FY 27-28 ROW Mowing 03,04,06,16
6501-12-001 · let Jul 2, 2026 · Dickens, Childress · Routine Maintenance Project
$823,363Low bid: SILVER LAKE CONSTRUCTION LLC-8.0% vs estimate $894,960
$119,825Left on the table14.6% gap to the second bid
5BiddersSpread 33% low to high
1Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SILVER LAKE CONSTRUCTION LLC | $823,363 | -8.0% | $119,825 | 0 | 0 | |
| 2 | GORMAN OUTDOOR, INC. | $943,188 | +14.6% | 5.4% | $42,511 | 0 | 0 |
| 3 | ABESCAPE LANDSCAPING, LLC | $985,699 | +19.7% | 10.1% | $33,312 | 0 | 0 |
| 4 | MARLANE CONSTRUCTION, LLC | $1,019,011 | +23.8% | 13.9% | $74,829 | 0 | 0 |
| 5 | TEXAS BLACKTOPS LLC | $1,093,840 | +32.9% | 22.2% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
SILVER LAKE CONSTRUCTION LLC vs GORMAN OUTDOOR, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 730-7022 FULL - WIDTH MOWING | 24,860 AC | $33.12 | $37.94 | $38.53 | $119,825 |
Positive: the low bidder was cheaper on that item. These 1 items account for $119,825 of the $119,825 gap.