On-Call MBGF FY27
6501-19-001 · let Jul 15, 2026 · Wichita, Wichita Falls · Routine Maintenance Project - Sealed
$779,554Low bid: AUSTIN BARRICADE COMPANY, L.L.C.-12.5% vs estimate $890,600
$650Left on the table0.1% gap to the second bid
4BiddersSpread 33% low to high
10Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | AUSTIN BARRICADE COMPANY, L.L.C. | $779,554 | -12.5% | $650 | 2+$124,354 | 4-$121,116 | |
| 2 | MARCOM'S MOWING SERVICE, LLC | $780,204 | +0.1% | -12.4% | $204,332 | 2+$55,119 | 3-$95,623 |
| 3 | E.V.G. ENTERPRISE | $984,536 | +26.3% | 10.5% | $49,464 | 1+$154,492 | 4-$82,929 |
| 4 | HJC FARMS, INC. | $1,034,000 | +32.6% | 16.1% | 2+$195,249 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
AUSTIN BARRICADE COMPANY, L.L.C. vs MARCOM'S MOWING SERVICE, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 770-7035 REPLACE W-BEAM RAIL | 5,000 LF | $45.00 | $34.00 | $24.10 | -$55,000 |
| 770-7026 REPLACE DOWNSTREAM ANCHOR TERMINAL | 50 EA | $100.00 | $1,000.00 | $534.87 | $45,000 |
| 500-7033 MOBILIZATION (EMERGENCY) | 12 EA | $2,500.00 | $3,500.00 | $844.81 | $12,000 |
| 770-7036 REPLACE THRIE-BEAM RAIL | 250 LF | $50.00 | $30.00 | $48.04 | -$5,000 |
| 770-7040 REMOVE RAIL | 5,000 LF | $0.2500 | $1.00 | $9.45 | $3,750 |
| 770-7037 REPLACE GUARDRAIL END TREATMENT SYSTEM | 125 EA | $4,000.00 | $3,980.00 | $3,116.90 | -$2,500 |
| 658-7019 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | 100 EA | $28.00 | $50.00 | $26.51 | $2,200 |
| 658-7037 INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2(BI) | 100 EA | $28.00 | $30.00 | $16.45 | $200 |
| 500-7002 MOBILIZATION (CALLOUT) | 24 EA | $1.00 | $1.00 | $600.85 | $0 |
| 505-7001 TMA (STATIONARY) | 180 DAY | $1.00 | $1.00 | $217.57 | $0 |
Positive: the low bidder was cheaper on that item. These 10 items account for $650 of the $650 gap.
AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 770-7035 REPLACE W-BEAM RAIL | 5,000 LF | $45.00 | $24.10 | 1.87x | $104,492 |
| 500-7033 MOBILIZATION (EMERGENCY) | 12 EA | $2,500.00 | $844.81 | 2.96x | $19,862 |
| 770-7040 REMOVE RAIL | 5,000 LF | $0.2500 | $9.45 | 0.03x | -$45,994 |
| 505-7001 TMA (STATIONARY) | 180 DAY | $1.00 | $217.57 | 0.00x | -$38,983 |
| 770-7026 REPLACE DOWNSTREAM ANCHOR TERMINAL | 50 EA | $100.00 | $534.87 | 0.19x | -$21,743 |
| 500-7002 MOBILIZATION (CALLOUT) | 24 EA | $1.00 | $600.85 | 0.00x | -$14,396 |
MARCOM'S MOWING SERVICE, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7033 MOBILIZATION (EMERGENCY) | 12 EA | $3,500.00 | $844.81 | 4.14x | $31,862 |
| 770-7026 REPLACE DOWNSTREAM ANCHOR TERMINAL | 50 EA | $1,000.00 | $534.87 | 1.87x | $23,257 |
| 770-7040 REMOVE RAIL | 5,000 LF | $1.00 | $9.45 | 0.11x | -$42,244 |
| 505-7001 TMA (STATIONARY) | 180 DAY | $1.00 | $217.57 | 0.00x | -$38,983 |
| 500-7002 MOBILIZATION (CALLOUT) | 24 EA | $1.00 | $600.85 | 0.00x | -$14,396 |
E.V.G. ENTERPRISE: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 770-7035 REPLACE W-BEAM RAIL | 5,000 LF | $55.00 | $24.10 | 2.28x | $154,492 |
| 770-7040 REMOVE RAIL | 5,000 LF | $2.00 | $9.45 | 0.21x | -$37,244 |
| 505-7001 TMA (STATIONARY) | 180 DAY | $100.00 | $217.57 | 0.46x | -$21,163 |
| 500-7002 MOBILIZATION (CALLOUT) | 24 EA | $1.00 | $600.85 | 0.00x | -$14,396 |
| 500-7033 MOBILIZATION (EMERGENCY) | 12 EA | $1.00 | $844.81 | 0.00x | -$10,126 |