Mowing Reagan/Irion FY 27
6488-50-001 · let Jul 23, 2026 · Reagan, San Angelo · Routine Maintenance Project - Sealed
$183,407Low bid: LUKEDA SANDBLASTING & SERVICES LLC-5.2% vs estimate $193,459
$8,290Left on the table4.5% gap to the second bid
4BiddersSpread 126% low to high
1Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | LUKEDA SANDBLASTING & SERVICES LLC | $183,407 | -5.2% | $8,290 | 0 | 0 | |
| 2 | BOEN LANDSCAPING & IRRIGATION, LLC | $191,697 | +4.5% | -0.9% | $15,543 | 0 | 0 |
| 3 | ABESCAPE LANDSCAPING, LLC | $207,240 | +13.0% | 7.1% | $207,240 | 0 | 0 |
| 4 | CROSS PLUS CONSTRUCTION, LLC | $414,480 | +126.0% | 114.2% | 1+$214,859 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
LUKEDA SANDBLASTING & SERVICES LLC vs BOEN LANDSCAPING & IRRIGATION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 730-7022 FULL - WIDTH MOWING | 5,181 AC | $35.40 | $37.00 | $38.53 | $8,290 |
Positive: the low bidder was cheaper on that item. These 1 items account for $8,290 of the $8,290 gap.
CROSS PLUS CONSTRUCTION, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 730-7022 FULL - WIDTH MOWING | 5,181 AC | $80.00 | $38.53 | 2.08x | $214,859 |