Bid Tab X-ray: 6503-79-001

Aug 20, 2026 · Parker Sign up free
Set your company to personalize scores

FY '27 Parker MMC Brine Solution

6503-79-001 · let Aug 20, 2026 · Parker, Fort Worth · Material Maintenance Project

$273,000Low bid: NSG LOGISTICS, LLC-5.9% vs estimate $290,000
$13,850Left on the table5.1% gap to the second bid
3BiddersSpread 11% low to high
4Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1NSG LOGISTICS, LLC $273,000-5.9% $13,850 0 0
2CLEMENTS FLUIDS BUFFALO, LTD. $286,850+5.1%-1.1% $15,650 0 0
3TOUCHSTONE RESOURCES, LLC $302,500+10.8%4.3% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.

Where the job was won

NSG LOGISTICS, LLC vs CLEMENTS FLUIDS BUFFALO, LTD., biggest item swings
ItemQtyLow2ndMarket2nd minus low
8032-7572 BRINE SOLUTION (DEL)(SITE 1)250,000 GAL $0.5000$0.5230$0.4203 $5,750
8032-7573 BRINE SOLUTION (DEL)(SITE 2)100,000 GAL $0.5200$0.5580$0.4172 $3,800
8032-7574 BRINE SOLUTION (DEL)(SITE 3)100,000 GAL $0.4700$0.4930$0.4280 $2,300
8032-7575 BRINE SOLUTION (DEL)(SITE 4)100,000 GAL $0.4900$0.5100$0.4158 $2,000

Positive: the low bidder was cheaper on that item. These 4 items account for $13,850 of the $13,850 gap.