1.1 Mi W of SH 16 to SH 16 Pave Repair
0007-06-268 · let Jul 1, 2026 · Eastland, Brownwood · Restoration
$1,029,929Low bid: O. TREVINO CONSTRUCTION, LLC-21.9% vs estimate $1,318,736
$54,867Left on the table5.3% gap to the second bid
4BiddersSpread 41% low to high
32Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | O. TREVINO CONSTRUCTION, LLC | $1,029,929 | -21.9% | $54,867 | 6+$168,291 | 2-$437,539 | |
| 2 | PRATER DIRT WORK LLC | $1,084,796 | +5.3% | -17.7% | $59,271 | 6+$137,957 | 2-$425,689 |
| 3 | GHB EQUIPMENT COMPANY, L.L.C. | $1,144,067 | +11.1% | -13.2% | $305,238 | 9+$227,284 | 2-$418,039 |
| 4 | STX CIVIL | $1,449,305 | +40.7% | 9.9% | 7+$376,592 | 1-$407,816 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
O. TREVINO CONSTRUCTION, LLC vs PRATER DIRT WORK LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 361-7008 FULL - DEPTH REPAIR CRCP (13") | 350 CY | $1,005.00 | $1,200.00 | $1,085.51 | $68,250 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $25,000.00 | $12,500.00 | $11,585.04 | -$37,500 |
| 341-7001 D-GR HMA TY-B PG64-22 | 155 TON | $300.00 | $500.00 | $97.82 | $31,000 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 4,350 LF | $22.00 | $17.05 | $12.08 | -$21,533 |
| 500-7001 MOBILIZATION | 1 LS | $103,000.00 | $115,000.00 | $523,850.32 | $12,000 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 4,350 LF | $10.00 | $7.70 | $7.54 | -$10,005 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 168 DAY | $150.00 | $200.00 | $87.82 | $8,400 |
| 505-7001 TMA (STATIONARY) | 56 DAY | $150.00 | $300.00 | $217.57 | $8,400 |
| 402-7001 TRENCH EXCAVATION PROTECTION | 56 LF | $120.00 | $1.00 | $5.96 | -$6,664 |
| 110-7001 EXCAV (ROADWAY) | 150 CY | $240.00 | $200.00 | $11.68 | -$6,000 |
| 662-7059 WK ZN PAV MRK REMOV (TRAF BTN) TY Y | 4,513 EA | $3.50 | $4.50 | $2.22 | $4,513 |
| 401-7001 FLOWABLE BACKFILL | 186 CY | $280.00 | $260.00 | $298.77 | -$3,720 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 10,393 LF | $0.0500 | $0.3400 | $0.0662 | $3,014 |
| 677-7002 ELIM EXT PM & MRKS (6") | 10,393 LF | $0.6000 | $0.8400 | $0.2755 | $2,494 |
| 666-7347 PAVEMENT SLER 6" | 10,393 LF | $0.2000 | $0.4200 | $0.1841 | $2,286 |
| 464-7005 RC PIPE (CL III)(24 IN) | 56 LF | $175.00 | $150.00 | $108.34 | -$1,400 |
| 662-7057 WK ZN PAV MRK REMOV (TRAF BTN) TY W | 966 EA | $3.50 | $4.50 | $3.01 | $966 |
| 512-7013 PORT CTB (DES SOURCE)(SGL SLP)(TY 1) | 4,350 LF | $23.00 | $22.80 | $15.26 | -$870 |
| 666-7408 REFL PAV MRK TY I (W)6"(BRK)(100MIL) | 2,150 LF | $0.7500 | $1.08 | $0.5627 | $710 |
| 666-7135 RE PV MRK TY I(BLACK)4"(SHADOW)(100MIL) | 2,150 LF | $0.6500 | $0.9600 | $1.19 | $667 |
Positive: the low bidder was cheaper on that item. These 20 items account for $55,008 of the $54,867 gap.
O. TREVINO CONSTRUCTION, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 4,350 LF | $22.00 | $12.08 | 1.82x | $43,137 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $25,000.00 | $11,585.04 | 2.16x | $40,245 |
| 110-7001 EXCAV (ROADWAY) | 150 CY | $240.00 | $11.68 | 20.54x | $34,248 |
| 341-7001 D-GR HMA TY-B PG64-22 | 155 TON | $300.00 | $97.82 | 3.07x | $31,337 |
| 533-7003 MILL RUMBLE STRIPS (CONC) (SHLDR) | 300 LF | $44.00 | $0.8732 | 50.39x | $12,938 |
| 402-7001 TRENCH EXCAVATION PROTECTION | 56 LF | $120.00 | $5.96 | 20.14x | $6,386 |
| 500-7001 MOBILIZATION | 1 LS | $103,000.00 | $523,850.32 | 0.20x | -$420,850 |
| 545-7006 CRASH CUSH ATTEN (INSTL)(L)(N)(TL3) | 1 EA | $9,500.00 | $26,188.60 | 0.36x | -$16,689 |
PRATER DIRT WORK LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 341-7001 D-GR HMA TY-B PG64-22 | 155 TON | $500.00 | $97.82 | 5.11x | $62,337 |
| 110-7001 EXCAV (ROADWAY) | 150 CY | $200.00 | $11.68 | 17.12x | $28,248 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 168 DAY | $200.00 | $87.82 | 2.28x | $18,847 |
| 533-7003 MILL RUMBLE STRIPS (CONC) (SHLDR) | 300 LF | $42.16 | $0.8732 | 48.28x | $12,386 |
| 662-7059 WK ZN PAV MRK REMOV (TRAF BTN) TY Y | 4,513 EA | $4.50 | $2.22 | 2.02x | $10,273 |
| 677-7002 ELIM EXT PM & MRKS (6") | 10,393 LF | $0.8400 | $0.2755 | 3.05x | $5,867 |
| 500-7001 MOBILIZATION | 1 LS | $115,000.00 | $523,850.32 | 0.22x | -$408,850 |
| 545-7006 CRASH CUSH ATTEN (INSTL)(L)(N)(TL3) | 1 EA | $9,350.00 | $26,188.60 | 0.36x | -$16,839 |
GHB EQUIPMENT COMPANY, L.L.C.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 4,350 LF | $25.00 | $12.08 | 2.07x | $56,187 |
| 341-7001 D-GR HMA TY-B PG64-22 | 155 TON | $425.00 | $97.82 | 4.34x | $50,712 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $24,500.00 | $11,585.04 | 2.11x | $38,745 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 4,350 LF | $14.00 | $7.54 | 1.86x | $28,123 |
| 533-7003 MILL RUMBLE STRIPS (CONC) (SHLDR) | 300 LF | $55.00 | $0.8732 | 62.99x | $16,238 |
| 402-7001 TRENCH EXCAVATION PROTECTION | 56 LF | $200.00 | $5.96 | 33.56x | $10,866 |
| 464-7005 RC PIPE (CL III)(24 IN) | 56 LF | $300.00 | $108.34 | 2.77x | $10,733 |
| 110-7001 EXCAV (ROADWAY) | 150 CY | $75.00 | $11.68 | 6.42x | $9,498 |
| 658-7032 INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB (BI) | 44 EA | $150.00 | $9.51 | 15.77x | $6,182 |
| 500-7001 MOBILIZATION | 1 LS | $120,000.00 | $523,850.32 | 0.23x | -$403,850 |
| 545-7006 CRASH CUSH ATTEN (INSTL)(L)(N)(TL3) | 1 EA | $12,000.00 | $26,188.60 | 0.46x | -$14,189 |
STX CIVIL: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 4,350 LF | $44.74 | $7.54 | 5.94x | $161,842 |
| 512-7013 PORT CTB (DES SOURCE)(SGL SLP)(TY 1) | 4,350 LF | $37.35 | $15.26 | 2.45x | $96,085 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 4,350 LF | $28.50 | $12.08 | 2.36x | $71,412 |
| 341-7001 D-GR HMA TY-B PG64-22 | 155 TON | $211.34 | $97.82 | 2.16x | $17,595 |
| 464-7005 RC PIPE (CL III)(24 IN) | 56 LF | $300.81 | $108.34 | 2.78x | $10,779 |
| 662-7059 WK ZN PAV MRK REMOV (TRAF BTN) TY Y | 4,513 EA | $4.51 | $2.22 | 2.03x | $10,318 |
| 533-7003 MILL RUMBLE STRIPS (CONC) (SHLDR) | 300 LF | $29.41 | $0.8732 | 33.68x | $8,561 |
| 500-7001 MOBILIZATION | 1 LS | $116,034.57 | $523,850.32 | 0.22x | -$407,816 |