0140-13-023 IH 10 Truck Parking
0140-13-023 · let Aug 6, 2026 · Crockett, San Angelo · Safety Rest Area
$13,741,321Low bid: RAGLE CONSTRUCTION, INC.-31.3% vs estimate $19,998,295
$2,876,465Left on the table20.9% gap to the second bid
6BiddersSpread 59% low to high
111Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RAGLE CONSTRUCTION, INC. | $13,741,321 | -31.3% | $2,876,465 | 2+$1,727,129 | 0 | |
| 2 | RELMCO, INC. | $16,617,786 | +20.9% | -16.9% | $823,329 | 5+$4,467,785 | 2-$517,344 |
| 3 | ALLEN KELLER COMPANY | $17,441,115 | +26.9% | -12.8% | $257,690 | 7+$4,023,138 | 1-$478,355 |
| 4 | CK NEWBERRY, LLC | $17,698,805 | +28.8% | -11.5% | $3,831,230 | 6+$3,608,625 | 1-$432,323 |
| 5 | A. L. HELMCAMP, INC. | $21,530,035 | +56.7% | 7.7% | $322,904 | 12+$8,183,976 | 0 |
| 6 | FNF CONSTRUCTION, INC. | $21,852,939 | +59.0% | 9.3% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
RAGLE CONSTRUCTION, INC. vs RELMCO, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 360-7003 CONC PVMT (CRCP) (9") | 36,488 SY | $80.00 | $155.00 | $87.77 | $2,736,600 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $100,000.00 | $4,500.00 | $11,585.04 | -$1,146,000 |
| 100-7002 PREPARING ROW | 121 STA | $10,500.00 | $2,500.00 | $6,072.92 | -$968,000 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 70,118 CY | $11.00 | $21.00 | $12.93 | $701,180 |
| 341-7001 D-GR HMA TY-B PG64-22 | 8,087 TON | $135.00 | $189.00 | $97.82 | $436,698 |
| 512-7088 PTB (REMOVE)(SSCB OR CSB)(TY1)OR(STL) | 15,090 LF | $16.30 | $42.00 | $17.41 | $387,813 |
| 168-7001 VEGETATIVE WATERING | 3,133 TGL | $5.00 | $50.00 | $8.43 | $140,985 |
| 110-7001 EXCAV (ROADWAY) | 34,963 CY | $11.00 | $15.00 | $11.68 | $139,852 |
| 500-7001 MOBILIZATION | 1 LS | $1,190,000.00 | $1,300,000.00 | $523,850.32 | $110,000 |
| 341-7006 D-GR HMA TY-B PG70-22 | 1,949 TON | $142.00 | $194.00 | $115.61 | $101,348 |
| 512-7085 PTB (FUR&INST)(SSCB OR CSB)(TY1)OR(STL) | 15,090 LF | $47.00 | $42.00 | $38.28 | -$75,450 |
| 344-7030 SP MIXES SP-C SAC-A PG76-22 | 1,548 TON | $167.00 | $215.00 | $138.38 | $74,304 |
| 466-7176 WINGWALL (PW - 1) (HW=6 FT) | 3 EA | $27,208.00 | $48,075.00 | $29,518.27 | $62,601 |
| 462-7027 CONC BOX CULV (9 FT X 5 FT) | 105 LF | $919.00 | $1,476.50 | $1,063.28 | $58,538 |
| 401-7001 FLOWABLE BACKFILL | 645 CY | $250.00 | $175.00 | $298.77 | -$48,375 |
| 105-7015 RMV (15"-19") TRT/UNTRT BASE & ASPH PAV | 6,385 SY | $10.80 | $5.00 | $17.92 | -$37,033 |
| 462-7070 CONC BOX CULV (7 FT X 3 FT)(EXTEND) | 180 LF | $607.00 | $757.50 | $906.96 | $27,090 |
| 462-7082 CONC BOX CULV (9 FT X 5 FT)(EXTEND) | 171 LF | $930.00 | $772.50 | $1,149.43 | -$26,933 |
| 550-7005 CHAIN LINK FENCE (INSTALL) (8') | 6,422 LF | $54.75 | $58.85 | $61.21 | $26,330 |
| 275-7006 CEMENT TRT (EXIST MATL & NEW BASE)(6") | 36,978 SY | $2.30 | $3.00 | $2.25 | $25,885 |
Positive: the low bidder was cheaper on that item. These 20 items account for $2,727,433 of the $2,876,465 gap.
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 1RELMCO, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 360-7003 CONC PVMT (CRCP) (9") | 36,488 SY | $155.00 | $87.77 | 1.77x | $2,452,979 |
| 500-7001 MOBILIZATION | 1 LS | $1,300,000.00 | $523,850.32 | 2.48x | $776,150 |
| 341-7001 D-GR HMA TY-B PG64-22 | 8,087 TON | $189.00 | $97.82 | 1.93x | $737,333 |
| 512-7088 PTB (REMOVE)(SSCB OR CSB)(TY1)OR(STL) | 15,090 LF | $42.00 | $17.41 | 2.41x | $371,096 |
| 168-7001 VEGETATIVE WATERING | 3,133 TGL | $50.00 | $8.43 | 5.93x | $130,227 |
| 100-7002 PREPARING ROW | 121 STA | $2,500.00 | $6,072.92 | 0.41x | -$432,323 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $4,500.00 | $11,585.04 | 0.39x | -$85,021 |
ALLEN KELLER COMPANY: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7004 EMBANK (FNL)(DC)(TY B) | 70,118 CY | $32.92 | $12.93 | 2.55x | $1,401,953 |
| 500-7001 MOBILIZATION | 1 LS | $1,660,000.67 | $523,850.32 | 3.17x | $1,136,150 |
| 341-7001 D-GR HMA TY-B PG64-22 | 8,087 TON | $191.90 | $97.82 | 1.96x | $760,785 |
| 110-7001 EXCAV (ROADWAY) | 34,963 CY | $21.69 | $11.68 | 1.86x | $349,903 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 5 EA | $45,228.17 | $9,253.78 | 4.89x | $179,872 |
| 168-7001 VEGETATIVE WATERING | 3,133 TGL | $39.90 | $8.43 | 4.73x | $98,584 |
| 416-7040 DRILL SHAFT (RDWY ILL POLE) (30 IN) | 424 LF | $497.00 | $270.84 | 1.84x | $95,891 |
| 100-7002 PREPARING ROW | 121 STA | $2,119.57 | $6,072.92 | 0.35x | -$478,355 |
CK NEWBERRY, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,750,000.00 | $523,850.32 | 3.34x | $1,226,150 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 70,118 CY | $25.00 | $12.93 | 1.93x | $846,619 |
| 512-7088 PTB (REMOVE)(SSCB OR CSB)(TY1)OR(STL) | 15,090 LF | $60.00 | $17.41 | 3.45x | $642,716 |
| 512-7085 PTB (FUR&INST)(SSCB OR CSB)(TY1)OR(STL) | 15,090 LF | $75.00 | $38.28 | 1.96x | $554,088 |
| 462-7082 CONC BOX CULV (9 FT X 5 FT)(EXTEND) | 171 LF | $2,250.00 | $1,149.43 | 1.96x | $188,197 |
| 462-7027 CONC BOX CULV (9 FT X 5 FT) | 105 LF | $2,500.00 | $1,063.28 | 2.35x | $150,855 |
| 100-7002 PREPARING ROW | 121 STA | $2,500.00 | $6,072.92 | 0.41x | -$432,323 |
A. L. HELMCAMP, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 360-7003 CONC PVMT (CRCP) (9") | 36,488 SY | $172.00 | $87.77 | 1.96x | $3,073,275 |
| 500-7001 MOBILIZATION | 1 LS | $1,900,000.00 | $523,850.32 | 3.63x | $1,376,150 |
| 512-7085 PTB (FUR&INST)(SSCB OR CSB)(TY1)OR(STL) | 15,090 LF | $105.00 | $38.28 | 2.74x | $1,006,788 |
| 512-7088 PTB (REMOVE)(SSCB OR CSB)(TY1)OR(STL) | 15,090 LF | $68.00 | $17.41 | 3.91x | $763,436 |
| 341-7001 D-GR HMA TY-B PG64-22 | 8,087 TON | $192.00 | $97.82 | 1.96x | $761,594 |
| 341-7006 D-GR HMA TY-B PG70-22 | 1,949 TON | $238.00 | $115.61 | 2.06x | $238,534 |
| 466-7176 WINGWALL (PW - 1) (HW=6 FT) | 3 EA | $95,000.00 | $29,518.27 | 3.22x | $196,445 |
| 344-7030 SP MIXES SP-C SAC-A PG76-22 | 1,548 TON | $255.00 | $138.38 | 1.84x | $180,521 |
| 462-7082 CONC BOX CULV (9 FT X 5 FT)(EXTEND) | 171 LF | $2,200.00 | $1,149.43 | 1.91x | $179,647 |
| 275-7006 CEMENT TRT (EXIST MATL & NEW BASE)(6") | 36,978 SY | $6.20 | $2.25 | 2.76x | $146,244 |