2025 HSIP(COLLEGE ST.) INTERCONN SIGNALS
0920-38-301 · let Jun 2, 2026 · Jefferson, Beaumont · Safety Improvement Projects
$750,343Low bid: DECO CONTRACTORS, INC.-29.6% vs estimate $1,065,220
$28,634Left on the table3.8% gap to the second bid
8BiddersSpread 25% low to high
8Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | DECO CONTRACTORS, INC. | $750,343 | -29.6% | $28,634 | 1+$82,245 | 2-$492,090 | |
| 2 | CREACOM, INC. | $778,977 | +3.8% | -26.9% | $743 | 2+$99,716 | 2-$502,121 |
| 3 | VACA UNDERGROUND UTILITIES INC | $779,720 | +3.9% | -26.8% | $8,105 | 1+$140,745 | 2-$510,190 |
| 4 | TRAF-TEX, INC. | $787,825 | +5.0% | -26.0% | $87,636 | 1+$150,820 | 2-$481,039 |
| 5 | THIRD COAST SERVICES LLC | $875,461 | +16.7% | -17.8% | $17,431 | 3+$246,112 | 2-$472,151 |
| 6 | FLORIDA TRAFFIC CONTROL DEVICES, INC. | $892,892 | +19.0% | -16.2% | $5,597 | ||
| 7 | ALLSTATE SIGNAL & CONSTRUCTION, LLC | $898,489 | +19.7% | -15.7% | $35,731 | ||
| 8 | SELECT MAINTENANCE, L.L.C. | $934,220 | +24.5% | -12.3% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
DECO CONTRACTORS, INC. vs CREACOM, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 6102-7001 ATSC (TY 3) | 14 EA | $31,500.00 | $34,098.75 | $42,480.77 | $36,383 |
| 500-7001 MOBILIZATION | 1 LS | $75,000.00 | $54,528.37 | $523,850.32 | -$20,472 |
| 6052-7002 INSTALLATION OF CELLULAR ROUTER | 13 EA | $8,500.00 | $9,388.79 | $2,173.48 | $11,554 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $775.00 | $3,385.23 | $11,585.04 | $10,441 |
| 6006-7023 VIVDS CAM ASS VAR LNS(FURN AND INSTAL) | 9 EA | $4,800.00 | $4,032.60 | $3,888.37 | -$6,907 |
| 680-7011 INSTALL HWY TRF SIG (UPGRADE) | 8 EA | $8,500.00 | $7,706.61 | $8,031.16 | -$6,347 |
| 505-7001 TMA (STATIONARY) | 9 DAY | $195.00 | $874.98 | $217.57 | $6,120 |
| 6006-7007 VIVDS CABLING | 2,640 LF | $2.95 | $2.14 | $2.85 | -$2,138 |
Positive: the low bidder was cheaper on that item. These 8 items account for $28,634 of the $28,634 gap.
DECO CONTRACTORS, INC.: unbalanced items
Placed 1CREACOM, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 6052-7002 INSTALLATION OF CELLULAR ROUTER | 13 EA | $9,388.79 | $2,173.48 | 4.32x | $93,799 |
| 505-7001 TMA (STATIONARY) | 9 DAY | $874.98 | $217.57 | 4.02x | $5,917 |
| 500-7001 MOBILIZATION | 1 LS | $54,528.37 | $523,850.32 | 0.10x | -$469,322 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $3,385.23 | $11,585.04 | 0.29x | -$32,799 |
VACA UNDERGROUND UTILITIES INC: unbalanced items
Placed 3TRAF-TEX, INC.: unbalanced items
Placed 4THIRD COAST SERVICES LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 6052-7002 INSTALLATION OF CELLULAR ROUTER | 13 EA | $12,602.64 | $2,173.48 | 5.80x | $135,579 |
| 680-7011 INSTALL HWY TRF SIG (UPGRADE) | 8 EA | $19,531.92 | $8,031.16 | 2.43x | $92,006 |
| 6006-7007 VIVDS CABLING | 2,640 LF | $9.87 | $2.85 | 3.46x | $18,527 |
| 500-7001 MOBILIZATION | 1 LS | $87,546.07 | $523,850.32 | 0.17x | -$436,304 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $2,623.38 | $11,585.04 | 0.23x | -$35,847 |