Cable Barrier Repair 09 0726
6502-74-001 · let Jul 8, 2026 · Ellis, Dallas · Routine Maintenance Project - Sealed
$740,750Low bid: AUSTIN BARRICADE COMPANY, L.L.C.+12.7% vs estimate $657,100
$286,100Left on the table38.6% gap to the second bid
3BiddersSpread 73% low to high
8Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | AUSTIN BARRICADE COMPANY, L.L.C. | $740,750 | 12.7% | $286,100 | 1+$4,773 | 3-$64,814 | |
| 2 | E.V.G. ENTERPRISE | $1,026,850 | +38.6% | 56.3% | $255,200 | 1+$35,119 | 1-$149,962 |
| 3 | MARCOM'S MOWING SERVICE, LLC | $1,282,050 | +73.1% | 95.1% | 4+$604,597 | 2-$182,448 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
AUSTIN BARRICADE COMPANY, L.L.C. vs E.V.G. ENTERPRISE, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 771-7025 REPLACE LINE OR TERMINAL POST (VALTIR) | 2,250 EA | $175.00 | $300.00 | $215.97 | $281,250 |
| 500-7002 MOBILIZATION (CALLOUT) | 250 EA | $600.00 | $1.00 | $600.85 | -$149,750 |
| 771-7026 REPLACE LINE OR TERMINAL POST (GIBRAL) | 790 EA | $225.00 | $300.00 | $176.83 | $59,250 |
| 771-7029 REPLACE CABLE RELEASE POST | 100 EA | $1.00 | $500.00 | $148.81 | $49,900 |
| 505-7001 TMA (STATIONARY) | 150 DAY | $1.00 | $250.00 | $217.57 | $37,350 |
| 771-7030 CHECK AND RE-TENSION CABLE SYSTEM | 70 EA | $100.00 | $300.00 | $350.67 | $14,000 |
| 771-7031 REPLACE CABLE | 1,000 LF | $8.00 | $0.1000 | $3.23 | -$7,900 |
| 771-7033 SPLICE CABLE | 20 EA | $200.00 | $300.00 | $342.77 | $2,000 |
Positive: the low bidder was cheaper on that item. These 8 items account for $286,100 of the $286,100 gap.
AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items
Placed 1E.V.G. ENTERPRISE: unbalanced items
Placed 2MARCOM'S MOWING SERVICE, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7025 REPLACE LINE OR TERMINAL POST (VALTIR) | 2,250 EA | $400.00 | $215.97 | 1.85x | $414,072 |
| 771-7026 REPLACE LINE OR TERMINAL POST (GIBRAL) | 790 EA | $335.00 | $176.83 | 1.89x | $124,954 |
| 771-7030 CHECK AND RE-TENSION CABLE SYSTEM | 70 EA | $1,000.00 | $350.67 | 2.85x | $45,453 |
| 771-7029 REPLACE CABLE RELEASE POST | 100 EA | $350.00 | $148.81 | 2.35x | $20,119 |
| 500-7002 MOBILIZATION (CALLOUT) | 250 EA | $1.00 | $600.85 | 0.00x | -$149,962 |
| 505-7001 TMA (STATIONARY) | 150 DAY | $1.00 | $217.57 | 0.00x | -$32,486 |