IH 10 at Wayside Dr and McCarty St
6496-99-001 · let Jul 14, 2026 · Harris, Houston · Bridge Preventative Maintenance - Sealed
$488,125Low bid: ISI CONTRACTING, INC.-26.7% vs estimate $666,280
$64,709Left on the table13.3% gap to the second bid
8BiddersSpread 187% low to high
14Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ISI CONTRACTING, INC. | $488,125 | -26.7% | $64,709 | 4+$165,912 | 4-$760,023 | |
| 2 | MACIAS SPECIALTY CONTRACTING LLC | $552,834 | +13.3% | -17.0% | $46,302 | 2+$39,147 | 2-$494,281 |
| 3 | SCR CIVIL CONSTRUCTION, LLC | $599,136 | +22.7% | -10.1% | $44,159 | 2+$17,017 | 2-$469,190 |
| 4 | STRUCTURAL INTEGRITY GROUP LLC | $643,294 | +31.8% | -3.4% | $52,636 | 1+$9,087 | 3-$543,205 |
| 5 | MC2 CIVIL, LLC | $695,930 | +42.6% | 4.5% | $51,461 | 4+$73,623 | 2-$460,090 |
| 6 | ICOS MANAGEMENT, LLC | $747,391 | +53.1% | 12.2% | $3,322 | ||
| 7 | FORDE CONSTRUCTION COMPANY, INC. | $750,713 | +53.8% | 12.7% | $652,263 | ||
| 8 | REAR CONTRACTORS LLC | $1,402,976 | +187.4% | 110.6% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
ISI CONTRACTING, INC. vs MACIAS SPECIALTY CONTRACTING LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 64 DAY | $2,500.00 | $287.00 | $217.57 | -$141,632 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 2,799 SF | $24.00 | $60.00 | $95.74 | $100,764 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 562 SF | $93.00 | $144.00 | $150.68 | $28,662 |
| 438-7007 CLEANING AND SEALING EXIST JOINTS (CL7) | 1,880 LF | $14.00 | $29.00 | $38.57 | $28,200 |
| 500-7001 MOBILIZATION | 1 LS | $25,000.00 | $50,000.00 | $523,850.32 | $25,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $4,500.00 | $16,667.00 | $11,585.04 | $24,334 |
| 361-7008 FULL - DEPTH REPAIR CRCP (13") | 6 CY | $3,000.00 | $6,253.00 | $1,085.51 | $19,518 |
| 788-7002 CONCRETE BEAM REPAIR (CFRP) | 6 EA | $6,050.00 | $3,087.00 | $6,492.05 | -$17,778 |
| 780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT) | 71 LF | $153.00 | $75.00 | $76.83 | -$5,538 |
| 529-7002 CONC CURB (TY II) | 40 LF | $100.00 | $230.00 | $26.45 | $5,200 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 82 LF | $25.00 | $47.00 | $15.92 | $1,804 |
| 438-7006 CLEANING AND SEALING EXIST JOINTS (CL5) | 880 LF | $27.00 | $25.00 | $30.07 | -$1,760 |
| 429-7001 CONC STR REPAIR(CLEAN & COAT WTH EPOXY) | 86 SF | $115.00 | $98.00 | $120.92 | -$1,462 |
| 788-7003 CONCRETE BEAM REP(STRAND SPLICE & CFRP) | 3 EA | $14,500.00 | $14,299.00 | $10,082.27 | -$603 |
Positive: the low bidder was cheaper on that item. These 14 items account for $64,709 of the $64,709 gap.
ISI CONTRACTING, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 64 DAY | $2,500.00 | $217.57 | 11.49x | $146,075 |
| 361-7008 FULL - DEPTH REPAIR CRCP (13") | 6 CY | $3,000.00 | $1,085.51 | 2.76x | $11,487 |
| 780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT) | 71 LF | $153.00 | $76.83 | 1.99x | $5,408 |
| 529-7002 CONC CURB (TY II) | 40 LF | $100.00 | $26.45 | 3.78x | $2,942 |
| 500-7001 MOBILIZATION | 1 LS | $25,000.00 | $523,850.32 | 0.05x | -$498,850 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 2,799 SF | $24.00 | $95.74 | 0.25x | -$200,809 |
| 438-7007 CLEANING AND SEALING EXIST JOINTS (CL7) | 1,880 LF | $14.00 | $38.57 | 0.36x | -$46,194 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $4,500.00 | $11,585.04 | 0.39x | -$14,170 |
MACIAS SPECIALTY CONTRACTING LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 361-7008 FULL - DEPTH REPAIR CRCP (13") | 6 CY | $6,253.00 | $1,085.51 | 5.76x | $31,005 |
| 529-7002 CONC CURB (TY II) | 40 LF | $230.00 | $26.45 | 8.70x | $8,142 |
| 500-7001 MOBILIZATION | 1 LS | $50,000.00 | $523,850.32 | 0.10x | -$473,850 |
| 788-7002 CONCRETE BEAM REPAIR (CFRP) | 6 EA | $3,087.00 | $6,492.05 | 0.48x | -$20,430 |
SCR CIVIL CONSTRUCTION, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 64 DAY | $400.00 | $217.57 | 1.84x | $11,675 |
| 529-7002 CONC CURB (TY II) | 40 LF | $160.00 | $26.45 | 6.05x | $5,342 |
| 500-7001 MOBILIZATION | 1 LS | $59,900.00 | $523,850.32 | 0.11x | -$463,950 |
| 429-7001 CONC STR REPAIR(CLEAN & COAT WTH EPOXY) | 86 SF | $60.00 | $120.92 | 0.50x | -$5,239 |
STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 361-7008 FULL - DEPTH REPAIR CRCP (13") | 6 CY | $2,600.00 | $1,085.51 | 2.40x | $9,087 |
| 500-7001 MOBILIZATION | 1 LS | $1.00 | $523,850.32 | 0.00x | -$523,849 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $5,000.00 | $11,585.04 | 0.43x | -$13,170 |
| 429-7001 CONC STR REPAIR(CLEAN & COAT WTH EPOXY) | 86 SF | $49.00 | $120.92 | 0.41x | -$6,185 |
MC2 CIVIL, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 788-7002 CONCRETE BEAM REPAIR (CFRP) | 6 EA | $12,500.00 | $6,492.05 | 1.93x | $36,048 |
| 788-7003 CONCRETE BEAM REP(STRAND SPLICE & CFRP) | 3 EA | $18,500.00 | $10,082.27 | 1.83x | $25,253 |
| 361-7008 FULL - DEPTH REPAIR CRCP (13") | 6 CY | $2,400.00 | $1,085.51 | 2.21x | $7,887 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 82 LF | $70.00 | $15.92 | 4.40x | $4,435 |
| 500-7001 MOBILIZATION | 1 LS | $69,000.00 | $523,850.32 | 0.13x | -$454,850 |
| 429-7001 CONC STR REPAIR(CLEAN & COAT WTH EPOXY) | 86 SF | $60.00 | $120.92 | 0.50x | -$5,239 |