Specialty Markings Handwork 07 0826
6498-34-001 · let Jul 8, 2026 · Collin, Dallas · Routine Maintenance Project - Sealed
$243,687Low bid: STRIPE-A-ZONE, LLC-17.1% vs estimate $293,913
$142,964Left on the table58.7% gap to the second bid
2BiddersSpread 59% low to high
16Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | STRIPE-A-ZONE, LLC | $243,687 | -17.1% | $142,964 | 0 | 3-$566,100 | |
| 2 | TRP INFRASTRUCTURE SERVICES, LLC | $386,651 | +58.7% | 31.6% | 2+$68,842 | 3-$537,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
STRIPE-A-ZONE, LLC vs TRP INFRASTRUCTURE SERVICES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 666-7244 RE PM TY III (W)(24")(SLD) | 8,961 LF | $8.50 | $14.50 | $7.96 | $53,766 |
| 500-7001 MOBILIZATION | 1 LS | $2,500.00 | $30,000.00 | $523,850.32 | $27,500 |
| 666-7254 RE PM TY III (W)(ARROW) | 205 EA | $250.00 | $350.00 | $239.01 | $20,500 |
| 666-7257 RE PM TY III (W)(WORD) | 203 EA | $290.00 | $385.00 | $274.97 | $19,285 |
| 677-7008 ELIM EXT PM & MRKS (24") | 2,070 LF | $2.00 | $4.00 | $2.87 | $4,140 |
| 677-7015 ELIM EXT PM & MRKS (WORD) | 203 EA | $40.00 | $60.00 | $53.95 | $4,060 |
| 666-7256 RE PM TY III (W)(U-TURN ARROW) | 38 EA | $320.00 | $425.00 | $314.79 | $3,990 |
| 677-7006 ELIM EXT PM & MRKS (12") | 8,701 LF | $2.00 | $2.45 | $1.27 | $3,915 |
| 677-7009 ELIM EXT PM & MRKS (ARROW) | 205 EA | $40.00 | $55.00 | $50.50 | $3,075 |
| 677-7012 ELIM EXT PM & MRKS (UTURN ARROW) | 38 EA | $40.00 | $75.00 | $49.92 | $1,330 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $250.00 | $500.00 | $11,585.04 | $750 |
| 666-7238 RE PM TY III (W)(6")(DOT) | 820 LF | $1.75 | $2.50 | $1.31 | $615 |
| 677-7004 ELIM EXT PM & MRKS (8") | 76 LF | $1.00 | $2.00 | $0.6468 | $76 |
| 666-7241 RE PM TY III (W)(8")(DOT) | 76 LF | $3.00 | $2.50 | $1.31 | -$38 |
| 505-7003 TMA (MOBILE OPERATION) | 47 DAY | $1.00 | $1.00 | $229.60 | $0 |
| 677-7002 ELIM EXT PM & MRKS (6") | 820 LF | $1.00 | $1.00 | $0.2755 | $0 |
Positive: the low bidder was cheaper on that item. These 16 items account for $142,964 of the $142,964 gap.
STRIPE-A-ZONE, LLC: unbalanced items
Placed 1TRP INFRASTRUCTURE SERVICES, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 666-7244 RE PM TY III (W)(24")(SLD) | 8,961 LF | $14.50 | $7.96 | 1.82x | $58,609 |
| 677-7006 ELIM EXT PM & MRKS (12") | 8,701 LF | $2.45 | $1.27 | 1.92x | $10,232 |
| 500-7001 MOBILIZATION | 1 LS | $30,000.00 | $523,850.32 | 0.06x | -$493,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $500.00 | $11,585.04 | 0.04x | -$33,255 |
| 505-7003 TMA (MOBILE OPERATION) | 47 DAY | $1.00 | $229.60 | 0.00x | -$10,744 |