Various Bridge Repairs for NHAO
0912-72-842 · let Jul 1, 2026 · Harris, Houston · Bridge Widening or Rehabilitation
$1,538,016Low bid: REAR CONTRACTORS LLC-1.0% vs estimate $1,553,482
$557,162Left on the table36.2% gap to the second bid
8BiddersSpread 114% low to high
24Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | REAR CONTRACTORS LLC | $1,538,016 | -1.0% | $557,162 | 5+$71,256 | 3-$1,376,867 | |
| 2 | RAGLE CONSTRUCTION, INC. | $2,095,178 | +36.2% | 34.9% | $249,458 | 4+$265,324 | 3-$365,221 |
| 3 | STRUCTURAL INTEGRITY GROUP LLC | $2,344,636 | +52.4% | 50.9% | $137,486 | 8+$545,983 | 1-$280,850 |
| 4 | MB WESTERN CONSTRUCTION CO. | $2,482,121 | +61.4% | 59.8% | $68,456 | 6+$635,758 | 1-$273,850 |
| 5 | SCR CIVIL CONSTRUCTION, LLC | $2,550,577 | +65.8% | 64.2% | $67,044 | 7+$688,134 | 2-$378,591 |
| 6 | CROSS PLUS CONSTRUCTION, LLC | $2,617,621 | +70.2% | 68.5% | $279,438 | ||
| 7 | MC2 CIVIL, LLC | $2,897,058 | +88.4% | 86.5% | $401,342 | ||
| 8 | SOUTHERN ROAD & BRIDGE, LLC | $3,298,400 | +114.5% | 112.3% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
REAR CONTRACTORS LLC vs RAGLE CONSTRUCTION, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 446-7002 CLEAN & PAINT EXIST STR (SYSTEM II) | 6 LS | $140,000.00 | $201,000.00 | $301,243.48 | $366,000 |
| 500-7001 MOBILIZATION | 1 LS | $140,000.00 | $230,000.00 | $523,850.32 | $90,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $10,000.00 | $55,000.00 | $11,585.04 | $90,000 |
| 505-7001 TMA (STATIONARY) | 118 DAY | $1.00 | $750.00 | $217.57 | $88,382 |
| 784-7002 REP STL BRIDGE MEMBER (BEAM) | 5 EA | $15,000.00 | $1,600.00 | $9,648.10 | -$67,000 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 88 DAY | $1.00 | $750.00 | $87.82 | $65,912 |
| 784-7008 REP STL BRIDGE MEMBER (BEARINGS) | 3 EA | $7,500.00 | $23,000.00 | $3,868.09 | $46,500 |
| 784-7022 REP STL BRIDGE MBR (WELD REPAIR) | 16 EA | $4,000.00 | $1,450.00 | $3,395.64 | -$40,800 |
| 784-7018 REP STL BRIDGE MEMBER (BOX CAP) | 44 EA | $3,000.00 | $2,500.00 | $2,239.58 | -$22,000 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 121.5 SF | $350.00 | $200.00 | $150.68 | -$18,225 |
| 786-7001 CARBON FIBER REINF POLYMER PROTECTION | 550 SF | $50.00 | $75.00 | $72.02 | $13,750 |
| 780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT) | 200 LF | $139.00 | $75.00 | $76.83 | -$12,800 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 51.5 SF | $500.00 | $275.00 | $192.68 | -$11,588 |
| 438-7007 CLEANING AND SEALING EXIST JOINTS (CL7) | 355 LF | $55.00 | $23.00 | $38.57 | -$11,360 |
| 784-7021 REP STL BRIDGE MBR (ANCHOR BOLT NUTS) | 8 EA | $1,200.00 | $240.00 | $302.07 | -$7,680 |
| 785-7005 BRIDGE JOINT REPAIR (SEJ) | 81 LF | $400.00 | $490.00 | $385.82 | $7,290 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 25 CY | $500.00 | $275.00 | $184.74 | -$5,625 |
| 784-7003 REP STL BRIDGE MEMBER (DIAPHRAGM) | 5 EA | $5,000.00 | $4,025.00 | $4,312.75 | -$4,875 |
| 442-7008 STR STEEL (MISCELLANEOUS BRIDGE) | 77 LB | $100.00 | $50.00 | $6.21 | -$3,850 |
| 401-7001 FLOWABLE BACKFILL | 5 CY | $1,000.00 | $500.00 | $298.77 | -$2,500 |
Positive: the low bidder was cheaper on that item. These 20 items account for $559,532 of the $557,162 gap.
REAR CONTRACTORS LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 121.5 SF | $350.00 | $150.68 | 2.32x | $24,217 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 51.5 SF | $500.00 | $192.68 | 2.59x | $15,827 |
| 780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT) | 200 LF | $139.00 | $76.83 | 1.81x | $12,434 |
| 784-7008 REP STL BRIDGE MEMBER (BEARINGS) | 3 EA | $7,500.00 | $3,868.09 | 1.94x | $10,896 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 25 CY | $500.00 | $184.74 | 2.71x | $7,882 |
| 446-7002 CLEAN & PAINT EXIST STR (SYSTEM II) | 6 LS | $140,000.00 | $301,243.48 | 0.46x | -$967,461 |
| 500-7001 MOBILIZATION | 1 LS | $140,000.00 | $523,850.32 | 0.27x | -$383,850 |
| 505-7001 TMA (STATIONARY) | 118 DAY | $1.00 | $217.57 | 0.00x | -$25,555 |
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $55,000.00 | $11,585.04 | 4.75x | $86,830 |
| 505-7001 TMA (STATIONARY) | 118 DAY | $750.00 | $217.57 | 3.45x | $62,827 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 88 DAY | $750.00 | $87.82 | 8.54x | $58,272 |
| 784-7008 REP STL BRIDGE MEMBER (BEARINGS) | 3 EA | $23,000.00 | $3,868.09 | 5.95x | $57,396 |
| 500-7001 MOBILIZATION | 1 LS | $230,000.00 | $523,850.32 | 0.44x | -$293,850 |
| 784-7002 REP STL BRIDGE MEMBER (BEAM) | 5 EA | $1,600.00 | $9,648.10 | 0.17x | -$40,241 |
| 784-7022 REP STL BRIDGE MBR (WELD REPAIR) | 16 EA | $1,450.00 | $3,395.64 | 0.43x | -$31,130 |
STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 784-7008 REP STL BRIDGE MEMBER (BEARINGS) | 3 EA | $85,000.00 | $3,868.09 | 21.97x | $243,396 |
| 784-7018 REP STL BRIDGE MEMBER (BOX CAP) | 44 EA | $4,500.00 | $2,239.58 | 2.01x | $99,458 |
| 786-7001 CARBON FIBER REINF POLYMER PROTECTION | 550 SF | $166.00 | $72.02 | 2.31x | $51,691 |
| 785-7005 BRIDGE JOINT REPAIR (SEJ) | 81 LF | $1,020.00 | $385.82 | 2.64x | $51,368 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $33,500.00 | $11,585.04 | 2.89x | $43,830 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 121.5 SF | $361.00 | $150.68 | 2.40x | $25,554 |
| 780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT) | 200 LF | $164.00 | $76.83 | 2.13x | $17,434 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 51.5 SF | $450.00 | $192.68 | 2.34x | $13,252 |
| 500-7001 MOBILIZATION | 1 LS | $243,000.00 | $523,850.32 | 0.46x | -$280,850 |
MB WESTERN CONSTRUCTION CO.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 784-7008 REP STL BRIDGE MEMBER (BEARINGS) | 3 EA | $142,000.00 | $3,868.09 | 36.71x | $414,396 |
| 784-7018 REP STL BRIDGE MEMBER (BOX CAP) | 44 EA | $4,950.00 | $2,239.58 | 2.21x | $119,258 |
| 784-7022 REP STL BRIDGE MBR (WELD REPAIR) | 16 EA | $6,150.00 | $3,395.64 | 1.81x | $44,070 |
| 784-7003 REP STL BRIDGE MEMBER (DIAPHRAGM) | 5 EA | $9,300.00 | $4,312.75 | 2.16x | $24,936 |
| 442-7008 STR STEEL (MISCELLANEOUS BRIDGE) | 77 LB | $246.00 | $6.21 | 39.59x | $18,464 |
| 780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT) | 200 LF | $150.00 | $76.83 | 1.95x | $14,634 |
| 500-7001 MOBILIZATION | 1 LS | $250,000.00 | $523,850.32 | 0.48x | -$273,850 |
SCR CIVIL CONSTRUCTION, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 784-7018 REP STL BRIDGE MEMBER (BOX CAP) | 44 EA | $8,000.00 | $2,239.58 | 3.57x | $253,458 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $118,500.00 | $11,585.04 | 10.23x | $213,830 |
| 784-7008 REP STL BRIDGE MEMBER (BEARINGS) | 3 EA | $37,000.00 | $3,868.09 | 9.57x | $99,396 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 121.5 SF | $500.00 | $150.68 | 3.32x | $42,442 |
| 785-7005 BRIDGE JOINT REPAIR (SEJ) | 81 LF | $850.00 | $385.82 | 2.20x | $37,598 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 51.5 SF | $625.00 | $192.68 | 3.24x | $22,264 |
| 438-7007 CLEANING AND SEALING EXIST JOINTS (CL7) | 355 LF | $92.50 | $38.57 | 2.40x | $19,145 |
| 500-7001 MOBILIZATION | 1 LS | $184,000.00 | $523,850.32 | 0.35x | -$339,850 |
| 784-7002 REP STL BRIDGE MEMBER (BEAM) | 5 EA | $1,900.00 | $9,648.10 | 0.20x | -$38,741 |