IH 35W; Bethesda Rd to Asher Rd
0014-03-088 · let Jul 1, 2026 · Johnson, Fort Worth · Interchange (New or Reconstructed)
$64,374,552Low bid: INDUS ROAD & BRIDGE, INC.-9.6% vs estimate $71,229,543
$1,993,044Left on the table3.1% gap to the second bid
6BiddersSpread 25% low to high
310Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | INDUS ROAD & BRIDGE, INC. | $64,374,552 | -9.6% | $1,993,044 | 3+$9,838,770 | 0 | |
| 2 | JAMES CONSTRUCTION GROUP, LLC | $66,367,596 | +3.1% | -6.8% | $2,295,552 | 4+$14,760,396 | 0 |
| 3 | RAGLE CONSTRUCTION, INC. | $68,663,148 | +6.7% | -3.6% | $1,135,560 | 4+$13,092,572 | 0 |
| 4 | HARPER BROTHERS CONSTRUCTION LLC | $69,798,708 | +8.4% | -2.0% | $3,900,385 | 4+$9,093,734 | 1-$742,168 |
| 5 | AUSTIN BRIDGE & ROAD SERVICES, LP | $73,699,093 | +14.5% | 3.5% | $6,800,907 | 4+$13,260,144 | 0 |
| 6 | REYES TX, INC. | $80,500,000 | +25.0% | 13.0% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
INDUS ROAD & BRIDGE, INC. vs JAMES CONSTRUCTION GROUP, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 132-7004 EMBANK (FNL)(DC)(TY B) | 297,691 CY | $14.30 | $26.06 | $12.93 | $3,500,846 |
| 100-7002 PREPARING ROW | 241 STA | $20,774.23 | $27,500.00 | $6,072.92 | $1,620,911 |
| 423-7001 RETAINING WALL (MSE) | 67,121 SF | $70.00 | $53.90 | $74.07 | -$1,080,648 |
| 500-7001 MOBILIZATION | 1 LS | $6,400,000.00 | $5,609,907.40 | $523,850.32 | -$790,093 |
| 110-7001 EXCAV (ROADWAY) | 88,324 CY | $13.00 | $6.44 | $11.68 | -$579,405 |
| 360-7005 CONC PVMT (CRCP) (11") | 67,992 SY | $95.00 | $103.16 | $94.72 | $554,815 |
| 432-7002 RIPRAP (CONC)(5 IN) | 3,402 CY | $550.00 | $417.55 | $585.15 | -$450,595 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 45 MO | $15,000.00 | $24,929.04 | $11,585.04 | $446,807 |
| 422-7002 REINF CONC SLAB (HPC) | 63,827 SF | $20.00 | $26.30 | $26.91 | $402,110 |
| 423-7012 RETAINING WALL (TEMP WALL) | 23,240 SF | $41.00 | $26.17 | $22.94 | -$344,649 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 7,500 LF | $74.00 | $30.96 | $43.56 | -$322,800 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 17,550 LF | $75.00 | $57.47 | $52.29 | -$307,652 |
| 105-7012 RMV (12"-16") TRT/UNTRT BASE & ASPH PAV | 72,233 SY | $9.00 | $4.91 | $8.45 | -$295,433 |
| 134-7002 BACKFILL (TY B) | 241 STA | $300.00 | $1,392.82 | $206.94 | $263,370 |
| 508-7001 CONSTRUCTING DETOURS | 30,674 SY | $100.00 | $107.52 | $83.58 | $230,668 |
| 531-7001 CONC SIDEWALKS (4") | 9,939 SY | $50.00 | $71.06 | $70.57 | $209,315 |
| 464-7005 RC PIPE (CL III)(24 IN) | 9,918.4 LF | $105.00 | $85.86 | $108.34 | -$189,838 |
| 341-7001 D-GR HMA TY-B PG64-22 | 23,128 TON | $130.00 | $122.50 | $97.82 | -$173,460 |
| 432-7012 RIPRAP (CONC)(FLUME) | 259 CY | $560.00 | $1,227.19 | $674.93 | $172,802 |
| 529-7007 CONC CURB (MONO) (TY II) | 20,204 LF | $6.00 | $13.84 | $6.85 | $158,399 |
Positive: the low bidder was cheaper on that item. These 20 items account for $3,025,470 of the $1,993,044 gap.
INDUS ROAD & BRIDGE, INC.: unbalanced items
Placed 1JAMES CONSTRUCTION GROUP, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 241 STA | $27,500.00 | $6,072.92 | 4.53x | $5,163,926 |
| 500-7001 MOBILIZATION | 1 LS | $5,609,907.40 | $523,850.32 | 10.71x | $5,086,057 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 297,691 CY | $26.06 | $12.93 | 2.02x | $3,909,933 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 45 MO | $24,929.04 | $11,585.04 | 2.15x | $600,480 |
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $6,800,000.00 | $523,850.32 | 12.98x | $6,276,150 |
| 100-7002 PREPARING ROW | 241 STA | $28,000.00 | $6,072.92 | 4.61x | $5,284,426 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 45 MO | $35,000.00 | $11,585.04 | 3.02x | $1,053,673 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $615,000.00 | $136,676.66 | 4.50x | $478,323 |
HARPER BROTHERS CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $6,600,000.00 | $523,850.32 | 12.60x | $6,076,150 |
| 100-7002 PREPARING ROW | 241 STA | $12,500.00 | $6,072.92 | 2.06x | $1,548,926 |
| 464-7005 RC PIPE (CL III)(24 IN) | 9,918.4 LF | $200.00 | $108.34 | 1.85x | $909,153 |
| 400-7010 CEM STABIL BKFL | 5,002 CY | $250.00 | $138.14 | 1.81x | $559,505 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 17,550 LF | $10.00 | $52.29 | 0.19x | -$742,168 |
AUSTIN BRIDGE & ROAD SERVICES, LP: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $7,400,000.00 | $523,850.32 | 14.13x | $6,876,150 |
| 100-7002 PREPARING ROW | 241 STA | $18,530.00 | $6,072.92 | 3.05x | $3,002,156 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 45 MO | $67,600.00 | $11,585.04 | 5.84x | $2,520,673 |
| 423-7012 RETAINING WALL (TEMP WALL) | 23,240 SF | $60.00 | $22.94 | 2.61x | $861,165 |