BPM 6500-97-001
6500-97-001 · let Jul 14, 2026 · Waller, Houston · Bridge Preventative Maintenance - Sealed
$716,400Low bid: ISI CONTRACTING, INC.-0.7% vs estimate $721,750
$122,584Left on the table17.1% gap to the second bid
5BiddersSpread 32% low to high
13Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ISI CONTRACTING, INC. | $716,400 | -0.7% | $122,584 | 1+$10,305 | 0 | |
| 2 | STRUCTURAL INTEGRITY GROUP LLC | $838,984 | +17.1% | 16.2% | $26,166 | 1+$16,555 | 1-$7,198 |
| 3 | MC2 CIVIL, LLC | $865,150 | +20.8% | 19.9% | $18,700 | 0 | 2-$61,879 |
| 4 | JACKSON EXCAVATION, LLC | $883,850 | +23.4% | 22.5% | $58,650 | 4+$176,996 | 2-$67,237 |
| 5 | GARRET SHIELDS INFRASTRUCTURE | $942,500 | +31.6% | 30.6% | 1+$46,497 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
ISI CONTRACTING, INC. vs STRUCTURAL INTEGRITY GROUP LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 1,000 SF | $85.00 | $163.00 | $150.68 | $78,000 |
| 361-7007 FULL - DEPTH REPAIR CRCP (12") | 170 CY | $900.00 | $1,124.00 | $905.39 | $38,080 |
| 785-7005 BRIDGE JOINT REPAIR (SEJ) | 300 LF | $625.00 | $562.00 | $385.82 | -$18,900 |
| 432-7055 RIPRAP (CONC)(CL B)(RR8&RR9) | 100 CY | $589.00 | $723.00 | $725.38 | $13,400 |
| 505-7001 TMA (STATIONARY) | 260 DAY | $200.00 | $250.00 | $217.57 | $13,000 |
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $750.00 | $1.00 | $600.85 | -$8,988 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 200 SF | $155.00 | $112.00 | $95.74 | -$8,600 |
| 361-7010 FULL - DEPTH REPAIR CRCP (15") | 20 CY | $900.00 | $1,257.00 | $1,044.24 | $7,140 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 25 DAY | $500.00 | $750.00 | $87.82 | $6,250 |
| 438-7007 CLEANING AND SEALING EXIST JOINTS (CL7) | 2,000 LF | $33.00 | $35.00 | $38.57 | $4,000 |
| 438-7008 CLEANING EXISTING JOINTS | 2,000 LF | $12.00 | $14.00 | $16.75 | $4,000 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 100 SF | $175.00 | $147.00 | $192.68 | -$2,800 |
| 500-7033 MOBILIZATION (EMERGENCY) | 2 EA | $1,000.00 | $1.00 | $844.81 | -$1,998 |
Positive: the low bidder was cheaper on that item. These 13 items account for $122,584 of the $122,584 gap.
ISI CONTRACTING, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 25 DAY | $500.00 | $87.82 | 5.69x | $10,305 |
STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 2MC2 CIVIL, LLC: unbalanced items
Placed 3JACKSON EXCAVATION, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 438-7008 CLEANING EXISTING JOINTS | 2,000 LF | $55.00 | $16.75 | 3.28x | $76,497 |
| 438-7007 CLEANING AND SEALING EXIST JOINTS (CL7) | 2,000 LF | $70.00 | $38.57 | 1.81x | $62,858 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 200 SF | $200.00 | $95.74 | 2.09x | $20,851 |
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $2,000.00 | $600.85 | 3.33x | $16,790 |
| 505-7001 TMA (STATIONARY) | 260 DAY | $10.00 | $217.57 | 0.05x | -$53,969 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 100 SF | $60.00 | $192.68 | 0.31x | -$13,268 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 438-7008 CLEANING EXISTING JOINTS | 2,000 LF | $40.00 | $16.75 | 2.39x | $46,497 |