ABL - West HMA
6506-64-001 · let Aug 13, 2026 · Howard, Abilene · Material Maintenance Project
$810,713Low bid: RK HALL, LLC+1.6% vs estimate $798,075
$183,450Left on the table22.6% gap to the second bid
2BiddersSpread 23% low to high
8Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RK HALL, LLC | $810,713 | 1.6% | $183,450 | 0 | 0 | |
| 2 | VULCAN CONSTRUCTION MATERIALS, LLC | $994,162 | +22.6% | 24.6% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
RK HALL, LLC vs VULCAN CONSTRUCTION MATERIALS, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8011-7061 D-GR HMA TY D PG 64-22 (DEL) SITE 6 | 3,500 TON | $102.50 | $140.12 | $93.49 | $131,670 |
| 8011-7067 D-GR HMA TY D PG 64-22 (DEL) SITE 12 | 2,000 TON | $118.00 | $130.20 | $124.08 | $24,400 |
| 8011-7062 D-GR HMA TY D PG 64-22 (DEL) SITE 7 | 1,200 TON | $111.50 | $126.17 | $90.71 | $17,604 |
| 8011-7063 D-GR HMA TY D PG 64-22 (DEL) SITE 8 | 500 TON | $111.50 | $137.64 | $84.86 | $13,070 |
| 8011-7013 D-GR HMA TY B PG 64-22 (DEL) SITE 12 | 100 TON | $155.00 | $130.20 | $155.00 | -$2,480 |
| 8011-7008 D-GR HMA TY B PG 64-22 (DEL) SITE 7 | 25 TON | $148.50 | $126.17 | $72.55 | -$558 |
| 8011-7009 D-GR HMA TY B PG 64-22 (DEL) SITE 8 | 25 TON | $148.50 | $137.64 | $77.94 | -$272 |
| 8011-7007 D-GR HMA TY B PG 64-22 (DEL) SITE 6 | 25 TON | $139.50 | $140.12 | $81.87 | $16 |
Positive: the low bidder was cheaper on that item. These 8 items account for $183,450 of the $183,450 gap.