6505-09-001 Cleaning & Sealing Cracks
6505-09-001 · let Aug 11, 2026 · Midland, Odessa · Routine Maintenance Project
$452,636Low bid: SCOUT 5 CONSTRUCTION LLC-8.9% vs estimate $496,710
$91,921Left on the table20.3% gap to the second bid
5BiddersSpread 134% low to high
5Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SCOUT 5 CONSTRUCTION LLC | $452,636 | -8.9% | $91,921 | 0 | 3-$557,679 | |
| 2 | FYL ENTERPRISES, LLC | $544,557 | +20.3% | 9.6% | $103,274 | 0 | 3-$481,376 |
| 3 | GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY | $647,831 | +43.1% | 30.4% | $179,771 | 0 | 3-$558,812 |
| 4 | CRACKSEAL OF TEXAS, LLC | $827,602 | +82.8% | 66.6% | $230,300 | 0 | 3-$469,778 |
| 5 | D & M CONTRACTORS, LLC | $1,057,902 | +133.7% | 113.0% | 1+$445,870 | 3-$374,148 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
SCOUT 5 CONSTRUCTION LLC vs FYL ENTERPRISES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,700.00 | $80,000.00 | $523,850.32 | $76,300 |
| 712-7001 JT / CRCK SEAL (RUBBER - ASPHALT) | 489 LMI | $915.00 | $950.00 | $868.20 | $17,115 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 5 DAY | $300.00 | $0.5000 | $87.82 | -$1,498 |
| 505-7001 TMA (STATIONARY) | 66 DAY | $0.0100 | $0.0550 | $217.57 | $3 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $0.0100 | $0.5000 | $11,585.04 | $1 |
Positive: the low bidder was cheaper on that item. These 5 items account for $91,921 of the $91,921 gap.
SCOUT 5 CONSTRUCTION LLC: unbalanced items
Placed 1FYL ENTERPRISES, LLC: unbalanced items
Placed 2GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY: unbalanced items
Placed 3CRACKSEAL OF TEXAS, LLC: unbalanced items
Placed 4D & M CONTRACTORS, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 712-7001 JT / CRCK SEAL (RUBBER - ASPHALT) | 489 LMI | $1,780.00 | $868.20 | 2.05x | $445,870 |
| 500-7001 MOBILIZATION | 1 LS | $187,000.00 | $523,850.32 | 0.36x | -$336,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $50.00 | $11,585.04 | 0.00x | -$23,070 |
| 505-7001 TMA (STATIONARY) | 66 DAY | $2.00 | $217.57 | 0.01x | -$14,228 |