Site Specific Mill & Inlay FY27
6502-48-001 · let Jul 2, 2026 · Lamar, Paris · Routine Maintenance Project - Sealed
$6,261,324Low bid: RK HALL, LLC-2.6% vs estimate $6,428,873
$334,716Left on the table5.3% gap to the second bid
3BiddersSpread 7% low to high
34Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RK HALL, LLC | $6,261,324 | -2.6% | $334,716 | 2+$248,348 | 0 | |
| 2 | AUSTIN BRIDGE & ROAD SERVICES, LP | $6,596,041 | +5.3% | 2.6% | $102,408 | 0 | 0 |
| 3 | DRAKE COMPANIES LLC | $6,698,449 | +7.0% | 4.2% | 0 | 1-$60,680 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
RK HALL, LLC vs AUSTIN BRIDGE & ROAD SERVICES, LP, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 341-7034 D-GR HMA TY-C SAC-A PG64-22(EXEMPT) | 19,025 TON | $123.26 | $142.75 | $136.91 | $370,797 |
| 341-7062 D-GR HMA TY-D SAC-A PG64-22 (EXEMPT) | 13,830 TON | $126.92 | $151.46 | $128.68 | $339,388 |
| 500-7001 MOBILIZATION | 1 LS | $300,000.00 | $623,731.00 | $523,850.32 | $323,731 |
| 354-7033 PLANE ASPH CONC PAV(0" TO 3") | 272,671 SY | $3.61 | $2.50 | $3.11 | -$302,665 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $36,904.15 | $13,474.96 | $11,585.04 | -$187,434 |
| 505-7001 TMA (STATIONARY) | 110 DAY | $633.89 | $0.0100 | $217.57 | -$69,727 |
| 341-7082 TACK COAT | 27,184 GAL | $6.36 | $4.21 | $3.93 | -$58,446 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 131 DAY | $255.74 | $143.45 | $87.82 | -$14,710 |
| 666-7422 REFL PAV MRK TY I (Y)6"(SLD)(090MIL) | 83,909 LF | $0.6800 | $0.5300 | $0.5014 | -$12,586 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 734 SY | $83.73 | $100.84 | $60.19 | $12,559 |
| 666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL) | 20,640 LF | $1.31 | $0.7300 | $0.6515 | -$11,971 |
| 666-7270 RE PROFILE PM TY I(Y)6"(SLD)(100MIL) | 18,704 LF | $1.31 | $0.7300 | $0.6629 | -$10,848 |
| 666-7410 REFL PAV MRK TY I (W)6"(SLD)(090MIL) | 64,232 LF | $0.6800 | $0.5300 | $0.4886 | -$9,635 |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) | 43,690 LF | $0.2600 | $0.0600 | $0.2040 | -$8,738 |
| 662-7113 WK ZN PAV MRK SHT TERM (TAB)TY Y | 4,825 EA | $2.14 | $0.5400 | $1.11 | -$7,720 |
| 533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE) | 29,972 LF | $0.2600 | $0.0800 | $0.2394 | -$5,395 |
| 164-7002 BROADCAST SEED (PERM_RURAL_CLAY) | 6,133 SY | $0.5300 | $1.40 | $0.3117 | $5,336 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 3,082 EA | $2.14 | $0.5400 | $1.03 | -$4,931 |
| 168-7001 VEGETATIVE WATERING | 52 TGL | $82.17 | $1.00 | $8.43 | -$4,221 |
| 666-7274 RE PROFILE PM TY I(Y)6"(BRK)(100MIL) | 2,410 LF | $2.10 | $0.7500 | $0.6738 | -$3,254 |
Positive: the low bidder was cheaper on that item. These 20 items account for $339,531 of the $334,716 gap.
RK HALL, LLC: unbalanced items
Placed 1DRAKE COMPANIES LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $4,000.00 | $11,585.04 | 0.35x | -$60,680 |