Bid Tab X-ray: 6504-47-001

Aug 12, 2026 · Brazos Sign up free
Set your company to personalize scores

FY27 - District Cross Drainage -08

6504-47-001 · let Aug 12, 2026 · Brazos, Bryan · Routine Maintenance Project

$362,100Low bid: GARRET SHIELDS INFRASTRUCTURE-14.9% vs estimate $425,370
$99,250Left on the table27.4% gap to the second bid
4BiddersSpread 89% low to high
34Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1GARRET SHIELDS INFRASTRUCTURE $362,100-14.9% $99,250 2+$6,567 0
2CEDAR HILL SERVICES, LLC $461,350+27.4%8.5% $117,712 4+$74,015 1-$2,641
3DIGG COMMERCIAL, LLC $579,062+59.9%36.1% $104,328 5+$196,735 0
4CROSS PLUS CONSTRUCTION, LLC $683,390+88.7%60.7% 11+$311,422 1-$5,585

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.

Where the job was won

GARRET SHIELDS INFRASTRUCTURE vs CEDAR HILL SERVICES, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
500-7002 MOBILIZATION (CALLOUT)6 EA $1,000.00$7,500.00$600.85 $39,000
530-7015 DRIVEWAYS (BASE)400 SY $30.00$80.00$27.85 $20,000
401-7001 FLOWABLE BACKFILL50 CY $200.00$480.00$298.77 $14,000
400-7006 CUT & RESTORING PAV300 SY $140.00$180.00$171.81 $12,000
400-7010 CEM STABIL BKFL400 CY $200.00$175.00$138.14 -$10,000
496-7007 REMOV STR (PIPE)400 LF $20.00$40.00$23.96 $8,000
464-7013 RC PIPE (CL III)(60 IN)40 LF $300.00$480.00$372.18 $7,200
467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P)4 EA $1,800.00$3,500.00$1,883.43 $6,800
132-7011 EMBANK (FNL)(OC)(TY D)250 CY $50.00$25.00$32.39 -$6,250
467-7326 SET (TY II) (24 IN) (RCP) (4: 1) (C)4 EA $1,800.00$3,200.00$2,065.28 $5,600
467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P)4 EA $1,200.00$2,500.00$1,176.76 $5,200
403-7001 TEMPORARY SPL SHORING100 SF $50.00$10.00$25.56 -$4,000
467-7306 SET (TY II) (18 IN) (RCP) (4: 1) (C)4 EA $1,200.00$2,000.00$1,482.25 $3,200
467-7366 SET (TY II) (36 IN) (RCP) (4: 1) (C)4 EA $3,500.00$4,300.00$4,173.90 $3,200
110-7004 EXCAV (ROADWAY & CHANNEL)600 CY $30.00$25.00$24.59 -$3,000
464-7003 RC PIPE (CL III)(18 IN)50 LF $80.00$130.00$83.08 $2,500
464-7005 RC PIPE (CL III)(24 IN)100 LF $120.00$145.00$108.34 $2,500
496-7004 REMOV STR (SET)10 EA $500.00$250.00$514.07 -$2,500
505-7001 TMA (STATIONARY)50 DAY $300.00$250.00$217.57 -$2,500
247-7136 FL BS (CMP IN PLACE)(TYA GR1-2)(IN VEH)400 CY $60.00$65.00$54.60 $2,000

Positive: the low bidder was cheaper on that item. These 20 items account for $102,950 of the $99,250 gap.

GARRET SHIELDS INFRASTRUCTURE: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
472-7011 REMOV & RE - LAY PIPE (36 IN)10 LF $400.00$56.587.07x$3,434
472-7013 REMOV & RE - LAY PIPE (48 IN)10 LF $500.00$186.692.68x$3,133

CEDAR HILL SERVICES, LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
500-7002 MOBILIZATION (CALLOUT)6 EA $7,500.00$600.8512.48x$41,395
530-7015 DRIVEWAYS (BASE)400 SY $80.00$27.852.87x$20,861
467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P)4 EA $3,500.00$1,883.431.86x$6,466
467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P)4 EA $2,500.00$1,176.762.12x$5,293
496-7004 REMOV STR (SET)10 EA $250.00$514.070.49x-$2,641

DIGG COMMERCIAL, LLC: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
505-7001 TMA (STATIONARY)50 DAY $3,500.00$217.5716.09x$164,121
247-7136 FL BS (CMP IN PLACE)(TYA GR1-2)(IN VEH)400 CY $100.00$54.601.83x$18,161
467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P)4 EA $3,500.00$1,883.431.86x$6,466
403-7001 TEMPORARY SPL SHORING100 SF $75.00$25.562.93x$4,944
506-7039 TEMP SEDMT CONT FENCE (INSTALL)500 LF $10.00$3.922.55x$3,042

CROSS PLUS CONSTRUCTION, LLC: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
400-7010 CEM STABIL BKFL400 CY $400.00$138.142.90x$104,743
400-7006 CUT & RESTORING PAV300 SY $400.00$171.812.33x$68,457
500-7002 MOBILIZATION (CALLOUT)6 EA $5,000.00$600.858.32x$26,395
530-7015 DRIVEWAYS (BASE)400 SY $90.00$27.853.23x$24,861
480-7002 CLEAN EXIST CULVERTS20 CY $1,000.00$42.8623.33x$19,143
110-7004 EXCAV (ROADWAY & CHANNEL)600 CY $55.00$24.592.24x$18,248
505-7001 TMA (STATIONARY)50 DAY $500.00$217.572.30x$14,121
403-7001 TEMPORARY SPL SHORING100 SF $150.00$25.565.87x$12,444
402-7001 TRENCH EXCAVATION PROTECTION20 LF $500.00$5.9683.91x$9,881
464-7011 RC PIPE (CL III)(48 IN)40 LF $451.00$255.071.77x$7,837
496-7007 REMOV STR (PIPE)400 LF $10.00$23.960.42x-$5,585