FY26 Overlay (Hidalgo County)
6491-09-001 · let Jun 3, 2026 · Hidalgo, Pharr · Routine Maintenance Project
$6,198,303Low bid: IOC COMPANY LLC-9.1% vs estimate $6,820,553
$15,779Left on the table0.3% gap to the second bid
3BiddersSpread 15% low to high
47Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | IOC COMPANY LLC | $6,198,303 | -9.1% | $15,779 | 0 | 3-$963,970 | |
| 2 | FOREMOST PAVING, INC. | $6,214,082 | +0.3% | -8.9% | $893,412 | 0 | 1-$323,850 |
| 3 | EARTHWORKS ENTERPRISE | $7,107,494 | +14.7% | 4.2% | 0 | 3-$661,864 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
IOC COMPANY LLC vs FOREMOST PAVING, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 344-7064 SP MIXES SP-D SAC-A PG76-22 | 38,362 TON | $127.15 | $110.00 | $129.17 | -$657,908 |
| 354-7051 PLANE ASPH CONC PAV(2") | 336,517 SY | $0.7500 | $1.67 | $1.86 | $309,596 |
| 500-7001 MOBILIZATION | 1 LS | $10,000.00 | $200,000.00 | $523,850.32 | $190,000 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 5,914 SY | $50.00 | $74.75 | $60.19 | $146,372 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $500.00 | $5,875.00 | $11,585.04 | $37,625 |
| 6008-7003 RVDS (PRESENCE AND ADVANCE DETECTION) | 39 EA | $8,182.42 | $7,654.60 | $10,685.77 | -$20,585 |
| 506-7044 BIODEG EROSN CONT LOGS (INSTL) (12") | 2,352 LF | $2.50 | $5.61 | $5.23 | $7,315 |
| 666-7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 8,315 LF | $6.00 | $6.87 | $7.19 | $7,234 |
| 672-7004 REFL PAV MRKR TY II-A-A | 2,686 EA | $6.00 | $3.44 | $3.97 | -$6,876 |
| 505-7001 TMA (STATIONARY) | 134 DAY | $1.00 | $50.00 | $217.57 | $6,566 |
| 668-7091 PREFAB PM TY C (W)(ARROW) | 85 EA | $125.00 | $196.95 | $201.69 | $6,116 |
| 688-7004 VEH LP DETECT (SAWCUT) | 7,413 LF | $10.77 | $10.10 | $13.72 | -$4,967 |
| 3007-7001 BONDING COURSE | 23,555 GAL | $3.00 | $2.81 | $3.32 | -$4,475 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 28,074 LF | $0.7800 | $0.6300 | $0.4757 | -$4,211 |
| 668-7103 PREFAB PM TY C (W)(WORD) | 79 EA | $175.00 | $222.20 | $249.54 | $3,729 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 4 EA | $3,676.62 | $4,542.98 | $3,190.07 | $3,465 |
| 672-7002 REFL PAV MRKR TY I-C | 1,446 EA | $6.00 | $3.84 | $4.04 | -$3,123 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 16 CY | $630.00 | $470.00 | $616.83 | -$2,560 |
| 666-7420 REFL PAV MRK TY I (Y)6"(BRK)(100MIL) | 12,730 LF | $0.8200 | $0.6300 | $0.4829 | -$2,419 |
| 506-7046 BIODEG EROSN CONT LOGS (REMOVE) | 2,352 LF | $0.1000 | $1.01 | $1.29 | $2,140 |
Positive: the low bidder was cheaper on that item. These 20 items account for $13,032 of the $15,779 gap.
IOC COMPANY LLC: unbalanced items
Placed 1FOREMOST PAVING, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |