US 59 Widening 2712 - Phase 1
0089-07-166 · let Aug 5, 2026 · Wharton, Yoakum · Freeway Operational Improvements
$185,831,780Low bid: WILLIAMS BROTHERS CONSTRUCTION CO., INC.-22.9% vs estimate $241,162,765
$15,395,792Left on the table8.3% gap to the second bid
3BiddersSpread 8% low to high
293Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | $185,831,780 | -22.9% | $15,395,792 | 4+$43,578,679 | 3-$5,709,761 | |
| 2 | WEBBER, LLC | $201,227,572 | +8.3% | -16.6% | -$5,078,566 | 3+$52,621,522 | 5-$16,741,832 |
| 3 | JAMES CONSTRUCTION GROUP, LLC | $196,149,006 | +5.6% | -18.7% | 3+$33,797,375 | 1-$2,472,258 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
WILLIAMS BROTHERS CONSTRUCTION CO., INC. vs WEBBER, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 132-7008 EMBANK (FNL)(DC)(TY C1) | 115,931 CY | $50.00 | $150.00 | $17.39 | $11,593,100 |
| 800-7001 NO. OF WORKING DAYS | 27,405 $/D | $940.00 | $525.00 | $612.55 | -$11,373,075 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 744,615 CY | $13.00 | $5.00 | $13.19 | -$5,956,920 |
| 360-7008 CONC PVMT (CRCP) (14") | 227,535 SY | $60.00 | $85.00 | $95.74 | $5,688,375 |
| 110-7001 EXCAV (ROADWAY) | 330,027 CY | $19.00 | $9.00 | $11.68 | -$3,300,270 |
| 276-7343 CEM TRT(PLNT MX)(CL N)(TY E)(GR 4)(6") | 349,085 SY | $6.00 | $15.30 | $12.63 | $3,246,491 |
| 132-7010 EMBANK (FNL)(DC)(TY C2) | 317,835 CY | $17.00 | $8.00 | $22.38 | -$2,860,515 |
| 247-7196 FL BS (CMP IN PLC)(TY E GR 5)(FNAL POS) | 53,491 CY | $65.00 | $115.00 | $88.48 | $2,674,550 |
| 423-7012 RETAINING WALL (TEMP WALL) | 120,622 SF | $20.00 | $0.7500 | $22.94 | -$2,321,974 |
| 416-7006 DRILL SHAFT (36 IN) | 20,406 LF | $300.00 | $229.00 | $280.58 | -$1,448,826 |
| 360-7004 CONC PVMT (CRCP) (10") | 106,629 SY | $60.00 | $73.00 | $87.39 | $1,386,177 |
| 422-7001 REINF CONC SLAB | 299,688 SF | $20.00 | $23.75 | $24.45 | $1,123,830 |
| 425-7005 PRESTR CONC GIRDER (TX54) | 16,233.66 LF | $125.00 | $192.00 | $215.33 | $1,087,655 |
| 425-7001 PRESTR CONC GIRDER (TX28) | 15,788.52 LF | $100.00 | $165.00 | $217.69 | $1,026,254 |
| 508-7001 CONSTRUCTING DETOURS | 46,179 SY | $150.00 | $130.00 | $83.58 | -$923,580 |
| 100-7002 PREPARING ROW | 278 STA | $66,800.00 | $70,000.00 | $6,072.92 | $889,600 |
| 425-7028 PRESTR CONC BOX BEAM (4B28) | 6,439.5 LF | $140.00 | $265.00 | $189.02 | $804,938 |
| 403-7001 TEMPORARY SPL SHORING | 98,730 SF | $10.00 | $2.25 | $25.56 | -$765,158 |
| 420-7022 CL C CONC (CAP) | 1,138.5 CY | $900.00 | $1,500.00 | $1,543.38 | $683,100 |
| 450-7024 RAIL (TY SSTR) | 23,952.6 LF | $60.00 | $88.00 | $69.92 | $670,673 |
Positive: the low bidder was cheaper on that item. These 20 items account for $1,924,425 of the $15,395,792 gap.
WILLIAMS BROTHERS CONSTRUCTION CO., INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $20,372,874.00 | $523,850.32 | 38.89x | $19,849,024 |
| 100-7002 PREPARING ROW | 278 STA | $66,800.00 | $6,072.92 | 11.00x | $16,882,128 |
| 132-7008 EMBANK (FNL)(DC)(TY C1) | 115,931 CY | $50.00 | $17.39 | 2.88x | $3,780,545 |
| 508-7001 CONSTRUCTING DETOURS | 46,179 SY | $150.00 | $83.58 | 1.79x | $3,066,983 |
| 276-7343 CEM TRT(PLNT MX)(CL N)(TY E)(GR 4)(6") | 349,085 SY | $6.00 | $12.63 | 0.47x | -$2,315,236 |
| 425-7001 PRESTR CONC GIRDER (TX28) | 15,788.52 LF | $100.00 | $217.69 | 0.46x | -$1,858,227 |
| 403-7001 TEMPORARY SPL SHORING | 98,730 SF | $10.00 | $25.56 | 0.39x | -$1,536,298 |
WEBBER, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $20,000,000.00 | $523,850.32 | 38.18x | $19,476,150 |
| 100-7002 PREPARING ROW | 278 STA | $70,000.00 | $6,072.92 | 11.53x | $17,771,728 |
| 132-7008 EMBANK (FNL)(DC)(TY C1) | 115,931 CY | $150.00 | $17.39 | 8.63x | $15,373,645 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 744,615 CY | $5.00 | $13.19 | 0.38x | -$6,099,812 |
| 132-7010 EMBANK (FNL)(DC)(TY C2) | 317,835 CY | $8.00 | $22.38 | 0.36x | -$4,569,991 |
| 423-7012 RETAINING WALL (TEMP WALL) | 120,622 SF | $0.7500 | $22.94 | 0.03x | -$2,677,169 |
| 403-7001 TEMPORARY SPL SHORING | 98,730 SF | $2.25 | $25.56 | 0.09x | -$2,301,456 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 8 EA | $1.00 | $136,676.66 | 0.00x | -$1,093,405 |
JAMES CONSTRUCTION GROUP, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $19,000,000.00 | $523,850.32 | 36.27x | $18,476,150 |
| 132-7008 EMBANK (FNL)(DC)(TY C1) | 115,931 CY | $117.35 | $17.39 | 6.75x | $11,588,498 |
| 100-7002 PREPARING ROW | 278 STA | $19,500.00 | $6,072.92 | 3.21x | $3,732,728 |
| 403-7001 TEMPORARY SPL SHORING | 98,730 SF | $0.5200 | $25.56 | 0.02x | -$2,472,258 |