Bid Tab X-ray: 6501-20-001

Jul 15, 2026 · Wichita Sign up free
Set your company to personalize scores

On-Call Cable Barrier Repair FY27

6501-20-001 · let Jul 15, 2026 · Wichita, Wichita Falls · Routine Maintenance Project - Sealed

$600,844Low bid: AUSTIN BARRICADE COMPANY, L.L.C.-3.0% vs estimate $619,618
$11,436Left on the table1.9% gap to the second bid
4BiddersSpread 25% low to high
10Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1AUSTIN BARRICADE COMPANY, L.L.C. $600,844-3.0% $11,436 4+$157,475 4-$76,333
2MARCOM'S MOWING SERVICE, LLC $612,280+1.9%-1.2% $84,618 3+$56,619 2-$53,979
3E.V.G. ENTERPRISE $696,898+16.0%12.5% $52,632 1+$18,499 3-$44,597
4HJC FARMS, INC. $749,530+24.7%21.0% 3+$90,965 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.

Where the job was won

AUSTIN BARRICADE COMPANY, L.L.C. vs MARCOM'S MOWING SERVICE, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
771-7025 REPLACE LINE OR TERMINAL POST (VALTIR)208 EA $843.00$240.00$215.97 -$125,424
771-7026 REPLACE LINE OR TERMINAL POST (GIBRAL)1,872 EA $200.00$250.00$176.83 $93,600
771-7029 REPLACE CABLE RELEASE POST41 EA $1.00$1,000.00$148.81 $40,959
771-7033 SPLICE CABLE15 EA $1,200.00$500.00$342.77 -$10,500
771-7030 CHECK AND RE-TENSION CABLE SYSTEM65 EA $100.00$200.00$350.67 $6,500
500-7033 MOBILIZATION (EMERGENCY)10 EA $1,900.00$2,500.00$844.81 $6,000
771-7031 REPLACE CABLE763 LF $8.00$10.00$3.23 $1,526
771-7032 REMOVE CABLE BARRIER SYSTEM25 LF $50.00$1.00$54.08 -$1,225
500-7002 MOBILIZATION (CALLOUT)25 EA $1.00$1.00$600.85 $0
505-7001 TMA (STATIONARY)180 DAY $1.00$1.00$217.57 $0

Positive: the low bidder was cheaper on that item. These 10 items account for $11,436 of the $11,436 gap.

AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
771-7025 REPLACE LINE OR TERMINAL POST (VALTIR)208 EA $843.00$215.973.90x$130,423
771-7033 SPLICE CABLE15 EA $1,200.00$342.773.50x$12,858
500-7033 MOBILIZATION (EMERGENCY)10 EA $1,900.00$844.812.25x$10,552
771-7031 REPLACE CABLE763 LF $8.00$3.232.48x$3,642
505-7001 TMA (STATIONARY)180 DAY $1.00$217.570.00x-$38,983
771-7030 CHECK AND RE-TENSION CABLE SYSTEM65 EA $100.00$350.670.29x-$16,294
500-7002 MOBILIZATION (CALLOUT)25 EA $1.00$600.850.00x-$14,996
771-7029 REPLACE CABLE RELEASE POST41 EA $1.00$148.810.01x-$6,060

MARCOM'S MOWING SERVICE, LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
771-7029 REPLACE CABLE RELEASE POST41 EA $1,000.00$148.816.72x$34,899
500-7033 MOBILIZATION (EMERGENCY)10 EA $2,500.00$844.812.96x$16,552
771-7031 REPLACE CABLE763 LF $10.00$3.233.10x$5,168
505-7001 TMA (STATIONARY)180 DAY $1.00$217.570.00x-$38,983
500-7002 MOBILIZATION (CALLOUT)25 EA $1.00$600.850.00x-$14,996

E.V.G. ENTERPRISE: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
771-7029 REPLACE CABLE RELEASE POST41 EA $600.00$148.814.03x$18,499
505-7001 TMA (STATIONARY)180 DAY $100.00$217.570.46x-$21,163
500-7002 MOBILIZATION (CALLOUT)25 EA $1.00$600.850.00x-$14,996
500-7033 MOBILIZATION (EMERGENCY)10 EA $1.00$844.810.00x-$8,438

HJC FARMS, INC.: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
771-7032 REMOVE CABLE BARRIER SYSTEM25 LF $2,500.00$54.0846.23x$61,148
771-7029 REPLACE CABLE RELEASE POST41 EA $750.00$148.815.04x$24,649
771-7031 REPLACE CABLE763 LF $10.00$3.233.10x$5,168