MBGF Collin 08-26
6504-18-001 · let Aug 12, 2026 · Collin, Dallas · Routine Maintenance Project - Sealed
$451,805Low bid: MARCOM'S MOWING SERVICE, LLC-41.5% vs estimate $771,975
$14,500Left on the table3.2% gap to the second bid
4BiddersSpread 88% low to high
10Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | MARCOM'S MOWING SERVICE, LLC | $451,805 | -41.5% | $14,500 | 1+$169,915 | 5-$128,277 | |
| 2 | FIREMAN EXCAVATING, INC. | $466,305 | +3.2% | -39.6% | $58,905 | 1+$232,986 | 4-$265,108 |
| 3 | AUSTIN BARRICADE COMPANY, L.L.C. | $525,210 | +16.2% | -32.0% | $324,790 | 1+$189,915 | 4-$155,626 |
| 4 | SYNERGY SIGNS & SERVICES LLC | $850,000 | +88.1% | 10.1% | 7+$242,507 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
MARCOM'S MOWING SERVICE, LLC vs FIREMAN EXCAVATING, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 770-7037 REPLACE GUARDRAIL END TREATMENT SYSTEM | 60 EA | $1,500.00 | $7,000.00 | $3,116.90 | $330,000 |
| 500-7002 MOBILIZATION (CALLOUT) | 100 EA | $2,300.00 | $1.00 | $600.85 | -$229,900 |
| 770-7035 REPLACE W-BEAM RAIL | 9,000 LF | $14.00 | $4.00 | $24.10 | -$90,000 |
| 658-7018 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2 | 100 EA | $1.00 | $20.00 | $35.16 | $1,900 |
| 658-7036 INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2 | 100 EA | $1.00 | $20.00 | $37.39 | $1,900 |
| 770-7038 REPLACE CURVED RAIL | 60 LF | $50.00 | $60.00 | $26.19 | $600 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 5 DAY | $1.00 | $1.00 | $87.82 | $0 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $1.00 | $217.57 | $0 |
| 658-7019 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | 100 EA | $1.00 | $1.00 | $26.51 | $0 |
| 770-7036 REPLACE THRIE-BEAM RAIL | 48 LF | $50.00 | $50.00 | $48.04 | $0 |
Positive: the low bidder was cheaper on that item. These 10 items account for $14,500 of the $14,500 gap.
MARCOM'S MOWING SERVICE, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 100 EA | $2,300.00 | $600.85 | 3.83x | $169,915 |
| 770-7037 REPLACE GUARDRAIL END TREATMENT SYSTEM | 60 EA | $1,500.00 | $3,116.90 | 0.48x | -$97,014 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $217.57 | 0.00x | -$21,657 |
| 658-7036 INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2 | 100 EA | $1.00 | $37.39 | 0.03x | -$3,639 |
| 658-7018 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2 | 100 EA | $1.00 | $35.16 | 0.03x | -$3,416 |
| 658-7019 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | 100 EA | $1.00 | $26.51 | 0.04x | -$2,551 |
FIREMAN EXCAVATING, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 770-7037 REPLACE GUARDRAIL END TREATMENT SYSTEM | 60 EA | $7,000.00 | $3,116.90 | 2.25x | $232,986 |
| 770-7035 REPLACE W-BEAM RAIL | 9,000 LF | $4.00 | $24.10 | 0.17x | -$180,914 |
| 500-7002 MOBILIZATION (CALLOUT) | 100 EA | $1.00 | $600.85 | 0.00x | -$59,985 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $217.57 | 0.00x | -$21,657 |
| 658-7019 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | 100 EA | $1.00 | $26.51 | 0.04x | -$2,551 |
AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 100 EA | $2,500.00 | $600.85 | 4.16x | $189,915 |
| 770-7035 REPLACE W-BEAM RAIL | 9,000 LF | $10.00 | $24.10 | 0.41x | -$126,914 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $217.57 | 0.00x | -$21,657 |
| 658-7036 INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2 | 100 EA | $1.00 | $37.39 | 0.03x | -$3,639 |
| 658-7018 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2 | 100 EA | $1.00 | $35.16 | 0.03x | -$3,416 |
SYNERGY SIGNS & SERVICES LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 100 EA | $2,000.00 | $600.85 | 3.33x | $139,915 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $500.00 | $217.57 | 2.30x | $28,243 |
| 658-7019 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | 100 EA | $250.00 | $26.51 | 9.43x | $22,349 |
| 658-7036 INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2 | 100 EA | $250.00 | $37.39 | 6.69x | $21,261 |
| 658-7018 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2 | 100 EA | $200.00 | $35.16 | 5.69x | $16,484 |
| 770-7036 REPLACE THRIE-BEAM RAIL | 48 LF | $250.00 | $48.04 | 5.20x | $9,694 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 5 DAY | $1,000.00 | $87.82 | 11.39x | $4,561 |