Concrete Pavement Repair McLennan DW
6493-33-001 · let Jul 1, 2026 · Hill, Waco · Routine Maintenance Project - Sealed
$1,432,275Low bid: STRUCTURAL INTEGRITY GROUP LLC-15.4% vs estimate $1,693,643
$59,427Left on the table4.1% gap to the second bid
7BiddersSpread 68% low to high
16Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | STRUCTURAL INTEGRITY GROUP LLC | $1,432,275 | -15.4% | $59,427 | 4+$208,273 | 2-$39,151 | |
| 2 | CROSS PLUS CONSTRUCTION, LLC | $1,491,702 | +4.1% | -11.9% | $92,451 | 2+$305,094 | 5-$511,462 |
| 3 | O. TREVINO CONSTRUCTION, LLC | $1,584,153 | +10.6% | -6.5% | $90,727 | 3+$64,823 | 1-$138,564 |
| 4 | MACIAS SPECIALTY CONTRACTING LLC | $1,674,879 | +16.9% | -1.1% | $188,471 | 4+$245,522 | 1-$272,448 |
| 5 | GARRET SHIELDS INFRASTRUCTURE | $1,863,350 | +30.1% | 10.0% | $85,152 | 2+$220,642 | 1-$236,940 |
| 6 | DIGG COMMERCIAL, LLC | $1,948,502 | +36.0% | 15.0% | $461,818 | ||
| 7 | ROY JORGENSEN ASSOCIATES, INC. | $2,410,320 | +68.3% | 42.3% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
STRUCTURAL INTEGRITY GROUP LLC vs CROSS PLUS CONSTRUCTION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 721-7003 FIBER REINFORCED POLYMER PATCHING REP | 22 CY | $16,770.00 | $500.00 | $16,770.00 | -$357,940 |
| 720-7001 SPALLING REPAIR (HYDRAULIC CEMENT) | 508 CF | $470.00 | $35.00 | $206.00 | -$220,980 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 328 SF | $175.00 | $800.00 | $192.68 | $205,000 |
| 361-7008 FULL - DEPTH REPAIR CRCP (13") | 384 CY | $737.00 | $1,199.00 | $1,085.51 | $177,408 |
| 713-7005 LONGT CRACK CLEANING AND SEALING (CRCP) | 12,850 LF | $11.00 | $22.00 | $14.53 | $141,350 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 210 SF | $175.00 | $600.00 | $95.74 | $89,250 |
| 361-7010 FULL - DEPTH REPAIR CRCP (15") | 110 CY | $727.00 | $1,200.00 | $1,044.24 | $52,030 |
| 361-7005 FULL - DEPTH REPAIR CRCP (10") | 133 CY | $650.00 | $900.00 | $1,202.68 | $33,250 |
| 720-7003 SPALLING REPAIR (POLYMERIC) (SEMIRIGID) | 550 GAL | $145.00 | $100.00 | $72.23 | -$24,750 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 62 DAY | $370.00 | $1.00 | $87.82 | -$22,878 |
| 361-7047 FULL-DEPTH REP(BR APPR SLAB)(9"-13") | 40 CY | $682.00 | $400.00 | $1,087.55 | -$11,280 |
| 361-7003 FULL - DEPTH REPAIR CRCP (8") | 10 CY | $947.00 | $805.00 | $721.60 | -$1,420 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 43 DAY | $1.00 | $10.00 | $117.34 | $387 |
| 500-7002 MOBILIZATION (CALLOUT) | 14 EA | $1.00 | $1.00 | $600.85 | $0 |
| 500-7033 MOBILIZATION (EMERGENCY) | 8 EA | $1.00 | $1.00 | $844.81 | $0 |
| 505-7001 TMA (STATIONARY) | 142 DAY | $1.00 | $1.00 | $217.57 | $0 |
Positive: the low bidder was cheaper on that item. These 16 items account for $59,427 of the $59,427 gap.
STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 720-7001 SPALLING REPAIR (HYDRAULIC CEMENT) | 508 CF | $470.00 | $206.00 | 2.28x | $134,111 |
| 720-7003 SPALLING REPAIR (POLYMERIC) (SEMIRIGID) | 550 GAL | $145.00 | $72.23 | 2.01x | $40,023 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 62 DAY | $370.00 | $87.82 | 4.21x | $17,495 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 210 SF | $175.00 | $95.74 | 1.83x | $16,644 |
| 505-7001 TMA (STATIONARY) | 142 DAY | $1.00 | $217.57 | 0.00x | -$30,753 |
| 500-7002 MOBILIZATION (CALLOUT) | 14 EA | $1.00 | $600.85 | 0.00x | -$8,398 |
CROSS PLUS CONSTRUCTION, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 328 SF | $800.00 | $192.68 | 4.15x | $199,200 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 210 SF | $600.00 | $95.74 | 6.27x | $105,894 |
| 721-7003 FIBER REINFORCED POLYMER PATCHING REP | 22 CY | $500.00 | $16,770.00 | 0.03x | -$357,940 |
| 720-7001 SPALLING REPAIR (HYDRAULIC CEMENT) | 508 CF | $35.00 | $206.00 | 0.17x | -$86,869 |
| 505-7001 TMA (STATIONARY) | 142 DAY | $1.00 | $217.57 | 0.00x | -$30,753 |
| 361-7047 FULL-DEPTH REP(BR APPR SLAB)(9"-13") | 40 CY | $400.00 | $1,087.55 | 0.37x | -$27,502 |
| 500-7002 MOBILIZATION (CALLOUT) | 14 EA | $1.00 | $600.85 | 0.00x | -$8,398 |
O. TREVINO CONSTRUCTION, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 361-7047 FULL-DEPTH REP(BR APPR SLAB)(9"-13") | 40 CY | $2,170.00 | $1,087.55 | 2.00x | $43,298 |
| 500-7033 MOBILIZATION (EMERGENCY) | 8 EA | $2,500.00 | $844.81 | 2.96x | $13,242 |
| 361-7003 FULL - DEPTH REPAIR CRCP (8") | 10 CY | $1,550.00 | $721.60 | 2.15x | $8,284 |
| 713-7005 LONGT CRACK CLEANING AND SEALING (CRCP) | 12,850 LF | $3.75 | $14.53 | 0.26x | -$138,564 |
MACIAS SPECIALTY CONTRACTING LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 14 EA | $12,505.00 | $600.85 | 20.81x | $166,658 |
| 720-7003 SPALLING REPAIR (POLYMERIC) (SEMIRIGID) | 550 GAL | $140.00 | $72.23 | 1.94x | $37,273 |
| 500-7033 MOBILIZATION (EMERGENCY) | 8 EA | $4,167.00 | $844.81 | 4.93x | $26,578 |
| 361-7003 FULL - DEPTH REPAIR CRCP (8") | 10 CY | $2,223.00 | $721.60 | 3.08x | $15,014 |
| 721-7003 FIBER REINFORCED POLYMER PATCHING REP | 22 CY | $4,386.00 | $16,770.00 | 0.26x | -$272,448 |