FY 27 BPM - Site Specific - East
6500-33-001 · let Jul 21, 2026 · Gregg, Tyler · Bridge Preventative Maintenance - Sealed
$473,835Low bid: GHB EQUIPMENT COMPANY, L.L.C.-24.7% vs estimate $628,992
$106,552Left on the table22.5% gap to the second bid
3BiddersSpread 69% low to high
29Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | GHB EQUIPMENT COMPANY, L.L.C. | $473,835 | -24.7% | $106,552 | 3+$11,310 | 2-$547,531 | |
| 2 | RED BARON BUILDING COMPANY MUNICIPAL PROJECTS DIVISION LLC | $580,387 | +22.5% | -7.7% | $219,105 | 5+$49,547 | 4-$604,535 |
| 3 | SHALOM SERVICES CORPORATION | $799,491 | +68.7% | 27.1% | 8+$337,383 | 5-$584,005 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
GHB EQUIPMENT COMPANY, L.L.C. vs RED BARON BUILDING COMPANY MUNICIPAL PROJECTS DIVISION LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 560 CY | $175.00 | $265.00 | $190.61 | $50,400 |
| 100-7017 PREPARING ROW(OPT 1) | 21 STA | $2,250.00 | $800.00 | $1,741.72 | -$30,450 |
| 432-7047 RIPRAP (STONE PROTECTION)(30 IN) | 427 CY | $200.00 | $265.00 | $160.54 | $27,755 |
| 104-7006 REMOV CONC (RIPRAP) | 587 SY | $9.00 | $50.00 | $14.32 | $24,067 |
| 438-7008 CLEANING EXISTING JOINTS | 1,686 LF | $12.00 | $24.00 | $16.75 | $20,232 |
| 432-7002 RIPRAP (CONC)(5 IN) | 77 CY | $450.00 | $675.00 | $585.15 | $17,325 |
| 500-7001 MOBILIZATION | 1 LS | $45,000.00 | $30,000.00 | $523,850.32 | -$15,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $3,000.00 | $1,500.00 | $11,585.04 | -$12,000 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 375 SF | $40.00 | $60.00 | $28.47 | $7,500 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 119 DAY | $75.00 | $125.00 | $87.82 | $5,950 |
| 423-7016 RETAINING WALL (CAST-IN-PLACE) | 23 SF | $100.00 | $300.00 | $115.72 | $4,600 |
| 164-7073 BOND FBR MTRX SEED (PERM)(RURAL)(SAND) | 6,000 SY | $1.25 | $2.00 | $0.5463 | $4,500 |
| 505-7001 TMA (STATIONARY) | 87 DAY | $150.00 | $100.00 | $217.57 | -$4,350 |
| 432-7001 RIPRAP (CONC)(4 IN) | 15.5 CY | $440.00 | $675.00 | $573.24 | $3,643 |
| 432-7053 RIPRAP (SPECIAL) | 13 CY | $500.00 | $750.00 | $567.00 | $3,250 |
| 7010-7001 MAINTENANCE SPEED LIMIT SIGNING | 5 EA | $200.00 | $800.00 | $36.55 | $3,000 |
| 168-7001 VEGETATIVE WATERING | 66 TGL | $50.00 | $10.00 | $8.43 | -$2,640 |
| 401-7001 FLOWABLE BACKFILL | 35 CY | $250.00 | $325.00 | $298.77 | $2,625 |
| 420-7060 CL C CONC (PILE ENCASEMENT) | 2 CY | $3,000.00 | $2,000.00 | $827.85 | -$2,000 |
| 104-7033 REMOV CONC (PILE ENCASEMENT) | 2 CY | $1,000.00 | $400.00 | $592.82 | -$1,200 |
Positive: the low bidder was cheaper on that item. These 20 items account for $107,207 of the $106,552 gap.
GHB EQUIPMENT COMPANY, L.L.C.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 420-7060 CL C CONC (PILE ENCASEMENT) | 2 CY | $3,000.00 | $827.85 | 3.62x | $4,344 |
| 164-7073 BOND FBR MTRX SEED (PERM)(RURAL)(SAND) | 6,000 SY | $1.25 | $0.5463 | 2.29x | $4,222 |
| 168-7001 VEGETATIVE WATERING | 66 TGL | $50.00 | $8.43 | 5.93x | $2,743 |
| 500-7001 MOBILIZATION | 1 LS | $45,000.00 | $523,850.32 | 0.09x | -$478,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $3,000.00 | $11,585.04 | 0.26x | -$68,680 |
RED BARON BUILDING COMPANY MUNICIPAL PROJECTS DIVISION LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 104-7006 REMOV CONC (RIPRAP) | 587 SY | $50.00 | $14.32 | 3.49x | $20,945 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 375 SF | $60.00 | $28.47 | 2.11x | $11,823 |
| 164-7073 BOND FBR MTRX SEED (PERM)(RURAL)(SAND) | 6,000 SY | $2.00 | $0.5463 | 3.66x | $8,722 |
| 423-7016 RETAINING WALL (CAST-IN-PLACE) | 23 SF | $300.00 | $115.72 | 2.59x | $4,238 |
| 7010-7001 MAINTENANCE SPEED LIMIT SIGNING | 5 EA | $800.00 | $36.55 | 21.89x | $3,817 |
| 500-7001 MOBILIZATION | 1 LS | $30,000.00 | $523,850.32 | 0.06x | -$493,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $1,500.00 | $11,585.04 | 0.13x | -$80,680 |
| 100-7017 PREPARING ROW(OPT 1) | 21 STA | $800.00 | $1,741.72 | 0.46x | -$19,776 |
| 505-7001 TMA (STATIONARY) | 87 DAY | $100.00 | $217.57 | 0.46x | -$10,229 |
SHALOM SERVICES CORPORATION: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 560 CY | $400.00 | $190.61 | 2.10x | $117,257 |
| 432-7047 RIPRAP (STONE PROTECTION)(30 IN) | 427 CY | $400.00 | $160.54 | 2.49x | $102,249 |
| 438-7008 CLEANING EXISTING JOINTS | 1,686 LF | $55.00 | $16.75 | 3.28x | $64,487 |
| 401-7001 FLOWABLE BACKFILL | 35 CY | $850.00 | $298.77 | 2.85x | $19,293 |
| 432-7053 RIPRAP (SPECIAL) | 13 CY | $1,500.00 | $567.00 | 2.65x | $12,129 |
| 400-7010 CEM STABIL BKFL | 5 CY | $2,500.00 | $138.14 | 18.10x | $11,809 |
| 104-7033 REMOV CONC (PILE ENCASEMENT) | 2 CY | $3,500.00 | $592.82 | 5.90x | $5,814 |
| 420-7060 CL C CONC (PILE ENCASEMENT) | 2 CY | $3,000.00 | $827.85 | 3.62x | $4,344 |
| 500-7001 MOBILIZATION | 1 LS | $60,000.00 | $523,850.32 | 0.11x | -$463,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $1,500.00 | $11,585.04 | 0.13x | -$80,680 |
| 505-7001 TMA (STATIONARY) | 87 DAY | $1.00 | $217.57 | 0.00x | -$18,842 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 119 DAY | $1.00 | $87.82 | 0.01x | -$10,331 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 375 SF | $1.00 | $28.47 | 0.04x | -$10,302 |