FY 27-28 ROW Mowing 03,04,06,16

6501-12-001 · let Jul 2, 2026 · Dickens, Childress · Routine Maintenance Project

$823,363Low bid: SILVER LAKE CONSTRUCTION LLC-8.0% vs estimate $894,960
$119,825Left on the table14.6% gap to the second bid
5BiddersSpread 33% low to high
1Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1SILVER LAKE CONSTRUCTION LLC $823,363-8.0% $119,825 0 0
2GORMAN OUTDOOR, INC. $943,188+14.6%5.4% $42,511 0 0
3ABESCAPE LANDSCAPING, LLC $985,699+19.7%10.1% $33,312 0 0
4MARLANE CONSTRUCTION, LLC $1,019,011+23.8%13.9% $74,829 0 0
5TEXAS BLACKTOPS LLC $1,093,840+32.9%22.2% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

SILVER LAKE CONSTRUCTION LLC vs GORMAN OUTDOOR, INC., biggest item swings
ItemQtyLow2ndMarket2nd minus low
730-7022 FULL - WIDTH MOWING24,860 AC $33.12$37.94$38.53 $119,825

Positive: the low bidder was cheaper on that item. These 1 items account for $119,825 of the $119,825 gap.