6504-95-001 Crack Seal
6504-95-001 · let Aug 11, 2026 · Ector, Odessa · Routine Maintenance Project - Sealed
$484,960Low bid: GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY-4.6% vs estimate $508,120
$2,550Left on the table0.5% gap to the second bid
5BiddersSpread 140% low to high
5Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY | $484,960 | -4.6% | $2,550 | 0 | 3-$549,483 | |
| 2 | SCOUT 5 CONSTRUCTION LLC | $487,510 | +0.5% | -4.1% | $102,546 | 0 | 3-$548,107 |
| 3 | FYL ENTERPRISES, LLC | $590,056 | +21.7% | 16.1% | $312,514 | 0 | 3-$471,806 |
| 4 | CRACKSEAL OF TEXAS, LLC | $902,570 | +86.1% | 77.6% | $261,094 | 1+$9,824 | 2-$462,000 |
| 5 | D & M CONTRACTORS, LLC | $1,163,664 | +140.0% | 129.0% | 1+$500,284 | 2-$349,920 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY vs SCOUT 5 CONSTRUCTION LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,300.00 | $3,700.00 | $523,850.32 | $1,400 |
| 712-7001 JT / CRCK SEAL (RUBBER - ASPHALT) | 536.9 LMI | $898.00 | $900.00 | $868.20 | $1,074 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 2 DAY | $250.00 | $300.00 | $87.82 | $100 |
| 505-7001 TMA (STATIONARY) | 22 DAY | $1.00 | $0.0100 | $217.57 | -$22 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $1.00 | $0.0100 | $11,585.04 | -$2 |
Positive: the low bidder was cheaper on that item. These 5 items account for $2,550 of the $2,550 gap.