Bid Tab X-ray: 6506-64-001

Aug 13, 2026 · Howard Sign up free
Set your company to personalize scores

ABL - West HMA

6506-64-001 · let Aug 13, 2026 · Howard, Abilene · Material Maintenance Project

$810,713Low bid: RK HALL, LLC+1.6% vs estimate $798,075
$183,450Left on the table22.6% gap to the second bid
2BiddersSpread 23% low to high
8Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1RK HALL, LLC $810,7131.6% $183,450 0 0
2VULCAN CONSTRUCTION MATERIALS, LLC $994,162+22.6%24.6% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.

Where the job was won

RK HALL, LLC vs VULCAN CONSTRUCTION MATERIALS, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
8011-7061 D-GR HMA TY D PG 64-22 (DEL) SITE 63,500 TON $102.50$140.12$93.49 $131,670
8011-7067 D-GR HMA TY D PG 64-22 (DEL) SITE 122,000 TON $118.00$130.20$124.08 $24,400
8011-7062 D-GR HMA TY D PG 64-22 (DEL) SITE 71,200 TON $111.50$126.17$90.71 $17,604
8011-7063 D-GR HMA TY D PG 64-22 (DEL) SITE 8500 TON $111.50$137.64$84.86 $13,070
8011-7013 D-GR HMA TY B PG 64-22 (DEL) SITE 12100 TON $155.00$130.20$155.00 -$2,480
8011-7008 D-GR HMA TY B PG 64-22 (DEL) SITE 725 TON $148.50$126.17$72.55 -$558
8011-7009 D-GR HMA TY B PG 64-22 (DEL) SITE 825 TON $148.50$137.64$77.94 -$272
8011-7007 D-GR HMA TY B PG 64-22 (DEL) SITE 625 TON $139.50$140.12$81.87 $16

Positive: the low bidder was cheaper on that item. These 8 items account for $183,450 of the $183,450 gap.