | $18.00 | $8.40 | $28.47 | -$84,528 |
| 431-7002 PNEUMATICALLY PLACED CONC (REPAIR) | 480 CF | $120.00 | $294.00 | $115.77 | $83,520 |
| 505-7001 TMA (STATIONARY) | 390 DAY | $1.00 | $189.00 | $217.57 | $73,320 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 3,833 CY | $150.00 | $168.00 | $190.61 | $68,994 |
| 505-7003 TMA (MOBILE OPERATION) | 195 DAY | $1.00 | $315.00 | $229.60 | $61,230 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 390 DAY | $1.00 | $147.00 | $87.82 | $56,940 |
| 132-7015 EMBANK (VEH)(OC)(TY B) | 4,039 CY | $35.00 | $21.00 | $25.35 | -$56,546 |
| 7001-7002 BENT CAP/ABUTMENT CAP CLEANING | 12 EA | $600.00 | $4,200.00 | $475.41 | $43,200 |
| 735-7060 DRIFTWOOD REMOVAL | 2,840 CY | $77.00 | $63.00 | $72.46 | -$39,760 |
| 446-7007 CLEAN & PAINT EXIST PILING (SYSTEM I) | 1 LS | $30,000.00 | $63,000.00 | $70,750.00 | $33,000 |
| 429-7001 CONC STR REPAIR(CLEAN & COAT WTH EPOXY) | 792 SF | $65.00 | $105.00 | $120.92 | $31,680 |
| 401-7001 FLOWABLE BACKFILL | 124 CY | $550.00 | $315.00 | $298.77 | -$29,140 |
| 4076-7001 CONCRETE ARMOR UNIT (48") | 200 EA | $288.00 | $420.00 | $288.00 | $26,400 |
| 495-7001 RAISING EXIST STRUCT | 1 LS | $15,800.00 | $42,000.00 | $52,755.69 | $26,200 |
| 459-7001 GABIONS (GALV) | 410 CY | $277.00 | $336.00 | $333.69 | $24,190 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 2,906 CY | $150.00 | $158.00 | $184.74 | $23,248 |
Positive: the low bidder was cheaper on that item. These 20 items account for $151,719 of the $294,635 gap.
THE TRUESDELL CORPORATION: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7002 EXCAV (CHANNEL) | 1,005 CY | $65.00 | $16.69 | 3.89x | $48,548 |
| 401-7001 FLOWABLE BACKFILL | 124 CY | $550.00 | $298.77 | 1.84x | $31,153 |
| 438-7004 CLEANING AND SEALING EXIST JOINTS (CL3) | 484 LF | $65.00 | $19.19 | 3.39x | $22,171 |
| 442-7010 STR STEEL (PEDESTAL) | 238 LB | $110.00 | $20.55 | 5.35x | $21,290 |
| 104-7006 REMOV CONC (RIPRAP) | 1,008 SY | $35.00 | $14.32 | 2.44x | $20,848 |
| 100-7002 PREPARING ROW | 31.5 STA | $1,250.00 | $6,072.92 | 0.21x | -$151,922 |
| 505-7001 TMA (STATIONARY) | 390 DAY | $1.00 | $217.57 | 0.00x | -$84,463 |
| 505-7003 TMA (MOBILE OPERATION) | 195 DAY | $1.00 | $229.60 | 0.00x | -$44,576 |
| 446-7007 CLEAN & PAINT EXIST PILING (SYSTEM I) | 1 LS | $30,000.00 | $70,750.00 | 0.42x | -$40,750 |
| 495-7001 RAISING EXIST STRUCT | 1 LS | $15,800.00 | $52,755.69 | 0.30x | -$36,956 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 390 DAY | $1.00 | $87.82 | 0.01x | -$33,859 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $1.00 | $9,253.78 | 0.00x | -$18,506 |
ICOS MANAGEMENT, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 420-7060 CL C CONC (PILE ENCASEMENT) | 52.8 CY | $3,150.00 | $827.85 | 3.81x | $122,610 |
| 431-7002 PNEUMATICALLY PLACED CONC (REPAIR) | 480 CF | $294.00 | $115.77 | 2.54x | $85,551 |
| 7001-7002 BENT CAP/ABUTMENT CAP CLEANING | 12 EA | $4,200.00 | $475.41 | 8.83x | $44,695 |
| 110-7002 EXCAV (CHANNEL) | 1,005 CY | $52.50 | $16.69 | 3.14x | $35,985 |
| 442-7010 STR STEEL (PEDESTAL) | 238 LB | $157.50 | $20.55 | 7.67x | $32,595 |
| 438-7004 CLEANING AND SEALING EXIST JOINTS (CL3) | 484 LF | $63.00 | $19.19 | 3.28x | $21,203 |
| 351-7002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(3") | 213 SY | $126.00 | $36.28 | 3.47x | $19,110 |
| 442-7017 MISC NON-BRIDGE (NBIS) | 168 LB | $157.50 | $47.98 | 3.28x | $18,399 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 87 SY | $262.50 | $60.19 | 4.36x | $17,601 |
| 500-7001 MOBILIZATION | 1 LS | $150,135.00 | $523,850.32 | 0.29x | -$373,715 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 8,805 SF | $8.40 | $28.47 | 0.30x | -$176,723 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $2.00 | $11,585.04 | 0.00x | -$150,580 |
| 100-7002 PREPARING ROW | 31.5 STA | $1,575.00 | $6,072.92 | 0.26x | -$141,685 |
| 466-7183 WINGWALL (PW - 1) (HW=13 FT) | 2 EA | $26,250.00 | $70,348.54 | 0.37x | -$88,197 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 104-7006 REMOV CONC (RIPRAP) | 1,008 SY | $40.00 | $14.32 | 2.79x | $25,888 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
| 100-7002 PREPARING ROW | 31.5 STA | $1,000.00 | $6,072.92 | 0.16x | -$159,797 |
| 466-7183 WINGWALL (PW - 1) (HW=13 FT) | 2 EA | $25,000.00 | $70,348.54 | 0.36x | -$90,697 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $5,000.00 | $11,585.04 | 0.43x | -$85,606 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 390 DAY | $10.00 | $87.82 | 0.11x | -$30,349 |
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7001 CONC STR REPAIR(CLEAN & COAT WTH EPOXY) | 792 SF | $250.00 | $120.92 | 2.07x | $102,229 |
| 431-7002 PNEUMATICALLY PLACED CONC (REPAIR) | 480 CF | $225.00 | $115.77 | 1.94x | $52,431 |
| 438-7004 CLEANING AND SEALING EXIST JOINTS (CL3) | 484 LF | $60.00 | $19.19 | 3.13x | $19,751 |
| 500-7001 MOBILIZATION | 1 LS | $75,000.00 | $523,850.32 | 0.14x | -$448,850 |
| 100-7002 PREPARING ROW | 31.5 STA | $500.00 | $6,072.92 | 0.08x | -$175,547 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $2,500.00 | $11,585.04 | 0.22x | -$118,106 |
| 495-7001 RAISING EXIST STRUCT | 1 LS | $20,000.00 | $52,755.69 | 0.38x | -$32,756 |
STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 420-7060 CL C CONC (PILE ENCASEMENT) | 52.8 CY | $4,395.00 | $827.85 | 5.31x | $188,346 |
| 466-7183 WINGWALL (PW - 1) (HW=13 FT) | 2 EA | $149,000.00 | $70,348.54 | 2.12x | $157,303 |
| 132-7015 EMBANK (VEH)(OC)(TY B) | 4,039 CY | $54.00 | $25.35 | 2.13x | $115,703 |
| 431-7002 PNEUMATICALLY PLACED CONC (REPAIR) | 480 CF | $246.00 | $115.77 | 2.12x | $62,511 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 87 SY | $650.00 | $60.19 | 10.80x | $51,313 |
| 401-7001 FLOWABLE BACKFILL | 124 CY | $695.00 | $298.77 | 2.33x | $49,133 |
| 351-7002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(3") | 213 SY | $263.00 | $36.28 | 7.25x | $48,291 |
| 4076-7001 CONCRETE ARMOR UNIT (48") | 200 EA | $520.00 | $288.00 | 1.81x | $46,400 |
| 100-7002 PREPARING ROW | 31.5 STA | $1,000.00 | $6,072.92 | 0.16x | -$159,797 |
| 505-7001 TMA (STATIONARY) | 390 DAY | $1.00 | $217.57 | 0.00x | -$84,463 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $5,600.00 | $11,585.04 | 0.48x | -$77,806 |
| 505-7003 TMA (MOBILE OPERATION) | 195 DAY | $1.00 | $229.60 | 0.00x | -$44,576 |
| 495-7001 RAISING EXIST STRUCT | 1 LS | $15,000.00 | $52,755.69 | 0.28x | -$37,756 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 390 DAY | $1.00 | $87.82 | 0.01x | -$33,859 |