VA: 0915-00-283: BRG Repair District
0915-00-283 · let Jun 2, 2026 · Bexar, San Antonio · Bridge Maintenance
$4,555,821Low bid: TAYLOR BRIDGE LLC-51.2% vs estimate $9,327,085
$400,068Left on the table8.8% gap to the second bid
5BiddersSpread 65% low to high
234Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TAYLOR BRIDGE LLC | $4,555,821 | -51.2% | $400,068 | 5+$377,825 | 19-$1,440,012 | |
| 2 | RELMCO, INC. | $4,955,889 | +8.8% | -46.9% | $1,900,816 | 12+$740,341 | 13-$1,528,826 |
| 3 | RAGLE CONSTRUCTION, INC. | $6,856,705 | +50.5% | -26.5% | $358,485 | 17+$1,599,860 | 8-$1,257,646 |
| 4 | ROY JORGENSEN ASSOCIATES, INC. | $7,215,190 | +58.4% | -22.6% | $308,241 | 10+$1,750,058 | 9-$806,871 |
| 5 | SCR CIVIL CONSTRUCTION, LLC | $7,523,431 | +65.1% | -19.3% | 17+$1,819,101 | 6-$565,755 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
TAYLOR BRIDGE LLC vs RELMCO, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 499-7001 ADJUST STL SHOES | 237 EA | $3,500.00 | $1,100.00 | $4,475.46 | -$568,800 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 24 MO | $1,500.00 | $15,000.00 | $11,585.04 | $324,000 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 7,240 LF | $5.00 | $25.00 | $43.56 | $144,800 |
| 784-7034 REP STL BRIDGE MEMB (HEAT STRAIGHTEN-2) | 3 LS | $75,000.00 | $27,500.00 | $75,000.00 | -$142,500 |
| 512-7057 PORT CTB (REMOVE)(LOW PROF)(TY 1) | 7,240 LF | $5.00 | $23.00 | $11.18 | $130,320 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 728 SF | $350.00 | $175.00 | $150.68 | -$127,400 |
| 784-7031 REP STL BRIDGE MEMBER (HALF BEAM-1) | 1 LS | $55,000.00 | $165,000.00 | $55,000.00 | $110,000 |
| 784-7032 REP STL BRIDGE MEMBER (HALF BEAM-2) | 1 LS | $55,000.00 | $165,000.00 | $55,000.00 | $110,000 |
| 545-7014 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) | 6 EA | $25,000.00 | $8,350.00 | $8,780.51 | -$99,900 |
| 401-7001 FLOWABLE BACKFILL | 449.11 CY | $400.00 | $185.00 | $298.77 | -$96,559 |
| 100-7002 PREPARING ROW | 8 STA | $5,500.00 | $15,000.00 | $6,072.92 | $76,000 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 3,780 LF | $10.00 | $28.00 | $52.29 | $68,040 |
| 5011-7003 REM LEAD-COATING (6 IN STRIP) | 619 LF | $25.00 | $132.50 | $25.00 | $66,543 |
| 442-7010 STR STEEL (PEDESTAL) | 3,450 LB | $5.00 | $22.00 | $20.55 | $58,650 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 3,780 LF | $10.00 | $25.00 | $12.08 | $56,700 |
| 459-7006 GABION MATTRESSES (GALV)(9 IN) | 530 SY | $160.00 | $65.00 | $179.71 | -$50,350 |
| 780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT) | 911 LF | $55.00 | $105.00 | $76.83 | $45,550 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 600 SF | $5.00 | $80.00 | $28.47 | $45,000 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 2,926 CY | $25.00 | $38.00 | $18.71 | $38,038 |
| 451-7024 RETROFIT RAIL (TY SSTR) | 362 LF | $140.00 | $235.00 | $175.01 | $34,390 |
Positive: the low bidder was cheaper on that item. These 20 items account for $222,522 of the $400,068 gap.
TAYLOR BRIDGE LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 728 SF | $350.00 | $150.68 | 2.32x | $145,105 |
| 545-7014 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) | 6 EA | $25,000.00 | $8,780.51 | 2.85x | $97,317 |
| 784-7020 REP STL BRIDGE MBR (STRAIGHTEN MEMB) | 2 EA | $50,000.00 | $13,366.16 | 3.74x | $73,268 |
| 438-7004 CLEANING AND SEALING EXIST JOINTS (CL3) | 454 LF | $100.00 | $19.19 | 5.21x | $36,686 |
| 4010-7007 STEEL BRIDGE ZONE PAINTING REF STR #6 | 1 EA | $48,000.00 | $22,550.80 | 2.13x | $25,449 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 7,240 LF | $5.00 | $43.56 | 0.11x | -$279,180 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 24 MO | $1,500.00 | $11,585.04 | 0.13x | -$242,041 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 3,780 LF | $10.00 | $52.29 | 0.19x | -$159,852 |
| 4010-7012 STEEL BRIDGE ZONE PAINTING REF STR #11 | 1 EA | $12,000.00 | $107,333.33 | 0.11x | -$95,333 |
| 4010-7006 STEEL BRIDGE ZONE PAINTING REF STR #5 | 1 EA | $22,000.00 | $102,967.17 | 0.21x | -$80,967 |
| 4010-7011 STEEL BRIDGE ZONE PAINTING REF STR #10 | 1 EA | $12,000.00 | $82,925.67 | 0.14x | -$70,926 |
| 4010-7009 STEEL BRIDGE ZONE PAINTING REF STR #8 | 1 EA | $22,000.00 | $84,776.67 | 0.26x | -$62,777 |
| 442-7010 STR STEEL (PEDESTAL) | 3,450 LB | $5.00 | $20.55 | 0.24x | -$53,635 |
| 4010-7004 STEEL BRIDGE ZONE PAINTING REF STR #3 | 1 EA | $14,000.00 | $65,547.71 | 0.21x | -$51,548 |
| 4010-7002 STEEL BRIDGE ZONE PAINTING REF STR #1 | 1 EA | $10,000.00 | $58,500.00 | 0.17x | -$48,500 |
RELMCO, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 784-7031 REP STL BRIDGE MEMBER (HALF BEAM-1) | 1 LS | $165,000.00 | $55,000.00 | 3.00x | $110,000 |
| 784-7032 REP STL BRIDGE MEMBER (HALF BEAM-2) | 1 LS | $165,000.00 | $55,000.00 | 3.00x | $110,000 |
| 512-7057 PORT CTB (REMOVE)(LOW PROF)(TY 1) | 7,240 LF | $23.00 | $11.18 | 2.06x | $85,543 |
| 100-7002 PREPARING ROW | 8 STA | $15,000.00 | $6,072.92 | 2.47x | $71,417 |
| 5011-7003 REM LEAD-COATING (6 IN STRIP) | 619 LF | $132.50 | $25.00 | 5.30x | $66,543 |
| 784-7020 REP STL BRIDGE MBR (STRAIGHTEN MEMB) | 2 EA | $45,000.00 | $13,366.16 | 3.37x | $63,268 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 2,926 CY | $38.00 | $18.71 | 2.03x | $56,434 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 3,780 LF | $25.00 | $12.08 | 2.07x | $48,825 |
| 3008-7001 SOIL DENS & RAISING CONC SLABS (HDPF) | 200 LB | $200.00 | $6.70 | 29.87x | $38,661 |
| 4010-7007 STEEL BRIDGE ZONE PAINTING REF STR #6 | 1 EA | $55,385.00 | $22,550.80 | 2.46x | $32,834 |
| 499-7001 ADJUST STL SHOES | 237 EA | $1,100.00 | $4,475.46 | 0.25x | -$799,983 |
| 784-7034 REP STL BRIDGE MEMB (HEAT STRAIGHTEN-2) | 3 LS | $27,500.00 | $75,000.00 | 0.37x | -$142,500 |
| 4010-7012 STEEL BRIDGE ZONE PAINTING REF STR #11 | 1 EA | $13,515.00 | $107,333.33 | 0.13x | -$93,818 |
| 4010-7006 STEEL BRIDGE ZONE PAINTING REF STR #5 | 1 EA | $26,102.50 | $102,967.17 | 0.25x | -$76,865 |
| 4010-7011 STEEL BRIDGE ZONE PAINTING REF STR #10 | 1 EA | $13,515.00 | $82,925.67 | 0.16x | -$69,411 |
| 459-7006 GABION MATTRESSES (GALV)(9 IN) | 530 SY | $65.00 | $179.71 | 0.36x | -$60,795 |
| 4010-7009 STEEL BRIDGE ZONE PAINTING REF STR #8 | 1 EA | $24,910.00 | $84,776.67 | 0.29x | -$59,867 |
| 4010-7004 STEEL BRIDGE ZONE PAINTING REF STR #3 | 1 EA | $15,502.50 | $65,547.71 | 0.24x | -$50,045 |
| 4010-7002 STEEL BRIDGE ZONE PAINTING REF STR #1 | 1 EA | $11,925.00 | $58,500.00 | 0.20x | -$46,575 |
| 4010-7017 STEEL BRIDGE ZONE PAINTING REF STR #15 | 1 EA | $10,600.00 | $54,343.75 | 0.20x | -$43,744 |
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 8 STA | $60,000.00 | $6,072.92 | 9.88x | $431,417 |
| 495-7001 RAISING EXIST STRUCT | 2 LS | $200,000.00 | $52,755.69 | 3.79x | $294,489 |
| 784-7031 REP STL BRIDGE MEMBER (HALF BEAM-1) | 1 LS | $150,000.00 | $55,000.00 | 2.73x | $95,000 |
| 784-7032 REP STL BRIDGE MEMBER (HALF BEAM-2) | 1 LS | $150,000.00 | $55,000.00 | 2.73x | $95,000 |
| 5011-7011 REM LEAD-CONTAINING COATING REF STR 6 | 1 EA | $145,000.00 | $55,000.00 | 2.64x | $90,000 |
| 5011-7003 REM LEAD-COATING (6 IN STRIP) | 619 LF | $148.50 | $25.00 | 5.94x | $76,447 |
| 5011-7018 REM LEAD-CONTAINING COATING REF STR 13 | 1 EA | $105,000.00 | $36,000.00 | 2.92x | $69,000 |
| 446-7020 CLEAN AND PAINT EXIST STR (REF NO. 1) | 1 EA | $85,000.00 | $28,146.70 | 3.02x | $56,853 |
| 4010-7007 STEEL BRIDGE ZONE PAINTING REF STR #6 | 1 EA | $72,000.00 | $22,550.80 | 3.19x | $49,449 |
| 5011-7012 REM LEAD-CONTAINING COATING REF STR 7 | 1 EA | $75,000.00 | $26,000.00 | 2.88x | $49,000 |
| 499-7001 ADJUST STL SHOES | 237 EA | $1,250.00 | $4,475.46 | 0.28x | -$764,433 |
| 784-7034 REP STL BRIDGE MEMB (HEAT STRAIGHTEN-2) | 3 LS | $12,000.00 | $75,000.00 | 0.16x | -$189,000 |
| 4010-7012 STEEL BRIDGE ZONE PAINTING REF STR #11 | 1 EA | $40,000.00 | $107,333.33 | 0.37x | -$67,333 |
| 4010-7006 STEEL BRIDGE ZONE PAINTING REF STR #5 | 1 EA | $42,000.00 | $102,967.17 | 0.41x | -$60,967 |
| 4010-7009 STEEL BRIDGE ZONE PAINTING REF STR #8 | 1 EA | $30,000.00 | $84,776.67 | 0.35x | -$54,777 |
| 4010-7011 STEEL BRIDGE ZONE PAINTING REF STR #10 | 1 EA | $40,000.00 | $82,925.67 | 0.48x | -$42,926 |
| 780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT) | 911 LF | $30.00 | $76.83 | 0.39x | -$42,662 |
| 4010-7004 STEEL BRIDGE ZONE PAINTING REF STR #3 | 1 EA | $30,000.00 | $65,547.71 | 0.46x | -$35,548 |
ROY JORGENSEN ASSOCIATES, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 499-7001 ADJUST STL SHOES | 237 EA | $8,000.00 | $4,475.46 | 1.79x | $835,317 |
| 495-7001 RAISING EXIST STRUCT | 2 LS | $150,000.00 | $52,755.69 | 2.84x | $194,489 |
| 784-7031 REP STL BRIDGE MEMBER (HALF BEAM-1) | 1 LS | $213,675.00 | $55,000.00 | 3.89x | $158,675 |
| 784-7032 REP STL BRIDGE MEMBER (HALF BEAM-2) | 1 LS | $192,885.00 | $55,000.00 | 3.51x | $137,885 |
| 505-7001 TMA (STATIONARY) | 542 DAY | $450.00 | $217.57 | 2.07x | $125,976 |
| 5011-7003 REM LEAD-COATING (6 IN STRIP) | 619 LF | $150.00 | $25.00 | 6.00x | $77,375 |
| 784-7020 REP STL BRIDGE MBR (STRAIGHTEN MEMB) | 2 EA | $49,665.00 | $13,366.16 | 3.72x | $72,598 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 3,780 LF | $30.00 | $12.08 | 2.48x | $67,725 |
| 4010-7007 STEEL BRIDGE ZONE PAINTING REF STR #6 | 1 EA | $62,700.00 | $22,550.80 | 2.78x | $40,149 |
| 784-7033 REP STL BRIDGE MEMBER (GOUGE REPAIR) | 3 EA | $20,790.00 | $7,500.00 | 2.77x | $39,870 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 7,240 LF | $1.00 | $43.56 | 0.02x | -$308,140 |
| 4010-7012 STEEL BRIDGE ZONE PAINTING REF STR #11 | 1 EA | $15,300.00 | $107,333.33 | 0.14x | -$92,033 |
| 512-7057 PORT CTB (REMOVE)(LOW PROF)(TY 1) | 7,240 LF | $1.00 | $11.18 | 0.09x | -$73,737 |
| 4010-7006 STEEL BRIDGE ZONE PAINTING REF STR #5 | 1 EA | $29,550.00 | $102,967.17 | 0.29x | -$73,417 |
| 4010-7011 STEEL BRIDGE ZONE PAINTING REF STR #10 | 1 EA | $15,300.00 | $82,925.67 | 0.18x | -$67,626 |
| 4010-7009 STEEL BRIDGE ZONE PAINTING REF STR #8 | 1 EA | $28,200.00 | $84,776.67 | 0.33x | -$56,577 |
| 4010-7004 STEEL BRIDGE ZONE PAINTING REF STR #3 | 1 EA | $17,550.00 | $65,547.71 | 0.27x | -$47,998 |
| 4010-7002 STEEL BRIDGE ZONE PAINTING REF STR #1 | 1 EA | $13,500.00 | $58,500.00 | 0.23x | -$45,000 |
| 4010-7017 STEEL BRIDGE ZONE PAINTING REF STR #15 | 1 EA | $12,000.00 | $54,343.75 | 0.22x | -$42,344 |
SCR CIVIL CONSTRUCTION, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 24 MO | $27,000.00 | $11,585.04 | 2.33x | $369,959 |
| 401-7001 FLOWABLE BACKFILL | 449.11 CY | $830.00 | $298.77 | 2.78x | $238,583 |
| 784-7031 REP STL BRIDGE MEMBER (HALF BEAM-1) | 1 LS | $213,000.00 | $55,000.00 | 3.87x | $158,000 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 2,926 CY | $69.00 | $18.71 | 3.69x | $147,140 |
| 784-7032 REP STL BRIDGE MEMBER (HALF BEAM-2) | 1 LS | $192,000.00 | $55,000.00 | 3.49x | $137,000 |
| 5011-7003 REM LEAD-COATING (6 IN STRIP) | 619 LF | $190.00 | $25.00 | 7.60x | $102,135 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 728 SF | $275.00 | $150.68 | 1.83x | $90,505 |
| 784-7020 REP STL BRIDGE MBR (STRAIGHTEN MEMB) | 2 EA | $51,500.00 | $13,366.16 | 3.85x | $76,268 |
| 459-7006 GABION MATTRESSES (GALV)(9 IN) | 530 SY | $320.00 | $179.71 | 1.78x | $74,355 |
| 505-7003 TMA (MOBILE OPERATION) | 116 DAY | $800.00 | $229.60 | 3.48x | $66,167 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 7,240 LF | $15.00 | $43.56 | 0.34x | -$206,780 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 3,780 LF | $21.00 | $52.29 | 0.40x | -$118,272 |
| 4010-7012 STEEL BRIDGE ZONE PAINTING REF STR #11 | 1 EA | $27,700.00 | $107,333.33 | 0.26x | -$79,633 |
| 4010-7006 STEEL BRIDGE ZONE PAINTING REF STR #5 | 1 EA | $41,600.00 | $102,967.17 | 0.40x | -$61,367 |
| 4010-7011 STEEL BRIDGE ZONE PAINTING REF STR #10 | 1 EA | $27,700.00 | $82,925.67 | 0.33x | -$55,226 |
| 4010-7009 STEEL BRIDGE ZONE PAINTING REF STR #8 | 1 EA | $40,300.00 | $84,776.67 | 0.48x | -$44,477 |