FY 27 Amarillo Area HMAC
6505-04-001 · let Jul 29, 2026 · Randall, Amarillo · Material Maintenance Project
$625,000Low bid: RK HALL, LLC0.0% vs estimate $625,000
$51,375Left on the table8.2% gap to the second bid
2BiddersSpread 8% low to high
7Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RK HALL, LLC | $625,000 | 0.0% | $51,375 | 0 | 0 | |
| 2 | J. LEE MILLIGAN, INC. | $676,375 | +8.2% | 8.2% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
RK HALL, LLC vs J. LEE MILLIGAN, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8011-7055 D-GR HMA TY D PG 64-22 (PICKUP) | 1,500 TON | $115.00 | $123.50 | $89.12 | $12,750 |
| 8011-7110 D-GR HMA TY D PG 64-28 (DEL) SITE 1 | 500 TON | $130.00 | $151.85 | $135.43 | $10,925 |
| 8011-7111 D-GR HMA TY D PG 64-28 (DEL) SITE 2 | 500 TON | $135.00 | $156.60 | $140.86 | $10,800 |
| 8011-7112 D-GR HMA TY D PG 64-28 (DEL) SITE 3 | 500 TON | $145.00 | $161.35 | $151.29 | $8,175 |
| 8011-7113 D-GR HMA TY D PG 64-28 (DEL) SITE 4 | 500 TON | $155.00 | $166.00 | $161.71 | $5,500 |
| 8011-7114 D-GR HMA TY D PG 64-28 (DEL) SITE 5 | 500 TON | $165.00 | $170.85 | $172.43 | $2,925 |
| 8011-7115 D-GR HMA TY D PG 64-28 (DEL) SITE 6 | 500 TON | $175.00 | $175.60 | $183.86 | $300 |
Positive: the low bidder was cheaper on that item. These 7 items account for $51,375 of the $51,375 gap.