FY 27 Amarillo District Flexbase
6505-52-001 · let Aug 5, 2026 · Dallam, Amarillo · Material Maintenance Project
$1,230,475Low bid: HOLMES CONSTRUCTION CO., L.P.+5.3% vs estimate $1,168,567
$123,275Left on the table10.0% gap to the second bid
4BiddersSpread 12% low to high
16Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HOLMES CONSTRUCTION CO., L.P. | $1,230,475 | 5.3% | $123,275 | 0 | 0 | |
| 2 | TOUCHSTONE RESOURCES, LLC | $1,353,750 | +10.0% | 15.8% | $24,220 | 0 | 0 |
| 3 | HOWELL SAND COMPANY, INC. | $1,377,970 | +12.0% | 17.9% | $3,103 | 0 | 0 |
| 4 | J. LEE MILLIGAN, INC. | $1,381,073 | +12.2% | 18.2% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
HOLMES CONSTRUCTION CO., L.P. vs TOUCHSTONE RESOURCES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8010-7225 FL BS(TY D GR 4)(DEL)(ST15) | 7,000 TON | $43.26 | $50.00 | $39.26 | $47,180 |
| 8010-7216 FL BS(TY D GR 4)(DEL)(ST6) | 6,500 TON | $35.99 | $41.00 | $39.85 | $32,565 |
| 8010-7224 FL BS(TY D GR 4)(DEL)(ST14) | 3,000 TON | $49.08 | $55.00 | $48.57 | $17,760 |
| 8010-7219 FL BS(TY D GR 4)(DEL)(ST9) | 1,000 TON | $37.45 | $44.00 | $36.78 | $6,550 |
| 8010-7218 FL BS(TY D GR 4)(DEL)(ST8) | 500 TON | $37.45 | $50.00 | $39.42 | $6,275 |
| 8010-7214 FL BS(TY D GR 4)(DEL)(ST4) | 2,000 TON | $49.08 | $52.00 | $50.10 | $5,840 |
| 8010-7228 FL BS(TY D GR 4)(DEL)(ST18) | 2,000 TON | $37.45 | $40.00 | $34.04 | $5,100 |
| 8010-7217 FL BS(TY D GR 4)(DEL)(ST7) | 3,000 TON | $35.99 | $35.00 | $34.20 | -$2,970 |
| 8010-7222 FL BS(TY D GR 4)(DEL)(ST12) | 1,500 TON | $40.35 | $42.00 | $41.42 | $2,475 |
| 8010-7220 FL BS(TY D GR 4)(DEL)(ST10) | 400 TON | $46.17 | $50.00 | $45.88 | $1,532 |
| 8010-7215 FL BS(TY D GR 4)(DEL)(ST5) | 1,000 TON | $31.63 | $33.00 | $39.75 | $1,370 |
| 8010-7213 FL BS(TY D GR 4)(DEL)(ST3) | 2,000 TON | $37.45 | $37.00 | $35.68 | -$900 |
| 8010-7221 FL BS(TY D GR 4)(DEL)(ST11) | 250 TON | $37.45 | $40.00 | $40.34 | $637 |
| 8010-7211 FL BS(TY D GR 4)(DEL)(ST1) | 50 TON | $28.93 | $33.00 | $28.09 | $204 |
| 8010-7226 FL BS(TY D GR 4)(DEL)(ST16) | 300 TON | $31.63 | $31.00 | $36.52 | -$189 |
| 8010-7223 FL BS(TY D GR 4)(DEL)(ST13) | 100 TON | $34.54 | $33.00 | $29.69 | -$154 |
Positive: the low bidder was cheaper on that item. These 16 items account for $123,275 of the $123,275 gap.