On-Call Cable Barrier Repair FY27
6501-20-001 · let Jul 15, 2026 · Wichita, Wichita Falls · Routine Maintenance Project - Sealed
$600,844Low bid: AUSTIN BARRICADE COMPANY, L.L.C.-3.0% vs estimate $619,618
$11,436Left on the table1.9% gap to the second bid
4BiddersSpread 25% low to high
10Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | AUSTIN BARRICADE COMPANY, L.L.C. | $600,844 | -3.0% | $11,436 | 4+$157,475 | 4-$76,333 | |
| 2 | MARCOM'S MOWING SERVICE, LLC | $612,280 | +1.9% | -1.2% | $84,618 | 3+$56,619 | 2-$53,979 |
| 3 | E.V.G. ENTERPRISE | $696,898 | +16.0% | 12.5% | $52,632 | 1+$18,499 | 3-$44,597 |
| 4 | HJC FARMS, INC. | $749,530 | +24.7% | 21.0% | 3+$90,965 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
AUSTIN BARRICADE COMPANY, L.L.C. vs MARCOM'S MOWING SERVICE, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 771-7025 REPLACE LINE OR TERMINAL POST (VALTIR) | 208 EA | $843.00 | $240.00 | $215.97 | -$125,424 |
| 771-7026 REPLACE LINE OR TERMINAL POST (GIBRAL) | 1,872 EA | $200.00 | $250.00 | $176.83 | $93,600 |
| 771-7029 REPLACE CABLE RELEASE POST | 41 EA | $1.00 | $1,000.00 | $148.81 | $40,959 |
| 771-7033 SPLICE CABLE | 15 EA | $1,200.00 | $500.00 | $342.77 | -$10,500 |
| 771-7030 CHECK AND RE-TENSION CABLE SYSTEM | 65 EA | $100.00 | $200.00 | $350.67 | $6,500 |
| 500-7033 MOBILIZATION (EMERGENCY) | 10 EA | $1,900.00 | $2,500.00 | $844.81 | $6,000 |
| 771-7031 REPLACE CABLE | 763 LF | $8.00 | $10.00 | $3.23 | $1,526 |
| 771-7032 REMOVE CABLE BARRIER SYSTEM | 25 LF | $50.00 | $1.00 | $54.08 | -$1,225 |
| 500-7002 MOBILIZATION (CALLOUT) | 25 EA | $1.00 | $1.00 | $600.85 | $0 |
| 505-7001 TMA (STATIONARY) | 180 DAY | $1.00 | $1.00 | $217.57 | $0 |
Positive: the low bidder was cheaper on that item. These 10 items account for $11,436 of the $11,436 gap.
AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7025 REPLACE LINE OR TERMINAL POST (VALTIR) | 208 EA | $843.00 | $215.97 | 3.90x | $130,423 |
| 771-7033 SPLICE CABLE | 15 EA | $1,200.00 | $342.77 | 3.50x | $12,858 |
| 500-7033 MOBILIZATION (EMERGENCY) | 10 EA | $1,900.00 | $844.81 | 2.25x | $10,552 |
| 771-7031 REPLACE CABLE | 763 LF | $8.00 | $3.23 | 2.48x | $3,642 |
| 505-7001 TMA (STATIONARY) | 180 DAY | $1.00 | $217.57 | 0.00x | -$38,983 |
| 771-7030 CHECK AND RE-TENSION CABLE SYSTEM | 65 EA | $100.00 | $350.67 | 0.29x | -$16,294 |
| 500-7002 MOBILIZATION (CALLOUT) | 25 EA | $1.00 | $600.85 | 0.00x | -$14,996 |
| 771-7029 REPLACE CABLE RELEASE POST | 41 EA | $1.00 | $148.81 | 0.01x | -$6,060 |
MARCOM'S MOWING SERVICE, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7029 REPLACE CABLE RELEASE POST | 41 EA | $1,000.00 | $148.81 | 6.72x | $34,899 |
| 500-7033 MOBILIZATION (EMERGENCY) | 10 EA | $2,500.00 | $844.81 | 2.96x | $16,552 |
| 771-7031 REPLACE CABLE | 763 LF | $10.00 | $3.23 | 3.10x | $5,168 |
| 505-7001 TMA (STATIONARY) | 180 DAY | $1.00 | $217.57 | 0.00x | -$38,983 |
| 500-7002 MOBILIZATION (CALLOUT) | 25 EA | $1.00 | $600.85 | 0.00x | -$14,996 |