FY27 - District Cross Drainage -08
6504-47-001 · let Aug 12, 2026 · Brazos, Bryan · Routine Maintenance Project
$362,100Low bid: GARRET SHIELDS INFRASTRUCTURE-14.9% vs estimate $425,370
$99,250Left on the table27.4% gap to the second bid
4BiddersSpread 89% low to high
34Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | GARRET SHIELDS INFRASTRUCTURE | $362,100 | -14.9% | $99,250 | 2+$6,567 | 0 | |
| 2 | CEDAR HILL SERVICES, LLC | $461,350 | +27.4% | 8.5% | $117,712 | 4+$74,015 | 1-$2,641 |
| 3 | DIGG COMMERCIAL, LLC | $579,062 | +59.9% | 36.1% | $104,328 | 5+$196,735 | 0 |
| 4 | CROSS PLUS CONSTRUCTION, LLC | $683,390 | +88.7% | 60.7% | 11+$311,422 | 1-$5,585 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
GARRET SHIELDS INFRASTRUCTURE vs CEDAR HILL SERVICES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $1,000.00 | $7,500.00 | $600.85 | $39,000 |
| 530-7015 DRIVEWAYS (BASE) | 400 SY | $30.00 | $80.00 | $27.85 | $20,000 |
| 401-7001 FLOWABLE BACKFILL | 50 CY | $200.00 | $480.00 | $298.77 | $14,000 |
| 400-7006 CUT & RESTORING PAV | 300 SY | $140.00 | $180.00 | $171.81 | $12,000 |
| 400-7010 CEM STABIL BKFL | 400 CY | $200.00 | $175.00 | $138.14 | -$10,000 |
| 496-7007 REMOV STR (PIPE) | 400 LF | $20.00 | $40.00 | $23.96 | $8,000 |
| 464-7013 RC PIPE (CL III)(60 IN) | 40 LF | $300.00 | $480.00 | $372.18 | $7,200 |
| 467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P) | 4 EA | $1,800.00 | $3,500.00 | $1,883.43 | $6,800 |
| 132-7011 EMBANK (FNL)(OC)(TY D) | 250 CY | $50.00 | $25.00 | $32.39 | -$6,250 |
| 467-7326 SET (TY II) (24 IN) (RCP) (4: 1) (C) | 4 EA | $1,800.00 | $3,200.00 | $2,065.28 | $5,600 |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 4 EA | $1,200.00 | $2,500.00 | $1,176.76 | $5,200 |
| 403-7001 TEMPORARY SPL SHORING | 100 SF | $50.00 | $10.00 | $25.56 | -$4,000 |
| 467-7306 SET (TY II) (18 IN) (RCP) (4: 1) (C) | 4 EA | $1,200.00 | $2,000.00 | $1,482.25 | $3,200 |
| 467-7366 SET (TY II) (36 IN) (RCP) (4: 1) (C) | 4 EA | $3,500.00 | $4,300.00 | $4,173.90 | $3,200 |
| 110-7004 EXCAV (ROADWAY & CHANNEL) | 600 CY | $30.00 | $25.00 | $24.59 | -$3,000 |
| 464-7003 RC PIPE (CL III)(18 IN) | 50 LF | $80.00 | $130.00 | $83.08 | $2,500 |
| 464-7005 RC PIPE (CL III)(24 IN) | 100 LF | $120.00 | $145.00 | $108.34 | $2,500 |
| 496-7004 REMOV STR (SET) | 10 EA | $500.00 | $250.00 | $514.07 | -$2,500 |
| 505-7001 TMA (STATIONARY) | 50 DAY | $300.00 | $250.00 | $217.57 | -$2,500 |
| 247-7136 FL BS (CMP IN PLACE)(TYA GR1-2)(IN VEH) | 400 CY | $60.00 | $65.00 | $54.60 | $2,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for $102,950 of the $99,250 gap.
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 1CEDAR HILL SERVICES, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $7,500.00 | $600.85 | 12.48x | $41,395 |
| 530-7015 DRIVEWAYS (BASE) | 400 SY | $80.00 | $27.85 | 2.87x | $20,861 |
| 467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P) | 4 EA | $3,500.00 | $1,883.43 | 1.86x | $6,466 |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 4 EA | $2,500.00 | $1,176.76 | 2.12x | $5,293 |
| 496-7004 REMOV STR (SET) | 10 EA | $250.00 | $514.07 | 0.49x | -$2,641 |
DIGG COMMERCIAL, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 50 DAY | $3,500.00 | $217.57 | 16.09x | $164,121 |
| 247-7136 FL BS (CMP IN PLACE)(TYA GR1-2)(IN VEH) | 400 CY | $100.00 | $54.60 | 1.83x | $18,161 |
| 467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P) | 4 EA | $3,500.00 | $1,883.43 | 1.86x | $6,466 |
| 403-7001 TEMPORARY SPL SHORING | 100 SF | $75.00 | $25.56 | 2.93x | $4,944 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 500 LF | $10.00 | $3.92 | 2.55x | $3,042 |
CROSS PLUS CONSTRUCTION, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 400-7010 CEM STABIL BKFL | 400 CY | $400.00 | $138.14 | 2.90x | $104,743 |
| 400-7006 CUT & RESTORING PAV | 300 SY | $400.00 | $171.81 | 2.33x | $68,457 |
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $5,000.00 | $600.85 | 8.32x | $26,395 |
| 530-7015 DRIVEWAYS (BASE) | 400 SY | $90.00 | $27.85 | 3.23x | $24,861 |
| 480-7002 CLEAN EXIST CULVERTS | 20 CY | $1,000.00 | $42.86 | 23.33x | $19,143 |
| 110-7004 EXCAV (ROADWAY & CHANNEL) | 600 CY | $55.00 | $24.59 | 2.24x | $18,248 |
| 505-7001 TMA (STATIONARY) | 50 DAY | $500.00 | $217.57 | 2.30x | $14,121 |
| 403-7001 TEMPORARY SPL SHORING | 100 SF | $150.00 | $25.56 | 5.87x | $12,444 |
| 402-7001 TRENCH EXCAVATION PROTECTION | 20 LF | $500.00 | $5.96 | 83.91x | $9,881 |
| 464-7011 RC PIPE (CL III)(48 IN) | 40 LF | $451.00 | $255.07 | 1.77x | $7,837 |
| 496-7007 REMOV STR (PIPE) | 400 LF | $10.00 | $23.96 | 0.42x | -$5,585 |