IH 20 SIX LANES NEAR JUDGE ELY TO SH 351
0006-06-109 · let Jun 3, 2026 · Taylor, Abilene · Widen Freeway
$136,705,244Low bid: FNF CONSTRUCTION, INC.+8.2% vs estimate $126,337,929
$3,475,673Left on the table2.5% gap to the second bid
3BiddersSpread 13% low to high
368Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | FNF CONSTRUCTION, INC. | $136,705,244 | 8.2% | $3,475,673 | 4+$16,898,146 | 2-$4,521,873 | |
| 2 | JAMES CONSTRUCTION GROUP, LLC | $140,180,917 | +2.5% | 11.0% | $14,721,937 | 4+$24,090,404 | 0 |
| 3 | WEBBER, LLC | $154,902,854 | +13.3% | 22.6% | 6+$45,717,099 | 1-$2,890,244 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
FNF CONSTRUCTION, INC. vs JAMES CONSTRUCTION GROUP, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 72.43 STA | $500.00 | $150,000.00 | $6,072.92 | $10,828,285 |
| 132-7007 EMBANK (FNL)(OC)(TY C1) | 192,911 CY | $58.00 | $85.27 | $50.95 | $5,260,683 |
| 360-7007 CONC PVMT (CRCP) (13") | 84,216 SY | $149.00 | $111.78 | $97.71 | -$3,134,520 |
| 360-7004 CONC PVMT (CRCP) (10") | 66,717 SY | $138.00 | $97.62 | $87.39 | -$2,694,032 |
| 403-7001 TEMPORARY SPL SHORING | 65,156 SF | $2.00 | $41.49 | $25.56 | $2,573,010 |
| 462-7023 CONC BOX CULV (8 FT X 6 FT) | 594 LF | $4,700.00 | $667.57 | $1,500.69 | -$2,395,263 |
| 423-7001 RETAINING WALL (MSE) | 201,671 SF | $54.00 | $45.44 | $74.07 | -$1,726,304 |
| 500-7001 MOBILIZATION | 1 LS | $13,000,000.00 | $11,482,639.83 | $523,850.32 | -$1,517,360 |
| 400-7010 CEM STABIL BKFL | 13,441.4 CY | $100.00 | $201.99 | $138.14 | $1,370,888 |
| 132-7010 EMBANK (FNL)(DC)(TY C2) | 241,286 CY | $10.00 | $15.26 | $22.38 | $1,269,164 |
| 425-7004 PRESTR CONC GIRDER (TX46) | 19,494.59 LF | $290.00 | $225.86 | $236.72 | -$1,250,383 |
| 6016-7002 TEMP SPEED MONITOR (2 SYS) | 1,650 DAY | $17.00 | $750.00 | $26.65 | $1,209,450 |
| 416-7006 DRILL SHAFT (36 IN) | 9,299 LF | $325.00 | $197.08 | $280.58 | -$1,189,528 |
| 422-7002 REINF CONC SLAB (HPC) | 183,676 SF | $33.00 | $26.87 | $26.91 | -$1,125,934 |
| 468-7002 THERMOPLASTIC PIPE (PP) (24") | 5,907 LF | $120.00 | $0.00 | $108.87 | -$708,840 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 14,420 LF | $40.00 | $87.54 | $43.56 | $685,527 |
| 468-7004 THERMOPLASTIC PIPE (PP) (36") | 2,573 LF | $200.00 | $0.00 | $147.48 | -$514,600 |
| 432-7001 RIPRAP (CONC)(4 IN) | 2,632.48 CY | $550.00 | $361.63 | $573.24 | -$495,880 |
| 450-7024 RAIL (TY SSTR) | 18,614 LF | $97.00 | $71.62 | $69.92 | -$472,423 |
| 508-7003 CONSTRUCTING DETOURS (TY1) | 46,500 SY | $130.00 | $140.04 | $101.74 | $466,860 |
Positive: the low bidder was cheaper on that item. These 20 items account for $6,438,800 of the $3,475,673 gap.
FNF CONSTRUCTION, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $13,000,000.00 | $523,850.32 | 24.82x | $12,476,150 |
| 462-7023 CONC BOX CULV (8 FT X 6 FT) | 594 LF | $4,700.00 | $1,500.69 | 3.13x | $1,900,391 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 30,930 LF | $110.00 | $52.29 | 2.10x | $1,785,007 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 40 MO | $30,000.00 | $11,585.04 | 2.59x | $736,598 |
| 132-7010 EMBANK (FNL)(DC)(TY C2) | 241,286 CY | $10.00 | $22.38 | 0.45x | -$2,986,759 |
| 403-7001 TEMPORARY SPL SHORING | 65,156 SF | $2.00 | $25.56 | 0.08x | -$1,535,114 |
JAMES CONSTRUCTION GROUP, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $11,482,639.83 | $523,850.32 | 21.92x | $10,958,790 |
| 100-7002 PREPARING ROW | 72.43 STA | $150,000.00 | $6,072.92 | 24.70x | $10,424,638 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 30,930 LF | $101.22 | $52.29 | 1.94x | $1,513,442 |
| 6016-7002 TEMP SPEED MONITOR (2 SYS) | 1,650 DAY | $750.00 | $26.65 | 28.15x | $1,193,534 |
WEBBER, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 72.43 STA | $213,865.00 | $6,072.92 | 35.22x | $15,050,380 |
| 500-7001 MOBILIZATION | 1 LS | $15,490,200.00 | $523,850.32 | 29.57x | $14,966,350 |
| 132-7007 EMBANK (FNL)(OC)(TY C1) | 192,911 CY | $103.00 | $50.95 | 2.02x | $10,041,808 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 40 MO | $95,325.00 | $11,585.04 | 8.23x | $3,349,598 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 30,930 LF | $94.75 | $52.29 | 1.81x | $1,313,325 |
| 423-7012 RETAINING WALL (TEMP WALL) | 48,437 SF | $43.50 | $22.94 | 1.90x | $995,637 |
| 132-7010 EMBANK (FNL)(DC)(TY C2) | 241,286 CY | $10.40 | $22.38 | 0.46x | -$2,890,244 |