2027 OA MBGF
6486-95-001 · let Jul 21, 2026 · Jasper, Beaumont · Routine Maintenance Project - Sealed
$313,007Low bid: T&L CLEANING SERVICES LLC-41.2% vs estimate $532,482
$136,959Left on the table43.8% gap to the second bid
4BiddersSpread 81% low to high
33Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | T&L CLEANING SERVICES LLC | $313,007 | -41.2% | $136,959 | 2+$6,605 | 3-$51,654 | |
| 2 | ISI CONTRACTING, INC. | $449,966 | +43.8% | -15.5% | $11,299 | 5+$80,495 | 3-$43,202 |
| 3 | RHINO EQUITY, LLC | $461,265 | +47.4% | -13.4% | $105,032 | 5+$259,436 | 5-$103,925 |
| 4 | AUSTIN BARRICADE COMPANY, L.L.C. | $566,297 | +80.9% | 6.4% | 2+$384,815 | 5-$163,197 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
T&L CLEANING SERVICES LLC vs ISI CONTRACTING, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 50 DAY | $100.00 | $1,000.00 | $217.57 | $45,000 |
| 770-7037 REPLACE GUARDRAIL END TREATMENT SYSTEM | 40 EA | $3,700.00 | $4,500.00 | $3,116.90 | $32,000 |
| 771-7029 REPLACE CABLE RELEASE POST | 10 EA | $200.00 | $2,500.00 | $148.81 | $23,000 |
| 451-7049 RETROFIT RAIL (TY T131RC) | 150 LF | $150.00 | $284.00 | $228.58 | $20,100 |
| 500-7002 MOBILIZATION (CALLOUT) | 50 EA | $1.00 | $250.00 | $600.85 | $12,450 |
| 770-7035 REPLACE W-BEAM RAIL | 2,000 LF | $30.00 | $25.00 | $24.10 | -$10,000 |
| 771-7032 REMOVE CABLE BARRIER SYSTEM | 200 LF | $50.00 | $4.70 | $54.08 | -$9,060 |
| 771-7033 SPLICE CABLE | 5 EA | $150.00 | $1,500.00 | $342.77 | $6,750 |
| 500-7033 MOBILIZATION (EMERGENCY) | 12 EA | $500.00 | $1,000.00 | $844.81 | $6,000 |
| 770-7026 REPLACE DOWNSTREAM ANCHOR TERMINAL | 3 EA | $1,000.00 | $2,879.00 | $534.87 | $5,637 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 20 DAY | $150.00 | $340.00 | $87.82 | $3,800 |
| 774-7003 REPAIR (SMTC) NARROW | 10 LF | $500.00 | $125.00 | $202.80 | -$3,750 |
| 774-7009 REPAIR (QUAD - ELITE) NARROW | 10 LF | $500.00 | $214.00 | $136.65 | -$2,860 |
| 770-7036 REPLACE THRIE-BEAM RAIL | 63 LF | $30.00 | $70.00 | $48.04 | $2,520 |
| 774-7002 REPLACE (SMTC) NARROW | 1 EA | $28,000.00 | $30,000.00 | $24,419.83 | $2,000 |
| 774-7001 REMOVE (SMTC) NARROW | 1 EA | $1.00 | $929.00 | $0.7353 | $928 |
| 545-7004 CRASH CUSH ATTEN (REMOVE) | 1 EA | $1.00 | $929.00 | $941.31 | $928 |
| 770-7041 REPLACE GDRL END TREATMENT MRKR | 3 EA | $50.00 | $318.00 | $29.93 | $804 |
| 771-7026 REPLACE LINE OR TERMINAL POST (GIBRAL) | 1 EA | $500.00 | $1,291.00 | $176.83 | $791 |
| 770-7038 REPLACE CURVED RAIL | 40 LF | $30.00 | $22.00 | $26.19 | -$320 |
Positive: the low bidder was cheaper on that item. These 20 items account for $136,718 of the $136,959 gap.
T&L CLEANING SERVICES LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 774-7009 REPAIR (QUAD - ELITE) NARROW | 10 LF | $500.00 | $136.65 | 3.66x | $3,634 |
| 774-7003 REPAIR (SMTC) NARROW | 10 LF | $500.00 | $202.80 | 2.47x | $2,972 |
| 500-7002 MOBILIZATION (CALLOUT) | 50 EA | $1.00 | $600.85 | 0.00x | -$29,992 |
| 545-7010 CRASH CUSH ATTEN (INSTL)(R)(N)(TL3) | 1 EA | $10,000.00 | $25,783.02 | 0.39x | -$15,783 |
| 505-7001 TMA (STATIONARY) | 50 DAY | $100.00 | $217.57 | 0.46x | -$5,879 |
ISI CONTRACTING, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 50 DAY | $1,000.00 | $217.57 | 4.60x | $39,121 |
| 771-7029 REPLACE CABLE RELEASE POST | 10 EA | $2,500.00 | $148.81 | 16.80x | $23,512 |
| 770-7026 REPLACE DOWNSTREAM ANCHOR TERMINAL | 3 EA | $2,879.00 | $534.87 | 5.38x | $7,032 |
| 771-7033 SPLICE CABLE | 5 EA | $1,500.00 | $342.77 | 4.38x | $5,786 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 20 DAY | $340.00 | $87.82 | 3.87x | $5,044 |
| 500-7002 MOBILIZATION (CALLOUT) | 50 EA | $250.00 | $600.85 | 0.42x | -$17,542 |
| 545-7010 CRASH CUSH ATTEN (INSTL)(R)(N)(TL3) | 1 EA | $10,000.00 | $25,783.02 | 0.39x | -$15,783 |
| 771-7032 REMOVE CABLE BARRIER SYSTEM | 200 LF | $4.70 | $54.08 | 0.09x | -$9,876 |
RHINO EQUITY, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 50 DAY | $5,000.00 | $217.57 | 22.98x | $239,121 |
| 771-7029 REPLACE CABLE RELEASE POST | 10 EA | $1,200.00 | $148.81 | 8.06x | $10,512 |
| 774-7009 REPAIR (QUAD - ELITE) NARROW | 10 LF | $500.00 | $136.65 | 3.66x | $3,634 |
| 770-7036 REPLACE THRIE-BEAM RAIL | 63 LF | $100.00 | $48.04 | 2.08x | $3,274 |
| 770-7026 REPLACE DOWNSTREAM ANCHOR TERMINAL | 3 EA | $1,500.00 | $534.87 | 2.80x | $2,895 |
| 500-7002 MOBILIZATION (CALLOUT) | 50 EA | $1.00 | $600.85 | 0.00x | -$29,992 |
| 451-7049 RETROFIT RAIL (TY T131RC) | 150 LF | $30.00 | $228.58 | 0.13x | -$29,787 |
| 770-7035 REPLACE W-BEAM RAIL | 2,000 LF | $10.00 | $24.10 | 0.41x | -$28,203 |
| 500-7033 MOBILIZATION (EMERGENCY) | 12 EA | $1.00 | $844.81 | 0.00x | -$10,126 |
| 771-7032 REMOVE CABLE BARRIER SYSTEM | 200 LF | $25.00 | $54.08 | 0.46x | -$5,816 |
AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 50 DAY | $7,849.00 | $217.57 | 36.08x | $381,571 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 20 DAY | $250.00 | $87.82 | 2.85x | $3,244 |
| 770-7037 REPLACE GUARDRAIL END TREATMENT SYSTEM | 40 EA | $1,000.00 | $3,116.90 | 0.32x | -$84,676 |
| 500-7002 MOBILIZATION (CALLOUT) | 50 EA | $1.00 | $600.85 | 0.00x | -$29,992 |
| 451-7049 RETROFIT RAIL (TY T131RC) | 150 LF | $38.00 | $228.58 | 0.17x | -$28,587 |
| 500-7033 MOBILIZATION (EMERGENCY) | 12 EA | $1.00 | $844.81 | 0.00x | -$10,126 |
| 771-7032 REMOVE CABLE BARRIER SYSTEM | 200 LF | $5.00 | $54.08 | 0.09x | -$9,816 |